Professional Documents
Culture Documents
Understanding cost
management
Budgeting
Cost estimation
Project cost management
Performance
Cost
Time
Scope Objectives
Cost is the easiest to measure—generally
refers to labor costs
Variance or Earned Value Analysis
Term Formula
Earned Value Budgeted Cost of Work Performed (BCWP) =
budgeted cost to date X % complete
Cost Variance CV=BCWP-ACWP (actual cost of work performed)
Schedule Variance SV=BCWP-BCWS (budgeted cost of work
scheduled)
Cost Performance Index CPI=BCWP/ACWP
Schedule Performance Index SPI = BCWP/BCWS
Example
SPI=BCWP($3600)/BCWS($3900), therefore
SPI=.92—you are nearly 10% behind in
schedule
Rules of Thumb for EVA Numbers
Example
– Say your BAC (budget at completion) is $120,000
and your CPI is (as before) .92,
BAC/CPI = $130,434.78
Excel file
NPV example