You are on page 1of 9

1. If a project has a To Complete Performance Index (TCPI) of 0.

80, this means that:

a. The project can spend money at a rate 12% higher than planned and still meet the
project budget (Correct)
b. 90% of the budget planned up to today has been spent
c. 90% of the work planned up to today has been completed
d. The project can spend money at a rate 8% lower than planned to meet the project
budget

Solution: 1 Mark.

The project can spend money at a rate 12% higher than planned and still meet the project budget.
The To Complete Performance Index (TCPI) is the efficiency needed to finish the project on budget. If
it is smaller than 1, that means that we have more money left on the budget than the remaining
Planned Value (PV) to achieve. Therefore, in theory, we can spend more money yet can still finish
the project on budget. (However, in reality, it is generally preferred to finish the project under
budget. A TCPI smaller than 1 is a good sign that the project is going healthy.)

e. Planned Value (PV)


f. Earned Value (EV)
g. Estimate at Completion (EAC)

Solution: 1 Mark.

Estimate to Complete (ETC). By definition, Estimate to Completion (ETC) is the amount of money we
need to put into the project from today in order to complete it.

Solution: 1 Mark.

Planned Value (PV). Planned Value (PV) is how much value of work was scheduled to achieve to
date.
EVM Estimate At Completion (EAC) Questions.

Since there are multiple Estimate at Completion (EAC) formulas, scholars should be able to get clues
from the questions on which EAC formula to use (Please write them down somewhere before
attempting any questions, in exam however you will be expected to memorize all formulas:

EAC = BAC/CPI
If we believe the project will continue to spend at the same rate up to now (e.g. the delay is caused
by reasons which is likely to continue)

EAC = AC + (BAC-EV)
If we believe that future expenditures will occur at the original forecasted amount (no more delays
of the same kind in future)

EAC = AC + [(BAC-EV)/(SPI*CPI)]
If we believe that both current cost and current schedule performance will impact future cost
performance

EAC = AC + New Estimate


If we believe the original conditions and assumptions are wrong

2. For the project with original project budget $1000 and both the Cost Performance Index
(CPI) and Schedule Performance Index (SPI) equal 1. Assuming the project will continue to
spend money at the same rate, what is the Estimate At Completion (EAC) of the project?

a. $1,000
b. $833
c. $933
d. $1,033

Solution: 2 Marks.

As the project will continue to spend at the same current rate, the formula to be used would be: EAC
= BAC/CPI, EAC = $1000 / 1 = $1000

3. For the project with Earned Value (EV) = $360, Actual Cost (AC) = $400 and both Cost
Performance Index (CPI) and Schedule Performance Index (SPI) equal 0.90. The original
project budget is $1,000. Assuming the remaining work will be impacted by the current cost
performance and current schedule performance, what is the Estimate At Completion (EAC)
of the project?

a. $1,190
b. $1,390
c. $1,290
d. $1,090

Solution: 2 Marks.
$1,190. As the project will be impacted by the current cost performance and current schedule
performance, the formula would be: EAC = AC + [(BAC-EV)/(SPI*CPI)], EAC = $400 + [($1000 – $360) /
(0.9 * 0.9)] = $1190

4. For a project with Estimate at Completion (EAC) = $120,000 and Cost Performance Index
(CPI) is 0.90. What is the Budget at Completion (BAC)?
a. $108,000
b. $118,000
c. $158,000
d. $208,000

Solution: 1 Mark.

$108,000. As no information is given on the future performance of the project, we could safely
assume that the project will spend at the same rate. So we will make use of the formula: EAC = BAC /
CPI, $120,000 = BAC / 0.90, BAC = $120,000 * 0.90 = $108,000

5. For a project with Earned Value (EV) = $300, Actual Cost (AC) = $350 and Planned Value (PV)
= $400. The overall project budget is $1,000. Assume that you will continue to spend at the
same rate as you are currently spending. What is the Variance At Completion (VAC)?

a. -$167
b. $167
c. $150
d. -$150

Solution: 2 Marks.

-$167. As the project will continue to spend at the same current rate, the formula to be used would
be: VAC = BAC – EAC, EAC = BAC/CPI, CPI = EV/AC, VAC = BAC – BAC/(EV/AC) = $1000 –
$1000/($300/$350) = -$167

6. For the project with Earned Value (EV) = $300, Actual Cost (AC) = $250 and Planned Value
(PV) = $300. The original project budget is $1000. Assuming the project will continue to
spend money at the same rate, what is the Estimate At Completion (EAC) of the project?

a. $833
b. $933
c. $1,000
d. $1,033

Solution: 1 Mark.

As the project will continue to spend at the same current rate, the formula to be used would be: EAC
= BAC/CPI, CPI = EV/AC, EAC = BAC/(EV/AC) = $1000 / ($300/$250) = $833

7. For the project with Earned Value (EV) = $350, Actual Cost (AC) = $300 and Planned Value
(PV) = $400. The original project budget is $1,000. Assuming the remaining work will be
impacted by the current cost performance and current schedule performance, what is the
Estimate At Completion (EAC) of the project?
a. $937
b. $837
c. $987
d. $1,280

Solution: 2 Marks.

As the project will be impacted by the current cost performance and current schedule performance,
the formula would be: EAC = AC + [(BAC-EV)/(SPI*CPI)], SPI = EV / PV = $350 / $400 = 0.875, CPI =
EV / AC = $350 / $300 = 1.167, EAC = BAC/(EV/AC) = $300 + [($1000 – $350) / (0.875 * 1.167)] = $937

8. Your project is scheduled for 2 years. There are six different teams working on five major
functional areas. Some teams are ahead of schedule while others are falling behind. There
are cost overruns in some areas, but you’ve also saved costs in others. Due to all this, it is
difficult to understand whether you are over or under budget. Nine months into the project,
while the total project budget is $4,200,000, you’ve already spent $1,650,000. CPI is 0.875.
Find out EAC?

Solution: 1 Mark.

EAC = BAC / CPI = 4,200,000 / 0.875 = $4,800,000

9. Your project is scheduled for 2 years. There are six different teams working on five major
functional areas. Some teams are ahead of schedule while others are falling behind. There
are cost overruns in some areas, but you’ve also saved costs in others. Due to all this, it is
difficult to understand whether you are over or under budget. Nine months into the project,
while the total project budget is $4,200,000, you’ve already spent $1,650,000. CPI is 0.875.
Find out ETC?

Solution: 1 Mark.

ETC = EAC – AC = 4,800,000 – 1,650,000 = $3,150,000

10. Your project is scheduled for 2 years. There are six different teams working on five major
functional areas. Some teams are ahead of schedule while others are falling behind. There
are cost overruns in some areas, but you’ve also saved costs in others. Due to all this, it is
difficult to understand whether you are over or under budget. Nine months into the project,
while the total project budget is $4,200,000, you’ve already spent $1,650,000. CPI is 0.875.
Find out VAC?

Solution: 2 Mark.

VAC = BAC – EAC, = 4,200,000 – 4,800,000 = $-600,000. Since the Variance At Completion is negative,
the project will be over budget at completion by $600,000

11. You are managing a software project with an initial budget estimate of 2 million USD. During
interim cost and schedule performance analysis, you figured out that: You should have spent
$500,000 till now based on your initial plans and 1,000 man/days of schedule activities. You
spent $600,000 till now and completed 1,100 man/days of schedule activities which should
have cost $450,000 based on your initial plans. You re-estimated the budget required for the
remaining work to be done as $1,500,000. What is the Variance at Completion?
a. -$100,000
b. $100,000
c. -$50,000
d. $50000

Solution: 3 Marks

VAC (Variance at Completion) = BAC - EAC = 2 million USD - EAC


EAC (Estimate at Completion) = AC + ETC = $600,000 + $1,500,000 = $2,100,000
VAC = $2,000,000 - $2,100,000 = -$100,000

12. You are managing a software project with an initial budget estimate of 2 million USD. During
interim cost and schedule performance analysis, you figured out that you should have spent
$500,000 till now based on your initial plans and 1,000 man/days of schedule activities. You
spent $600,000 till now and completed 1,100 man/days of schedule activities which should
have cost $450,000 based on your initial plans. You re-estimated the budget required for the
remaining work to be done as $1,500,000. What is the TCPI based on your new Estimate at
Completion value?

a. 1.03
b. 1.11
c. 0.90
d. 0.97

Solution: 1 Mark

TCPI based on EAC is calculated as below:


TCPI = [BAC-EV] / [EAC-AC] = [$2,000,000-$450,000] / [$2,100,000-$600,000]
TCPI (based on EAC) = 1.03

13. You are managing a software project with an initial budget estimate of 2 million USD. During
interim cost and schedule performance analysis, you figured out that you should have spent
$500,000 till now based on your initial plans and 1,000 man/days of schedule activities. You
spent $600,000 till now and completed 1,100 man/days of schedule activities which should
have cost $450,000 based on your initial plans. You re-estimated the budget required for the
remaining work to be done as $1,500,000. What is the status of your project?

a. Project is ahead of schedule, over budget, and it is harder to complete the project
on new EAC
b. Project is ahead of schedule, over budget, and it is easier to complete the project on
new EAC
c. Project is behind schedule, over budget, and it is harder to complete the project on
new EAC
d. Project is ahead of schedule, under budget, and it is easier to complete the project
on new EAC

Solution: 1 Mark.

Project is ahead of schedule, over budget, and it is harder to complete the project on new EAC

CPI<1 and CV is negative, therefore project is over budget


SPI>1 and SV is positive, therefore project is ahead of schedule
TCPI>1, therefore project is harder to complete in new EAC value based on current project
performance.

14. When you collect the earned value data for your project, you get the following data: PV =
$1,500,000, EV = $ 1,200,000, AC = $1,000,000. You expect the factors for cost variance to
continue in the same way in future. The value of the remaining work is $1,000,000. What
should be the new EAC for the project?

a. $1,833,333
b. $2,233,333
c. $2,000,000
d. $2,400,000

Solution: 3 Marks.

Solution: EAC= BAC/CPI,


BAC = 1,200,000+1,000,000
=2,200,000.

CPI = EV/AC
= 1,200,000/1,000,000
= 1.2.

EAC = 2,200,000/1.2
= 1,833,333

15. The project is budgeted at $1,000,000. The following earned value figures have been
derived. PV=$500,000, EV = $450,000, AC= $550,000. The cost variances in the project are
caused by one-time factors which are no more effective. What will be the estimate at
completion for the project?

a. $1,100,000
b. $1,000,000
c. $900,000
d. $1,222,222

Solution: 1 Mark.

Solution: When the cost variance caused is one time and not expected to continue (the future
work will be accomplished at the planned rate),

EAC= AC+(BAC-EV)
EAC = 550000 + 1000000 – 450000
= 1,100,000

16. A software development project that you are managing has budget at completion of
$400,000. At month seven, 65% of the work was planned to be complete but stands at 50%.
Actual cost is $275,000. What is the project's ETC?

a. $275,000
b. $289,000
c. $389,855
d. $55,000

Solution: 2 Marks.

Solution: CPI = 50% *400000/ 275000


= 0.72

EAC = BAC/CPI
= 400000/0.72
= 550000

ETC = EAC – AC
= 550000 - 275000
= 275000

17. During your project analysis, you understand that there is a cost-variance in the project.
Further analysis shows that it is a one-time variance caused by an unexpected rework. You
do not expect such situation in future. You would like to get the Estimate at completion for
your project, so you perform earned value analysis and get the following data: EV =
2,000,000; PV = 1,500,000; AC = 2,500,000; BAC = 4,000,000. What is EAC?

a. $4,500,000
b. $5,000,000
c. $4,000,000
d. $5,500,000

Solution: 1 Mark.

Solution: When the variations are one-time, then


EAC = AC + BAC - EV
= 2,500,000 + 4,000,000 – 2,000,000
= 4,500,000

18. Given a project with the following characteristics, answer the following questions: You are
the project manager of a project to build fancy birdhouses. You are to build two birdhouses
a month for 12 months. Each birdhouse is planned to cost $100. Your project is scheduled to
last for 12 months. It is the beginning of month 10. You have built 20 birdhouses and your
CPI is .9091. If the variance experienced so far were to stop, what is the project’s estimate at
completion?

a. $2600
b. $2440
c. $2400
d. $2800

Solution: 1 Mark. $2600.

A few of the EMV questions you encounter in the exam will be fairly straightforward. This question is
asking you for the EAC if a variance that was encountered on a project is expected to stop, so use

EAC = AC + BAC – EV.


EAC = 2200 + 2400 – 2000
EAC = $2600
19. Given a project with the following characteristics, answer the following questions: You are
the project manager of a project to build fancy birdhouses. You are to build two birdhouses
a month for 12 months. Each birdhouse is planned to cost $100. Your project is scheduled to
last for 12 months. It is the beginning of month 10. You have built 20 birdhouses and your
CPI is .9091. What is the project’s TCPI using the project’s budget at completion?

a. 0.5
b. 1.0
c. 1.5
d. 2.0

Solution: 1 Mark. This one says use BAC,

so TCPI = (BAC – EV)/(BAC – AC)


= (2400 – 2000) / (2400 – 2200)
= 400/200
= 2.

20. Given a project with the following characteristics, answer the following questions: You are
the project manager of a project to build fancy birdhouses. You are to build two birdhouses
a month for 12 months. Each birdhouse is planned to cost $100. Your project is scheduled to
last for 12 months. It is the beginning of month 10. You have built 20 birdhouses and your
CPI is .9091. Senior management wants the percentage of the project that is complete. What
should you report?

a. 75%
b. 83%
c. 92%
d. 95%

Solution: 1 Mark.

If you can recall the percentage complete formula, then this problem is really easy! Just plug in the
values of EV and BAC to formula: (EV / BAC) *100 = 83%

21. An investment of $200,000 is expected to generate the following cash inflows in six years:
Year 1: $70,000, Year 2: $60,000, Year 3: $55,000, Year 4: $40,000, Year 5: $30,000, Year 6:
$25,000. Required: Compute payback period of the investment. Should the investment be
made if management wants to recover the initial investment in 3 years or less? (Simply
mention the payback period calculated for this problem and your interpretation with respect
to the question asked at the end of this problem).

Solution: 2 Marks.

Your payback period must equal 3.375 years, or 3.4 years. Even then it is larger than the required
period of three years. This implies this project will not be desirable.

22. An initial investment of $8,320 thousand on plant and machinery is expected to generate net
cash flows of $3,411 thousand, $4,070 thousand, $5,824 thousand and $2,065 thousand at
the end of first, second, third and fourth year respectively. Calculate the net present value of
the investment if the discount rate is 18%. Round your answer to nearest thousand dollars.
Calculate NPV, PI, IRR and Payback period? (PV Factors: Year 1 = 1 ÷ (1 + 18%)1 = 0.8475;
Year 2 = 1 ÷ (1 + 18%)2 = 0.7182; Year 3 = 1 ÷ (1 + 18%)3 = 0.6086; Year 4 = 1 ÷ (1 + 18%)4 =
0.5158), (Write down calculated values of NPV, PI, IRR and Payback period and interpret as
to what will be your decision based on each of the answers obtained for NPV, PI, IRR and
Payback period, separately/individually)

Solution: 6 Marks. Your answers are following:

IRR is 29.33% > 18% therefore ACCEPT


PI is 1.25 therefore ACCEPT
NPV at RRR is $2,103,458.82 therefore ACCEPT
Payback Period is 2.14 therefore ACCEPT

4 marks for answers to each criteria and 0.5 mark each for the four interpretations!

You might also like