Professional Documents
Culture Documents
Cheat Sheet
--
"Once you’re 20% into
a project, your current
performance can be
used to predict the
future of the project
with a plus or minus
10% deviation.
Fleming and Koppelman
/
About The Author
Our market-leading digital site diary can help you get paid
for 100% of your work, deliver projects on schedule and
highlight inefficiencies for future savings.
CEO Raildiary
/
Earned Value Analysis Cheat Sheet
CPI = EV /AC = BCWP / ACWP The farther the CSI is from 1.0, the
more unlikely a project that is late
CPI ≥1: very efficient utilisation
and/or over budget is to recover.
CPI ≤1: less efficient utilisation
--
10 Earned Value Analysis
Essentials
/
10 Earned Value Analysis Essentials
1. What is the purpose of EVA?
According to a detailed study by Fleming and Koppelman, once you’re 20% into a project, your
current performance can be used to predict the future of the project with a plus or minus 10%
deviation.
Earned value analysis builds on this to compare the planned work with what has actually been
completed to determine if cost, schedule and work accomplished are progressing as planned.
A Contractor usually reports the Budgeted Cost or Work Performed (BCWP) on all work packages
completed for a project. The BCWP is then compared to BCWS to determine if the project is behind
or ahead of where it’s projected to be. If the contractor has not completed all the scheduled work
packages on time, then the BCWP will be less than the BCWS.
Worked Example
PV can also be calculated for a period of time, month 3-6 inclusive = £100,000 * 40% = £40,000.
/
3. ACWP - Actual Cost of Work Performed
The Project Management Institute defined Actual Cost of Work Performed as “the realised cost
incurred for the work performed during a specific time period”.
The ACWP is reported by the contractor’s accounting system in accordance with generally accepted
accounting procedures and is simply stated actuals are actuals.
Worked Example
Contractors usually report the BCWP on individual packages within a project and compare it to
Budgeted Cost of Work Scheduled (BCWS) to understand if a project or package is being or ahead of
where it was projected to be .
If the contractor has not completed all the scheduled work packages on time, then the BCWP will be
less than the BCWS.
Worked Example
BWCP or EV = Total Project cost * % of actual work complete = £100,000 * 55% = £55,000.
/
5. SV - Schedule Variance (BCWP-BCWS)
Schedule Variance (SV) indicates how much ahead or behind schedule the project is. It measures
whether a project is on track by calculating actual progress against expected progress
This variance indicates how much cost of the work is yet to be completed as per schedule or how
much cost of work has been completed over and above the scheduled cost.
Worked Example
SV = BCWP - BCWS
SV = £55,000 - £60,000
SV = -£5000
SV% = SV / BCWS
It is used to track expense line items, but can also be tracked at the project level, as long as there is a
budget allocated to the item.
Worked Example
CV = EV – AC
/
7. SPI - Schedule Performance Index
SPI reviews the project performance from a schedule perspective and can be calculated using the
following formula:
SPI value greater than (≥) 1: indicates the project team is very efficient in utilising the time allocated
to the project
SPI value less than (≤) 1: indicates the project team is less efficient in utilising the time allocated to
the project
Worked Example
SPI = 0.92
This indicates that the project is only 92% as per the original plan or is 8% behind schedule.
CPI is an index showing the efficiency of the utilisation of the resources on the project.
Greater than (≥) 1 indicates efficiency in utilising the resources allocated to the project is good.
Less than (≤) 1: indicates efficiency in utilising the resources allocated to the project is not good.
Worked Example
CPI = 0.79
/
9. CSI - Cost Schedule Index
If a project is slipping on programme or likely to over spend then the Cost Schedule Index is a
valuable measurement to consider. It measures the project’s overall efficiency and indicates how
likely a project that’s deviating from baselines is to recover.
Cost Schedule Index (CSI) = Cost Performance Index (CPI) x Schedule Performance Index (SPI)
The farther the CSI is from 1.0, the more unlikely a project that is late and/or over budget is to
recover.
Worked Example
CSI = 0.72
The most common way to determine EAC is a “bottom-up” approach where the actual costs (AC) are
added to the forecasted remaining – the estimate to complete (ETC).
Alternatively, if the project has recurring variances then the following formula is recommended:
--
Book A Consultation
If you want to automate the capture and
analysis of this essential industry data, then
find out how in a 1-1 consultation with our
product experts.