Professional Documents
Culture Documents
Earned Value
(EV)
Actual Cost
(AC)
Planned Value (PV)
• Authorized budget assigned to
scheduled work for an activity or WBS
component, not including
management reserve
• It is the budget
associated with the
authorized work that has
been completed
Actual Cost (AC)
• Actual cost (AC) is the
realized cost incurred for
the work performed on an
activity during a specific
time period.
SV = EV – PV
(-) is Behind the schedule
(0) is on schedule
(+) is Ahead of schedule
Cost Variance (CV)
• Amount of budget deficit or surplus at a given point in time,
expressed as the difference between earned value and the
actual cost
CV = EV – AC
(-) is Over the Budget
(0) is on Budget
(+) is Under the Budget
Example Questions (SV & CV)
o If EV = Rs. 1000, AC = Rs. 2000 then CV is ?
a) -1000
b) 2
c) 1000
d) 0.5
SPI = EV/PV
CPI = EV/AC