Inspection of completed construction activity before handover to pre-commission
inspection activity usually contains these major points to satisfy
1. All piping components are installed or re-installed in their respective locations as shown in the P&ID. (i.e.:
Piping, removable pipe spools, valves, vents, drains, spectacle plates, blinds, flange spacers, etc)
2. All in-line equipment & Instruments are installed or re-installed in the respective locations as shown in the
P&ID. (i.e.: Strainer, meter tube, straightening vanes, flow meter, orifice fitting, Pressure Indicators,
Temperature, Temperature Indicators, sample probes, etc)
3. Pressure and temperature gauges installed are of the same range as shown in the P&ID.
4. Test plug to be seal welded. (if required)
5. Jack screw bolts installed in flange with spectacle plates. (NOTE : Not required if flange spreaders are
supplied.)
7. Gasket material shall be verified by visually with piping specification on reinstated flange
8. Bolt and Nut material shall be verified by visually with piping specification on reinstated flange
10 The pipe shall not be used to support other pipes and structures without an appropriate analysis.
11. Access is provided for equipment regularly operated or maintained or operated in an emergency, such as
valve hand wheels, instrumentation, controls, and their associated manifolds.
12. Safety yellow-and-black stripes are painted on obstructions that present bump hazards. (Concrete supports
at the base of stairways or ladders, passageway pinch points, unguarded edges, tripping hazards).
13. Lifting equipment and devices shall be painted safety yellow and clearly marked with the rated capacity of
the equipment in metric tons.