Total hours 71

October 8 and 9, 8am - 8pm

Took down all the wall hanging

Shut off water to the sink

Removed the sink and vanity

Removed shower head and tub spigot

Removed shower walls and tub

Added new water shutoff valves to shower water lines

October 15, 8am - 5pm /October 16, 12pm - 4pm

Removed sheet rock

October 29 - 30, 8 am - 4 pm

Cut out old tub / shower drain, and removed drain to new location

November 5 - 6, 8am - 4pm, 11am - 4pm

Built frame for shower and insulated the stud wall of shower enclosure

November 12, 8am - 3pm, November 13, 12pm - 3pm

Installed the shower base and shower walls

December 3 - 4, 8am - 6pm, 12pm - 3 pm

Installed new electrical boxes

Light switch

Light outlet

Receptacle box

Exhaust fan housing

Ran romex between boxes and fixtures

Decmber 10 - 11, 8am - 1pm


Insulated the rest of the stud wallls

Installed sheet rock, cutting out around the electrical and plumbing openings coming out of the stud walls

Holesawed sheet rock for lights

March 18-19 8am - 3pm

Mud and tape