Professional Documents
Culture Documents
Value (EV) Cost Variance (CV) Schedule Variance (SV) Cost Performance Index (CPI) Schedule Performance Index (SPI) Estimate At Completion (EAC) Estimate to Complete (ETC) Variance At Completion (VAC) = % complete * BAC = EV AC = EV - PV = EV / AC = = = = EV / PV (>0 good) ( >0 good) (>1 good) (>1 good)
PERT = (O+4M+P) / 6 ; (O=Optimistic; M= Most likely; P=Pessimistic) Standard Deviation of Activity (SD) = (P-O) / 6 Normal Distribution 1 Sigma = 68.26%; 99.999% 2 Sigma = 95.46%; 3 Sigma = 99.73%; 6 Sigma =
Present Value =
FV (1+r)n
Communication Channels =
N (N-1) 2