Formulas
Symbol / Formula Description Explanation
BAC Budget at complete Total cost planned or Total PV
PV = sum to date Planned value Value “should” have achieved to date
EV = PV or Total PV x % complete Earned value Value of work completed to date
TCPI = (BAC - EV) / (BAC - AC) To-complete performance index Efficiency needed to hit original budget
TCPI = (BAC - EV) / (EAC - AC) Efficiency needed to hit new budget
3
Formulas (cont.)
Symbol / Formula Description Explanation
(P + 4M + O) / 6 PERT estimate 3-points (pessimistic, most likely, optimistic)