Construction Procurement Methods

A key decision for any developer client Design and Build


commencing a construction project is In design and build procurement, the
how the project should be procured or, contractor assumes responsibility for
in other words, what contractual both the design and the construction of
structure should be adopted. the works. The client will usually engage
a team of consultants to produce a
The two most common procurement preliminary design for the project. The
methods are “traditional” and “design design consultants are then typically
and build”. novated to the contractor so that they
can assist the contractor in developing
Traditional the preliminary design.
The traditional procurement route keeps
the design and construction elements of The main selling point of design and
the project separate. The client directly build is single point responsibility. If
employs both a team of professional something goes wrong, the contractor
consultants to design the project and a should be the client’s first and only port
contractor to build to that design. An of call. However, to guard against the
architect or project manager will be risk of contractor insolvency, the client
appointed to administer the building should take additional security in the
contract for the client. The contractor form of collateral warranties from
has no design responsibility unless the novated consultants and sub-
parties agree that he will design a contractors.
discrete portion of the works.
Design and build projects can be
A key benefit of traditional procurement commenced more quickly than those
is that the client has a high level of which are traditionally procured because
control over the project because he the client can go out to tender with
directly employs each designer and the outline design requirements. However, if
contractor. This allows the client to keep the client’s requirements are not well
a close eye on how his requirements for developed, the client may be
the project are being implemented. Hawkswell Kilvington
disappointed with the end result.
Traditional procurement can also 17 Navigation Court
provide the client with a reasonable Although design and build projects can Calder Park
degree of cost certainty, as the design of provide reasonable cost certainty due to Wakefield
the project should be largely complete at WF2 7BJ
them often being procured on a lump-
tender stage to allow the contractor to sum basis, there is a risk that the quality 90 Long Acre
price for it. of the project could be compromised if Covent Garden
the contractor’s tender price turns out to London
However, since construction cannot WC2E 9RZ
have been too low, because this will
begin until the professional team have incentivise the contractor to cut costs. T: 0844 809 9566
completed their designs, traditional E: enquiries@hklegal.co.uk
procurement can take some time. Want to know more? W: www.hklegal.co.uk
Another potential disadvantage of As a specialist construction law firm, This bulletin contains information of
traditional procurement is that if Hawkswell Kilvington can work in general interest about current legal
something goes wrong with the project, partnership with your commercial issues, but does not provide legal
advice. This bulletin should not be
the client is likely to have to pursue property team, allowing you to offer relied upon in any specific situation
claims against multiple different parties your clients a full property and without appropriate legal advice. If you
in order to recover damages. require legal advice on any of the
construction service whilst giving you issues raised in this bulletin, please
peace of mind that you will not lose your contact one of our specialist
property clients to us. construction lawyers.