Professional Documents
Culture Documents
SV = EV – PV or
If SV is negative, the task is behind schedule.
SV = BCWP-BCWS
If SV is zero, the task is on schedule.
If SV is positive, the task is ahead of schedule.
7
Cont’d……
SPI = EV/PV or
If SPI < 1, the task is behind schedule
SPI= BCWP/BCWS
If SPI = 1, the task is on schedule
If SPI > 1, the task is ahead of schedule
8
Cont’d…...
6. Cost Variance (CV)
Similar to the schedule variance, the Cost Variance tells the
project manager how far the task is over or under budget.
CV = EV – AC or
If CV is negative, the task is over budget
CV = BCWP - ACWP
If CV is zero, the project is on budget
If CV is positive, the project is under budget
9
Cont’d….
CPI = EV/AC or
If CPI < 1, the task is over budget
CPI = BCWP/ACWP
If CPI = 1, the task is on budget
If CPI > 1, the task is under budget
10
Cont’d…..
11
Cont’d…
EAC = BAC/CPI
EAC = AC + [(BAC – EV)/(SPI x CPI)]
EAC = AC + ETC
12
Cont’d….
10. Estimate to Complete (ETC)
This value tells the project manager how much money must be
spent from this point forward, to complete the project
Sometimes the project assumptions have changed and a new
estimate must be produced instead of old performance metrics
assumed.
The project is expected to continue with the same performance
in the future as the past. ETC = EAC – AC
ETC = new estimate
13
Cont’d…..
Tells the project manager what CPI would be necessary to finish the project on
budget
16
The Comparison between planned and earned values provides
work accomplishment or project performance in terms of cost and
time variances
18
Example Problem 2
For the following project calculate SV,CV, SPI and CPI at the
end of second month.
Month 1 2 3 4
19
Example Problem 3
20
Problem Example 4
The following bar chart shows the activities to complete a project in six
months (each cell represents 1 month). The total project cost is $1,480.
A $100
B $200
C $60
D $80
E $40
F $150
G $300
H $100
H $50
J $400
21
Cont’d…..
After 3 months, Activities A, B, C, E, D and
half of F are completed, for a cost of$490.
What is the status of the project in terms of the
budget (over or under) and the schedule (ahead or
behind)? (Give each answer in terms of a percent
variance)
22
Problem Example 5
• The following depicts a one-year schedule for a project.
Activity Cost Month 1 Month 2 Month 3 Month 4 Month 5 Month 6
A $50
B $120
C $80
D $200
E $120
F $300
G $60
H $70
J $50
K $60
23
Cont’d…..
• After three months on the job (July 1), the contractor concluded
that 20% of Activity F , Activities A, B, and D was 100 %
completed, 80% of Activity C was completed, and 40% of
Activity E was completed. The project has cost the contractor a
total of $535.For this project, using earned value concepts
determine the schedule variance and the cost variance. State if
the project is over or under budget and if it is ahead of or
behind
schedule.
24
Problem example 6
You are building a 4-sided fence. Each side is of equal length and
you estimate that each side will contain the same material and labor
costs as well as take the same amount of time to complete. You
estimate that the project will take 4 days to complete and your
budget, including a contingency reserve is $4,000.
At the end of 3 days, you are asked to prepare an Earned Value
calculation in order to determine how the project is progressing. You
determine that as of the end of day 3, total costs incurred are $3,500.
and 70% of the project is completed.
Determine :-
1. ACWP, BCWP, BCWS, CV, CPI, SV, SPI, EAC, BAC, VAC &
ETC
2. Status of the project
25
Problem example 7
27