PMP Formulas

Forward Pass

ES
EF

ES = EF of the predecessor node


EF = ES + Du

Du
Node

Backward Pass

Slack = LF EF = LS ES

LF = LS of the Successor

Free Float = ES(Successor) EF(Predecessor)

LS = LF Du

QUALITY
CoQ = ( ( Review Efforts + Test Efforts +
Training Efforts + Rework
Efforts + Efforts of
Prevention) / Total Efforts) x
100 %
PERT =

O + 4ML + P
6

STD. DEV. OF TASK =

MEAN Average
MODE The most found number
RANGE Largest - Smallest Measure.
MEDIUM No in the middle or avg. of 2
middle Nos
SIGMA

P-O
6

(P O) 2 = Std. Dev ^ 2
6
____________
CP STD. DEV. = + +
TASK VAR. =

PROJECT

1 = 68.26
2 = 95.46
3 = 99.73
6 = 99.99

Channels of Communication
COMM = (N2 - N) / 2 = (N x (N 1)) /

SELECTION
Cash Flow = Cash Inflow Cash Outflow

PV
FV

FV .
(1+r)

Discounted Cash Flow = CF x Discount


Factor

= PV x (1+r)

NPV = ( PV + PV +
PV + PV
(1+r) (1+r) (1+r) (1+r)

ARR = Cash Flow / No. of Years


ROI = (ARR / Investment) * 100 %
BCR = Benefits / Cost
Exp. Value = Probability % x Consequence
$

Contract Incentives
Savings = Target Cost Actual Cost
Bonus = Savings x Percentage
Contract Cost = Bonus + Fees
Total Cost = Actual Cost + Contract
Cost

Earned Value Management


PV (Present Value) = BCWS (Budgeted Cost of Work Scheduled)
EV (Earned Value) = BCWP (Budgeted Cost of Work Performed)
AC (Actual Cost) = ACWP (Actual Cost of Work Performed)
CV = EV AC
CPI = EV / AC (efficiency)
SV = EV PV
SPI = EV / PV
TCPI using BAC = (BAC-EV) / (BAC-AC)
TCPI using EAC = (BAC-EV) / (EAC-AC)
% COMPLETE = EV / BAC x 100
% SPENT
= AC / BAC x 100

ETC = EAC AC or
(BAC EV) / CPI
EAC = AC + ETC
EAC = BAC / CPI
EAC = AC + BAC EV
EAC = AC+ {(BAC-EV) / (cumulative CPI x
cumulative SPI)}
VAC = BAC EAC
CV% = AC / EV x 100
SV% = AC / PV x 100
Page 1 of 2

PMP Formulas

Page 2 of 2