Construction Engineering Management
Module 1 Bidding Process
5. Who are the following responsive bidders?
P.D. 1594 f 6. What is the average of all the responsive The implementing rules and regulations of P.D. 1594 bids? states that no award of contracts shall be made to a bidder 7. What is the Allowable Government Estimates whose bid price is higher than the Allowable 8. Which bidder should the project be awarded Government Estimate (AGE) or the Approve Agency to? Estimate (AAE), whichever is higher, or lower than the 70% of the AGE. The Allowable Government Estimate P.D. 1594 for Unbalanced Bids (AGE) is defined as one-half the sum of the AAE and the average of all responsive bids. For purposes of The implementing rules of P.D. 1594 defines determining the average of all responsive bids, bids an unbalanced bid as a bid containing one or higher than one hundred twenty (120%) of the AAE or more pay items that are 30% higher than the lower than the sixty percent (60%) of the AAE shall not unit Allowable Government Estimate (AGE) in be considered/ No negotiation will be allowed to bring respect to major items whereas other pay items down the bid to the level of the AAE/AGE. are priced lower than the unit AGE. AGE is defined as one-half the sum of the AAE and the Sample Problems average of all responsive bids. For purposes of Situation I: determining the average of all responsive bids, bids higher than 120% of the AAE or lower than A project has been bid out by the Department of Public 60% of the AAE shall not be considered. Major Works and Highways. The Approved Agency Estimate items are defined as pay items representing at (AAE) is 500 million pesos. The results of responsive bids least 20% of the AAE or those indicated or are as follows: specified in the instruction to bidders. Bidders Bid Price Situation III: Bidder A ₱ 354,000,000 The responsive bids for a government project Bidder B ₱ 639,000,000 with 8 bid items are as follows (all cost figures are Bidder C ₱ 483,000,000 Bidder D ₱ 583,000,000 in thousands of pesos): Bidder E ₱ 295,000,000 Bidder F ₱ 385,000,000 Qty AAE Bid A Bid B Bid C Item 100 1,000 1,000 1,250 750 1. Who are the following responsive bidders? 1 2. What is the average of all the responsive bids? Item 100 20,000 22,000 16,000 19,000 3. What is the Allowable Government Estimates? 2 4. Which bidder should the project be awarded to? Item 500 5,000 4,000 6,100 5,100 3 Situation II: Item 60 6,000 6,000 4,800 5,600 4 A project has been bid out by the Department of Public Item 1,000 3,000 2,900 3,300 2,800 Works and Highways. The Approved Agency Estimate 5 (AAE) is 280 million pesos. The results of responsive bids Item 400 1,600 1,000 1,600 2,100 are as follows: 6 Bidders Bid Price Item 3,000 3,000 2,500 2,400 3,200 Bidder A ₱ 354,000,000 7 Item 20 25,000 31,000 20,000 26,000 Bidder B ₱ 639,000,000 8 Bidder C ₱ 483,000,000 Bidder D ₱ 583,000,000 Bidder E ₱ 295,000,000 Bidder F ₱ 385,000,000 Technological University of the Philippines – Taguig Campus Km. 14, East Service Rd., Western, Bicutan, Taguig City
Construction Engineering Management
Module 1 Bidding Process
9. What is the total AAE?
10. What are/is considered as major item/s? Situation V: 11. What are/is considered as unbalanced bids? The quantities and contract prices for a P.D. 1594 for Change Order government project are as follows (all cost figures The implementing rules and regulations of P.D. 1594 are in thousands of pesos): prescribe the conditions where a change order may be Unit Price issued. Change orders are limited to 25% of the original Qty AAE Contract contact cost excluding the effects of price escalation Item 1 120 100 80 and provided that no major item shall be increased by Item 2 50 2,400 2,500 more than 100% of its original cost. Major items are Item 3 600 160 150 defined as pay items representing at least 20% of the AAE Item 4 80 1,000 900 or the first two items having the highest percentage of the Item 5 800 40 45 AAE or those indicated/specified in the instruction to Item 6 500 80 90 bidders. Item 7 25 1,200 1,100 Item 8 3,500 20 18 The Implementing rules and regulations of P.D. 1594 states that for a unit-price contract, quantity overruns or 15. What is the total AAE? under runs of not more than fifteen percent (15%) of the estimates per major pay item (i.e pay items which 16. What item/s are/is considered as major represents at least 20% of the total estimated cost) and item/s? twenty five percent (25%) per minor item in the Bill of 17. What item/s should be covered by a change order given the following table? Quantities need not to be covered by Change Order provided that the same is authorized by the Approving Change Qty Order Authority for the contract. Item 1 120 150 Item 2 50 55 Situation IV: Item 3 600 500 The quantities and contract prices for a government Item 4 80 90 project are as follows (all cost figures are in thousands of Item 5 800 650 pesos): Item 6 500 380 Unit Price Item 7 25 15 Qty AAE Contract Item 8 3,000 4,200 Item 1 100 1,000 800 Item 2 50 10,000 12,000 Item 3 500 5,000 6,000 -END- Item 4 60 6,000 5,000 Item 5 1,000 3,000 2,500 Item 6 400 1,500 1,600 Item 7 3,000 2,000 1,800 Item 8 20 25,000 30,000
12. What is the total AAE?
13. What are/is considered as major item/s? 14. Assuming that a Change Order is necessary for item 5, what will be the maximum allowable increase in contract amount?