Class Test - 1

Student No: Time: 20 Minutes Total marks: 20

Q1. Determine the expected time for each of the path. Which path is critical? Calculate the variance along
Critical Path. (10)

Q2. The maintenance project of a Building consists ten jobs. The predecessor relationships are identified
by their node numbers, as indicated below:
Activity/Job Identification Activity/Job Identification
A (1,2) F (4,5)
B (2,3) G (4,7)
C (2,4) H (5,8)
D (3,6) I (6,8)
E (3,5) J (7,8)

Draw the network diagram for the project. (6)


Q.3 A Project consists of 8 Activities A, B, C, D, E, F, G and H with their times of completion as follows: (4)

Activity A B C D E F G H
Duration 2 4 2 4 6 4 5 4
(weeks)

The precedence relationships are as follows:


 A and B can performed in parallel
 C and D cannot starts until A is completed
 E cannot start until half the work of activity C is completed
 F can starts only after activity D is completed
 G succeeds C
 H is the last activity, which should succeed E.
Draw the BAR CHARTS.