Professional Documents
Culture Documents
) هو تكنيك يستخدم في ادارة المشاريع و ذلك إلعطاء دالالت عن وضعEVM( مفهوم الـ
)Budget( ) و الميزانيةSchedule( المشروع من ناحية الوقت
With EVM:
The project manager will know exactly whether the project is:
Ahead of / on / Behind Schedule
Under / on / Over Budget
Basic EVM Formulas
SV = EV – PV
Basic EVM Formulas
Ratio between EV and PV, to reflect whether the project work is ahead
of / on / behind schedule in relative terms
SPI = EV/PV
Basic EVM Formulas
Difference between EV and AC, to tell whether the project work is under
/ on / over budget
CV = EV – AC
Basic EVM Formulas
Ratio between EV and AC, to reflect whether the project work is under /
on / over budget in relative terms
CPI = EV/AC
Basic EVM Formulas
لذلك من الجيد العمل بالـ( )EVMباإلضافة إلى Critical Path Managementللحصول
على نتائج أدق.
والعيب اآلخر في ( )EVMهو انه ال يراعي الـ( )Qualityفي المشروع و لكن كل ما يراعيه
هو الوقت و التكلفة.
Example
If earned value (EV) = 350, actual cost (AC) = 400, and planned
value (PV) = 325, what is cost variance (CV)?
A. 350
B. -75
C. 400
D. -50
Example
If earned value (EV) = 350, actual cost (AC) = 400, and planned
value (PV) = 325, what is cost variance (CV)?
A. 350
B. -75
C. 400
D. -50
Example
Explanation: The CPI is less than one, so the situation is bad. The project
is only getting 89 cents out of every dollar invested.
Example
Under Over
-CV
+CV
Ahead +SV
+SV
Schedule
+CV -CV
-SV -SV
Behind
Budget
Advanced EVM Formulas
BAC/CPI
If we believe the project will continue to spend at the same rate up to
now
The delay is caused by reasons which is likely to continue (e.g. labor with
less skilled than expected)
Example:
The EAC for the housing project = US$10000 / 0.75 = US$13333
Advanced EVM Formulas
AC + [(BAC-EV)/(SPI*CPI)]
If we believe that both current cost and current schedule performance
will impact future cost performance
This formula is less likely to be used for the PMP® Exam
Example:
The EAC for the housing project
= US$4000 + [(US$10000 – $3000)/(0.75*0.75)]
= US$16444
Advanced EVM Formulas
BAC – EAC
The difference between the new estimate at completion and original
planned value
If we forecast the project will be over budget, VAC will be negative
If we forecast the project will be under budget, VAC will be positive
Example:
The VAC for the housing project
= US$10000 – US$13333 (just take the 1st EAC as an example only)
= -US$3333
Advanced EVM Formulas
(BAC-EV)/(BAC-AC)
Use this equation if the project is required to finish within BAC
Example:
The TCPI for the housing project at end of week 4
= (US$10000 – US$3000) / (US$10000 – US$4000)
the TCPI for the housing project at end of week 4 = (US$10000 – US$3000) /
(US$10000 – US$4000) = 1.67 = 1.67
Advanced EVM Formulas
(BAC-EV)/(EAC-AC)
Use this equation if the project is required to finish within new EAC
Example:
The TCPI for the housing project at end of week 4 with new EAC US$13333
= (US$10000 – US$3000) / (US$13333 – US$4000)
= 0.75
Example
You are the project manager for a project where your team must travel to the work site
by foot. The walk is 100 miles, and is the first task on the project schedule. The total
amount budgeted for this task is $4,000. If the team is scheduled to walk 20 miles per
day, they should reach the work site at the end of day 5. At the end of the second
day, you realize the team has only traveled 30 miles, and you have spent $2,000.
Based on this, what is the SPI for your project, and the projected TCPI
A. 0.8, 1.4
B. 0.75, 1.4
C. 0.75, 1.2
D. Cannot be determined with the given information
Example
You are the project manager for a project where your team must travel to the work site
by foot. The walk is 100 miles, and is the first task on the project schedule. The total
amount budgeted for this task is $4,000. If the team is scheduled to walk 20 miles per
day, they should reach the work site at the end of day 5. At the end of the second
day, you realize the team has only traveled 30 miles, and you have spent $2,000.
Based on this, what is the SPI for your project, and the projected TCPI
A. 0.8, 1.4
B. 0.75, 1.4
C. 0.75, 1.2
D. Cannot be determined with the given information
Example
You are the project manager for a project where your team must travel to the work site
by foot. The walk is 100 miles, and is the first task on the project schedule. The total
amount budgeted for this task is $4,000. If the team is scheduled to walk 20 miles per
day, they should reach the work site at the end of day 5. At the end of the second
day, you realize the team has only traveled 30 miles, and you have spent $2,000.
Based on this, what is the SPI for your project, and the projected TCPI
BAC =
AC =
PV =
EV =
Example
You are the project manager for a project where your team must travel to the work site
by foot. The walk is 100 miles, and is the first task on the project schedule. The total
amount budgeted for this task is $4,000. If the team is scheduled to walk 20 miles per
day, they should reach the work site at the end of day 5. At the end of the second
day, you realize the team has only traveled 30 miles, and you have spent $2,000.
Based on this, what is the SPI for your project, and the projected TCPI
BAC = $4,000
AC = $2,000
PV = $1,600 ($4,000 / 5 days = $800 / day x 2 days = $1,600)
EV = $1,200 ($4,000 / 100 = $40 / mile; 30 miles x $40 / mile)
Example
BAC = $4,000
AC = $2,000
PV = $1,600 ($4,000 / 5 days = $800 / day x 2 days = $1,600)
EV = $1,200 ($4,000 / 100 = $40 / mile; 30 miles x $40 / mile)
SPI = ….
Example
BAC = $4,000
AC = $2,000
PV = $1,600 ($4,000 / 5 days = $800 / day x 2 days = $1,600)
EV = $1,200 ($4,000 / 100 = $40 / mile; 30 miles x $40 / mile)
SPI = EV/PV
= $1,200 / $1,600
= 0.75 (or 30 miles / 40 miles = 0.75)
Example
BAC = $4,000
AC = $2,000
PV = $1,600 ($4,000 / 5 days = $800 / day x 2 days = $1,600)
EV = $1,200 ($4,000 / 100 = $40 / mile; 30 miles x $40 / mile)
TCPI =…
Example
BAC = $4,000
AC = $2,000
PV = $1,600 ($4,000 / 5 days = $800 / day x 2 days = $1,600)
EV = $1,200 ($4,000 / 100 = $40 / mile; 30 miles x $40 / mile)
SPI = 0.75
TCPI = 1.4
Click to edit Master title style