In the moneh application software application for working people, stay-

at-home moms, and anyone who doesn't have enough time to do the
shopping , this project will start at December 2022 and end at May 2023
that means it take 6 months.

the total budget of 2000$. We 've planned to spend 200$ in the first
three months and We 've planned to spend 1000$ in the second three
months, We 've planned to spend 800$ in the third three months.

i had planned to complete 50% of the work by the end of 3 months, the
Planned Value for the project at this point:

PV = Budgeted Cost of Work Scheduled (BCWS)


= 50% of Total Budget = $1,000

But actually I hah   spent $1100 in the first 3 months . the Actual Cost
(AC) of the project at this point.

AC = Actual Cost of Work Performed (ACWP) = 1100$

the team has completed only 40% of the work that was planned to be
completed by the end of 3 months

EV = Budgeted Cost of Work Performed (BCWP)


= 40% of Total Budget = $800
So PV = $1,000
AC = $1100
EV = $800

(SV) = EV – PV = 800$ - 1000$= -200$


the project is behind schedule

(CV) = EV - AC = 800$ - 1100$ = -300$


the project is over budget

(SPI) = EV / PV = $800 / $1000 = 0.8


is behind schedule.

(CPI) = EV / AC = $800 / $1100= 0.72


project is over budget.