Activity Description Immediate Predecessors

1 Lease the Site None

2 Hire the workers 1

3 Arrange for the Furnishings 1

4 Install the Furnishings 3

5 Arrange for the Phones 1

6 Install the Phones 4.5

7 Move into the Office 2,6,4

Table of ES,EF,LS,LF, Slack

Activity Earliest Start (ES) Earliest Finish (EF)

1 0 1
2 1 6
3 1 2
4 2 4
5 1 2
6 4 5
7 6 8
Time Network

1
Insert graphical NWP

2
(Nodes, Arrow) here

Latest Start (LS) Latest Finish (LF) Slack or Float

0 1 0
1 6 0
3 4 2
4 6 2
4 5 3
5 6 1
6 8 0