PMP – Formula Summary

No Group - Names Formulas


1 PERT (Beta distribution) PERT = (0+4ML+ P)/6

2 PERT (Triangle PERT = (0+ML+ P)/3


distribution)
3 STD DEV of Task STD, DEV. OF TASK = (P – 0)/6
4 Variance TASKVAR. = ((P-0)/6) 2 = (Std.Dev)2
5 CP. STD. DEV. CP STD. DEV. = √ σ2 + σ2 + σ2
6 Sigma Values 1σ = 68.26% | 2σ = 95.46% | 3σ = 99.73% | 6σ = 99.99985%
7 Communication COMMUNICATION CHANNELS = (N2-N)/2 = (Nx(N-1))/ 2
8 Project Selection PV = FV/(1+r)n
FV = PV x(1+r)n
NPV = S ( PV + PV + PV + PV )
--- --- --- -- -- --------
or NPV=FV/(1+R)n > best (1+r)n (l+r)n (1+r)n (1+r)n
11 Contract Incentives Savings = Target Cost ~ Actual Cost
12 Bonus = Savings x Percentage
13 Contract Cost = Bonus + Fees
14 Total Cost = Actual Cost + Contract Cost
15 Total point of assumption ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost

16 Total Float LS-ES or LF-EF


17 Free Float Successor (ES) – Activity (EF)
Website : www.infocareerindia.com Email : info@infocareerindia.com
No Group- Names Formulas
18 Earned Value PV (Planned Value) = BCWS (Budgeted Cost of Work Schedule)
Management EV (Earned Value) = BCWP (Budgeted Cost of Work Performed)
AC (Actual Cost) = ACWP (Actual Cost of Work Performed)
19 CV = EV – AC
21 CPI = EV /AC (efficiency)
22 SV = EV – PV
23 SPI = EV / PV
24 EAC = AC + ETC
25 EAC=BAC/CPI
26 EAC atypical in future = AC+(BAC-EV)
27 EAC typical in future = AC+(BAC-EV)/CPI
28 EAC with CPI and SPI = AC+((BAC-EV) / (CPI*SPI))
29 VAC = BAC – EAC
30 % COMPLETE = EV / BAC x 100
31 % SPENT = AC / BAC x 100
30 CV% = CV/EVx100
32 SV% = SV/PVx100
33 TCPI with BAC = (BAC-EV)/(BAC-AC)
34 TCPI with EAC = (BAC-EV)/(EAC-AC)
35 Risk Expected Monetary Value (EMV)=Probability x Impact