Professional Documents
Culture Documents
Project Management
Data Date
When is this project data as of?
Performance Indices
CPI = (EV) / (AC)
Cost Performance Index
> 1 typically good (cost < plan)
CPI Ratio of planned spend on what’s actually done to what’s
< 1 bad (cost > plan)
actually spent for the work delivered by reporting date
= 1 good (cost = plan)
SPI = (EV) / (PV)
Schedule Performance Index
> 1 typically good (ahead vs. plan)
SPI Ratio of planned spend on what’s actually done to planned
< 1 bad (behind vs. plan)
spend on what you planned to have done by reporting date
= 1 good (on plan)
Forecasts
Estimate At Completion EAC = AC + ((BAC – EV) / CPI)) (typical)
EAC Expected TOTAL cost for 100% complete]
Atypical - assumes similar variances seen will not occur in future EAC = AC + (BAC – EV) (atypical)
Estimate to Complete
ETC Expected cost to finish REMAINING work ETC = EAC - AC
Earned Value Management (EVM)
3
Example
PV = 4,156,633
BAC
Months 0 1 2 3 4 5 6 7 8 9
EV = 3,800,000
AC = 3,400,000
Variances and Calculations : EV = 3,800,000 BAC = 7,045,140
AC = 3,400,000 PV = 4,156,633
SV = EV - PV -356,633
Behind Schedule
SPI = EV / PV 0.9142015
CV = EV - AC 400,000
Under Budget
CPI = EV / AC 1.1176471