Estimation of Construction cost of Residential Buildings

Area Sq. m. 75 Apply to 30-300 Sq m Apply up to 100 sq.m


Load Bearing str. For Four Story
Materials Unit Rate For Single Rate Analysis For Double Rate Analysis RCC Frame Rate Analysis
super sub
Bricks No. 2.5 23630 59075 22425 56062.5 11180 27950
Cement tone 4400 12.045 52998 11.415 50226 13.3 1.516 65190.4
Steel kg 35 1283.5 44922.5 1342.75 46996.25 3384 382.875 131840.625
Sand cum 350 28.25 9887.5 22.6 7910 26.695 2.7 10288.25
20mm cum 250 12.99 3247.5 13.14 3285 21.375 5.315 6672.5
40mm cum 350 12.375 4331.25 6.405 2241.75 1.1625 0.0525 425.25

Brick Aggr cum 600 7.645 4587 3.78 2268 1.596 957.6

Tiber Frame and Shutter cum 32000 1.655 52960 1.655 52960 1.61 51520
Timber Shuttering cum 32000 0.315 10080 0.315 10080 0.645 0.0525 22320
Ballies m 15 37.8 567 37.8 567 65.09 2.76 1017.75
Lime quintal 220 10.525 2315.5 5.305 1167.1 4.645 1021.9
surkhi cum 33 3.53 116.49 1.77 58.41 0.75 24.75
Bitumen kg 20 128.7 2574 64.85 1297 26.915 538.3
Glass sqm 120 4.07 488.4 4.07 488.4 4.14 496.8
Primer lt 15 5.1 76.5 5.1 76.5 5.135 77.025
Paint lt 20 8.37 167.4 8.37 167.4 8.305 166.1
Stone rubble cum 600 2.4 1440

Labour

Mason Days 250 128.125 32031.25 126.125 31531.25 123.25 1.725 31243.75
Carpenter Days 300 79.8 23940 80.55 24165 120.75 3.75 37350
Painter Days 200 66.75 13350 6.675 1335 6.75 1350
Blacksmith Days 250 9.175 2293.75 16.55 4137.5 58.275 14568.75
Mazdoor Days 150 389.675 58451.25 401.25 60187.5 402.55 25.725 64241.25
378460.29 357207.56 470701

Water supply , plumbing , drains 20%--> 75692.058 71441.512 94140.2


electrical wiring (20%) No. of Storey 1 2 4
Total Cost 454152.348 857298.144 2259364.8
Estimation of Construction cost of Residential Buildings

Area Sq. m. 80 Apply to 30-300 Sq m


Load Bearing str.
Materials Unit Rate For Single Rate Analysis For Double Rate Analysis

Bricks No. 2.5 24760 61900 23500 58750


Cement tone 4000 12.81 51240 12.14 48560
Steel kg 35 1390 48650 1452.6 50841
Sand cum 350 30.6 10710 24.48 8568
20mm cum 250 13.87 3467.5 14.03 3507.5
40mm cum 350 13.1 4585 6.78 2373

Brick Aggr cum 600 8.21 4926 4.06 2436

Tiber Frame and Shutter cum 32000 1.75 56000 1.75 56000
Timber Shuttering cum 32000 0.336 10752 0.336 10752
Ballies m 15 40.32 604.8 40.32 604.8
Lime quintal 220 11.25 2475 5.67 1247.4
surkhi cum 33 3.79 125.07 1.9 62.7
Bitumen kg 20 137.88 2757.6 69.44 1388.8
Glass sqm 120 4.39 526.8 4.39 526.8
Primer lt 15 5.44 81.6 5.44 81.6
Paint lt 15 8.91 133.65 8.91 133.65
Stone rubble cum 600

Labour

Mason Days 250 134.8 33700 132.8 33200


Carpenter Days 250 85.72 21430 86.52 21630
Painter Days 150 71.2 10680 7.12 1068
Blacksmith Days 200 9.52 1904 17.92 3584
Mazdoor Days 150 413.52 62028 425.8 63870
388677.02 369185.25

Water supply , plumbing , drains 15%--> 58301.553 55377.7875


electrical wiring (20%) No. of Storey 1 2
Total Cost 446978.573 849126.075
per Sq Ft 595.971430667