ESTM 1270

Critical Path Method - Class Example 2

For the following schedules;


 Draw the network diagram for a project consisting of the tasks listed.
 Calculate the ES/EF/LS/LF/FF for the project.
 Label and identify the Critical Path (the Sequence by ID)

1. ID Duration Predecessor
ST 0 n/a
A 3 Start
B 2 A
C 1 A
D 1 A
E 3 B,C
F 2 D
G 1 E
H 2 E,F
I 2 G,H
END 0 I