Professional Documents
Culture Documents
Objective:
Many a times one could easily be on time, however may overspend, or may be on
time & within budget however scope may be incomplete. In simple terms, EV
analysis is better than comparing actual to planned results or by simply guessing
the project status.
Definitions
Originally
planned cost of
the work that
Planned Value (PV) or Budgeted Cost of Work Scheduled (BCWS) should have
been done by
this time
Actual cost
expenses on
Actual Cost (AC) or Actual Cost of Work Performed (ACWP)
this project
upto this time
Estimated cost
of budgeted
Earned Value (EV) or Budgeted cost of Work Performed (BCWP)
work
completed
Total budget
Budget at Completion (BAC)
for the project
Estimated final
Estimate At Completion (EAC) cost of the
project
Estimated cost
of the
Estimate To Completion (ETC) remaining
work of the
project
Description EVA Formulas Result
Positive value is good.
Cost Variance (CV) CV = EV – AC Negative value
unfavourable.
Value below 1.0 = below
par performance. Value
above 1.0 = above par
Schedule Variance (SV) SV = EV – PV performance The further
away the ratio is from
1.0 the more urgent need
to investigate
>1 means project
Cost Performance CPI = EV / AC, compares performed to
efficient, <1 means
Indicator (CPI) actual cost
project inefficient
>1 means project ahead
Schedule Performance SPI = EV / PV, compares work
of schedule, <1 means
Indicator (SPI) performed to work planned
project behind schedule
Estimate At Completion
EAC = BAC/CPI
(EAC)
Estimate To Complete
ETC = (BAC – EV) / CPI
(ETC)
Example
Assume a project that has exactly one task. The task was baselined at 100 hours,
but 110 hours have been spent and the estimate to complete is 10 additional hours.
The task was to have been completed already. Assume an hourly rate of $100 per
hour.
Description Formulae Result
Hourly Rate * Total Hours
PV 100*100 = 10,000
Planned or Scheduled
Hourly Rate * Total Hours
AC 100*110 = 11,000
Spent
AC divided by estimated cost at
% Complete completion which is 11,000 11000/(11000+1000) = 91.667%
plus cost of 10 additional hours
Baselined Cost * % Complete 9166.667 (baseline of 10,000 *
EV
Actual 91.667% complete)
10000 (100 hours * 100) indicates
Baselined Effort in hours *
BAC initially budget signed off for the
Hourly Rate
project
12000 (11000 + 1000) notice this
EAC AC + ETC
is over budget
-2000 (10000 – 12000) indicates
VAC BAC – EAC additional funds required to
complete work
% Completed
PV / BAC 100% (10000/10000)
Planned
% Completed 91.7% (11000/12000) lesser than
AC / EAC
Actual planned completion
-833.33 (9166.667 – 10000)
Earned Value (EV) – Planned
SV negative schedule variance or
Value (PV)
behind schedule
0.9167 (9166.667 /
SPI SPI = EV / PV 10000) indicating poor schedule
performance
Earned Value (EV) – Actual -1.833.33 (9166.67 – 11000)
CV
Cost (AC) indicating a cost overrun
Earned Value (EV) /Actual 0.833 (9166.667 / 11000)
CPI
Cost (AC) indicating over budget
3.2 The Critical Ratio
The critical ratio (CR) is the product of CPI and SPI. It can also be called the
cost-schedule index (CSI).
It is used as an indicator of the overall project health
CR = CPI x SPI.
A graph of the critical ratio over time provides a quick indicator of trends in the
overall project performance, and of the impact of any corrective actions. These
graphs may be very effective in project reviews
3.3 Line of Balance
A simple diagram in which line shows location and time at which a certain crew
will be working on a given operation is known as LOB. It is used on repetitive
work such as constructing multiple dwelling units, when used on linear work such
as roads and railways the technique is more accurately called Time/Location
Charts
The purpose of the LOB method is to ensure that the many activities of a repetitive
production process stay “in balance” that is, they are producing at a pace which
allows an even flow of the items produced through a process and at a speed
compatible with the goals set forth in a plan.
Clearly shows the amount of work taking place in a certain area at a specific
time of the project.
Has the ability to show and optimize the resources used for large number
of repeated activities, executed in several zones or locations.
Easier cost and time optimization analysis because of all the information
available for each activity in the project.
Ease of setup and its superior presentation and visualization.
Easier to modify, update and change the schedule.
Better managing of all the various sub-contractors in the project.
Allows for simpler and clearer resource management and resource
optimization functions.
Visualization of productivity and location of crews.
It allows project managers to see, in the middle of a project, whether they
can meet the schedule if they continue working as they have been.
Advantages:
Disadvantages:
Delays and incomplete tasks could lead to project delays, depending on whether
the activities are in the critical path. In addition, project costs get impacted
negatively. Delayed tasks translate to effort that has not been budgeted for,
therefore cost of that task to completion goes up.
Some simple, yet effective, project control techniques that you can use to ensure
timely completion of tasks are:
Project crashing
As projects continue over time, they consume indirect costs, including the
cost of facilities, equipment, and machinery, interest on investment, utilities,
labor, personnel costs, and the loss of skills and labor from members of the
project team who are not working at their regular jobs.
Financial penalties for not completing a project on time were also incurred.
For example, many construction contracts and government contracts have
penalty clauses for exceeding the project completion date.
Project crashing costs and indirect costs have an inverse relationship;
crashing costs are highest when the project is shortened, whereas indirect
costs increase as the project duration increases. This time-cost relationship is
illustrated in the above figure. The best, or optimal, project time is at the
minimum point on the total cost curve.
Critical path for the house building network in following figure is activities 1-2-3-
4-6-7 and the project duration was 9 months, or 36 weeks. Suppose the home
builder needed the house in 30 weeks and wanted to know how much extra cost
would be incurred to complete the house by this time.
Following table represents the time and costs before and after project crashing
The total cost of crashing the project to 30 weeks is 2,500. The contractor could
inform the customer that an additional cost of only 2,500 would be incurred to
finish the house in 30 weeks.