Professional Documents
Culture Documents
FINA 2303 Chapter 13 Cost of Capital Spring 2023
FINA 2303 Chapter 13 Cost of Capital Spring 2023
______________________________________________________
Cost of Capital
______________________________________________________
Cost of capital provides us with an indication of how the market views the
risk of our assets
Knowing cost of capital can also help us determine our required return for
capital budgeting projects
______________________________________________________
To create value, manager should invest in assets that yield higher returns than cost of
funds (weighted average cost of bond, preferred stock, and common stock).
Example: if investor requires 10% rate of return, to create value, manager must invest in
assets that give more than 10% rate of return.
______________________________________________________
Required Return
The required return is the same as the appropriate discount rate and is based
on the risk of the cash flows from the project
We need to earn at least the required return to compensate our investors for
the financing they have provided
______________________________________________________
Source of Capital
Long-term debt
Preferred stock
Common Stock
______________________________________________________
Because in equilibrium, expected return and required return on common stock are the
same, we can find cost of equity from either one of the equations below.
D1
RE g
P0
Capital Asset Pricing Model (CAPM) 3/4 of U.S. Companies use CAPM
RE R f ( Rm R f )
______________________________________________________
Blair Brothers’ stock currently has a price of $50 per share and is expected to pay a year-end
dividend of $2.50 per share (D1 = $2.50). The dividend is expected to grow at a constant
rate of 4 percent per year. What is the company’s cost of equity?
D1 2 .5
RE g 0.04 0.09 9% Cost of equity
P0 50
______________________________________________________
The common stock of Anthony Steel has a beta of 1.20. The risk-free rate is 5 percent and the
market risk premium (Rm - Rf) is 6 percent. What is the company’s cost of equity?
Key assumption
The systematic risk (beta) of the new project is the same as the systematic risk of the firm
______________________________________________________
______________________________________________________
Johnson & Johnson issues dividends at an annual rate of $2.16. Its current
stock price is $60.50, and you expect dividends to increase at a constant rate
of 4% per year.
Because of the different assumptions we make when using each method, the two
methods do not have to produce the same answer.
We must examine the assumptions we made for each approach and decide which
set of assumptions is more realistic.
Ekkachai Saenyasiri Page 10 2/26/2023
FINA 2303 Spring 2023
______________________________________________________
Reminders
Preferred stock generally pays a constant dividend each period
Dividends are expected to be paid every period forever
A preferred stock can usually be valued like a perpetuity.
D D D D D D D D D
| | | | | | | | | | | |
0 1 2 3 4 5 6 7 8 9 10 11 12
D D
P R ps =
R ps P
Rps = Investor’ s required return for preferred stock = Cost of preferred stock
______________________________________________________
Example: If Prescott Corporation issues preferred stock, it will pay a dividend of $8 per
year and the preferred stock should be valued at $75 per share. What is the cost of
preferred stock for Prescott?
Dividends on preferred stock are not tax deductible. Dividends are paid after tax.
______________________________________________________
Cost of Debt
For the issuing firm, the cost of debt is the rate of return required by investors,
adjusted for taxes
Note that
Dividends on common stock and preferred stocks are not tax deductible, so
no tax adjustments necessary.
Interests paid on debt are tax deductible (good for investors), stockholders
focus on after-tax cash flows. Therefore, we should focus on after-tax cost of
debt.
______________________________________________________
______________________________________________________
Now suppose the firm with all equity pays $50,000 in dividends to stockholders.
Firm’s value is higher when using debt. Notice that both of them pay out $50,000 to investors.
Bottom line is that both firms generate equal income from operation, but
With all equity (no debt), government gets $136,000. Investors get
Shareholder gets 50000 + 214,000 = $264,000 $264,000
______________________________________________________
Example: Suppose a bond pays 10% coupon on $1,000 par value. And assume that
investors' required return = 10%.
Cost of debt pay coupon $100 each year
Benefit of debt reduce tax $34 each year
Net cost of debt = $100 - $34 = $66 6.6 % 10% (1- 0.34) Rd (1- tax rate)
After tax cost of debt = Before tax cost of debt * (1 – Marginal Tax Rate)
Example: Suppose that before-tax cost of debt = 10%, what is after-tax cost of
debt? Assuming that marginal tax rate = 34%.
______________________________________________________
Example: Prescott Corporation issues a 20-year bond paying 10% coupon rate
on $1,000 face value. Coupons are semiannual. Assume that the bond will be
sold for $950. What is the pre-tax cost of debt for Prescott Corporation?
1
1
n
(1 Rd ) Par
C
Bond Price = Rd
1 Rd n
Rb = interest rate for half year.
C = 10% * 1,000 = $100 per year = $50 every six months.
1
1
40
(1 Rd ) 1000
50
950 = R d 1 Rd 40
______________________________________________________
1
1
40
(1 Rd ) 1000 Solve for Rd
50
1 R 40
Rd
950 = d
______________________________________________________
What is the after-tax cost of debt for Prescott Corporation? Assume marginal tax
rate = 34%.
After tax cost of debt = Before tax cost of debt * ( 1- tax rate)
= 10.6% * (1 - 0.34)
= 7%
So, a 10% bond costs the firm only 7% since the interest is tax deductible.
______________________________________________________
The Weight Average Cost of Capital (Rwacc)
The weighted average cost of capital is the weighted average cost of all the
financing sources.
wd + wps + wE = 1
______________________________________________________
Ten million dollars in debt trading at 95% of face value is $9.5 million in market
value.
One million shares of stock at $30 per share is $30 million in market value.
______________________________________________________
Example: A company wants to invest in a new project. This project will be financed by
$140 million of retained earnings, $40 million of new debt and $20 million of new
preferred stock. Given the information in the table below, find the weighted average cost
of capital for this project.
Source of Capital Weights Before tax cost of capital
Assume tax rate = 34%. Note that after tax cost of debt = 9.09% * (1-0.34) = 6%
Do not adjust for tax for both preferred and common stock.
Rwacc 0.2 0.0909 (1 0.34) 0.1 0.1 0.7 0.16 = 0.134 = 13.4%
To create value, this new project has to yield return at least 13.4% to satisfy all investors
who bought bonds, preferred stocks and common stocks.
The firm should not invest in this project if it yields return less than 13.4%.
Ekkachai Saenyasiri Page 22 2/26/2023
FINA 2303 Spring 2023
______________________________________________________
Before tax
Assume tax rate = 35%
______________________________________________________
We can use the firm's WACC to estimate a project's NPV only when the level of risk of
that project is similar to the level of risk of the firm.
If project risk differs from that of the firm, then
The firm’s WACC is no longer appropriate cost of capital for the project. For this
reason, firms that invest in multiple divisions or business unites that have different
risk characteristics should calculate a different cost of capital for each division.
We can use WACC of competitors whose business are similar to the new project
We may also compute the new project's WACC by adjusting the firm's WACC
upward/downward depend on whether the new project is more or less risky than the
firm
By using the firm's WACC for a new project, we also implicitly assume that the firm will
keep the debt-equity ratio constant
______________________________________________________
Example
The cost of bringing the beer to market is $200 million, but Heineken expects first-
year incremental free cash flows from BeerZero to be $100 million and to grow at
3% per year thereafter.
______________________________________________________
The cost of capital of the new project must depend on the risk of the new project
To use the firm's WACC, we have to assume that the new project is as risky as
the firm overall.
Answer: McDonald’s must evaluate this project based on 12% cost of capital
reject this project
______________________________________________________
- Cost of filing and registration with the Securities and Exchange Commission
- Fees charged by investment bankers, accountants and lawyers
We should treat the issuing costs as negative cash flow in the NPV analysis
______________________________________________________
DuPont plans to offer $23 billion as the purchase price for firm X. To do so,
Dupont will need to issue additional debt and equity to finance such a large
acquisition.
You estimate that the issuance costs will be $0.8 billion and will be paid as soon
as the transaction closes.
You estimate the incremental free cash flows from the acquisition will be $1.4
billion in the first year and will grow at 3% per year thereafter.
1.4
𝑁𝑃𝑉 23 0.8 0.338 𝑏𝑖𝑙𝑙𝑖𝑜𝑛
0.088 0.03
______________________________________________________
– Suppose DuPont is considering an investment that would extend the life of one
of its chemical facilities for 4 years
– The project would require upfront costs of $6.67 million plus a $24 million
investment in equipment
– The equipment will be obsolete in four years and will be depreciated via
straight-line over that period
– DuPont expects annual sales of $60 million per year from this facility
– Material costs and operating expenses are expected to total $25 million and $9
million, respectively, per year
– DuPont expects no net working capital requirements for the project, and it pays
a tax rate of 35%.
– WACC = 9.11%
______________________________________________________
Expected Free Cash Flow from Dupont' s Facility Project
19 19 19 19
𝑁𝑃𝑉 28.34 33.07 𝑚𝑖𝑙𝑙𝑖𝑜𝑛
1.0911 1.0911 1.0911 1.0911
Ekkachai Saenyasiri Page 30 2/26/2023
FINA 2303 Spring 2023
______________________________________________________
Equity Information
50 million shares
$80 per share
Beta = 1.15
Market risk premium = 9%
Risk-free rate = 5%
Debt Information
$1 billion in outstanding debt (face value)
Current quote = 110 (i.e., bond price is traded at 110% of face value)
Coupon rate = 9%, semiannual coupons
15 years to maturity
______________________________________________________
______________________________________________________
______________________________________________________
Example: A firm is considering a project that will result in after-tax cash
savings of $5 million at the end of first year. These savings will grow at the rate
of 5% per year. WD = 0.333. WE = 0.667. RD = 10%. RE = 29.2%. Should the
firm take on the project? Assume tax rate = 34%
$5,000,000
PV
WACC 0.05
The NPV will be positive only if the cost is less than $30 million.
Ekkachai Saenyasiri Page 34 2/26/2023