You are on page 1of 14

i!)BI
PRECAST/PRESTRESSED
Daniel P. Jenny Research Fellowship
CONCRETE INSTITUTE

The NU Precast/Prestressed
Concrete Bridge 1-Girder Series
Designers have experienced limitations when using existing
precast, prestressed concrete /-girders in continuous span
bridges. The Nebraska University (NU) girder series was re-
cently developed to overcome these limitations and to take
advantage of recent advances in precast concrete production
technology. The girder was developed in "hard" metric units
for optimal performance in a two-span bridge with full-length
continuity post-tensioning. In addition, the girder performs well
for pretensioned systems with continuity achieved by mild
K. Lynn Geren steel reinforcement in the cast-in-place deck, and in simple
Graduate Research Assistant span applications. The NU girder has a wide bottom flange to
University of Nebraska-Lincoln enhance the compressive strength in negative moment re-
Omaha, Nebraska
gions for continuous span designs, and to allow placement of
a large number of strands in the bottom flange for simple
span designs. This is particularly helpful when high strength
concrete is used. The relatively long span capability and shal-
low depth of the NU girder makes it an economical alternative
in situations previously reserved for structural steel girder sys-
tems. This paper presents a short history of precast, pre-
stressed concrete bridge /-girder development, the procedure
undertaken to develop the NU girder series, performance
comparisons with several existing standard girder shapes,
and the steps taken by the Nebraska Department of Roads
(NDOR) to implement the research results.

Maher K. Tadros, Ph.D., P.E.


n the Uni ted States, precast, pre- bridge . However , as precast, pre-

I
Cheryl Prewett Professor
of Civil Engineering and stressed concrete !-girders were first stressed concrete girders were used
Director, Center for Infrastructure used in bridge applications in the more freq uently in bridges, several
Research early 1950s. Today, they have become states began to adopt their own stan-
University of Nebraska-Lincoln
Omaha, Nebraska the most widely used girders in the 70 dard girder section shapes.
to 120 ft (2 1 to 36 m) span range. 1 In 1956, the B urea u of Publ ic
During its early stages of develop- Roads, known today as the Federal
ment, a different girder shape was de- Highway Admi nistration (FHW A),
signed and manufactured for each new adopted its own standards for precast

26 PCI JOURNAL
concrete I-girders. 2 These shapes, now
known as the AASHTO girders, are il-
lustrated in Fig. 1 with complete di- 12"

,:{~~~;,
mensions and section properties con- 12"
tained in Appendix A. bo5~
45"
Significant savings were realized as (1 143)
a result of standardization. However, 28"[_516 ..
(711) ~52)
standardization has tended to inhibit
the advancement of the design of pre- 16"
cast, prestressed concrete bridge gird- I(4o6> I ~
(457)
ers. Since the introduction of the AASHTO Type I AASHTO Type II AASHTO Type Ill
AASHTO V and VI shapes, evolution
toward increased structural efficiency
has been very slow. This is due, in
part, to the fact that precasters, having
made an investment in particular
forms, are reluctant to purchase addi- 72"
63" (1 829)
tional forms to make newer girder 54" (1600)
8"
shapes available to local markets. (1 372)
The financial incentive to optimize
the shape is further hampered by the
fact that the older, less efficient shapes
are still generally less expensive than
the competing structural steel shapes. AASHTO Type IV AASHTO Type V AASHTO Type VI
Also , engineers and de signers are dimensions in () are in millimeters
sometimes reluctant to use new girder
shapes when they have had success Fig. 1. AASHTO girders.
with older, well established girder
shapes. One example that highlights
this situation is the Washington bulb
tee developed by Arthur R. Anderson
in 1959. This shape was not adop-
ted as the AASHTO/PCI bulb tee stan-
dard shape until 1988 - nearly 30
years after its introduction. 3 .. This
AASHTO/PCI bulb tee is a slightly
72"
modified version of the girder shape (1 829)
54"
developed by Anderson (see Fig. 2 (1 372)
and Appendix A).
Some states have continued to rely
on the federal standards while other
states pioneered their own girder
shapes. This uncoordinated evolution (660)
has resulted in significant diversity in dimensions in () are in millmeters
the girder shapes that are used from
state to state throughout the nation. Fig. 2. AASHTO/PCI bulb tees.
Currently, many states specify the use
of AASHTO Types III, IV, V, and VI
or similar girders in their standard the Washington and Colorado shapes areas where under-clearance was a
bridge plans, despite the existence of (see Fig. 3 and Appendix A) can be at- critical concern. In addition, the girder
more efficient girders such as the tributed to the availability of aggre- was required to withstand large pre-
AASHTO/PCI bulb tee (see Fig. 2 and gates that allow easy production of stressing forces, leading to its relative
Appendix A). higher strength concrete and to the bulkiness. ' Pennsylvania's modern
Differences in available local mate- technology developed by the local fab- standard sections, though deeper, have
rials, as well as in the technology ricators that allows excellent consoli- retained their characteristic bulky
available in different geographic re- dation of concrete. flanges.
gions, have also brought about diver- In eastern states such as Pennsylva- These and the other factors men-
sity from state to state in girder nia, very shallow girders were neces- tioned above have contributed to the
shapes. For example, the thin webs of sary to compete with structural steel in diversity in girder shapes. In Fig. 3,

May-June 1994 27
73.5"
72' 78.7"
(1 867)
(1 829) (2000)
68.0"
(1 728)

Washington Series 14 Bulb Tee ColoradoG72

Canadian Girders

72" 75"
70.9" (1905)
(1 829) (1800)

I· ~Jf!; ·I I• (610)
24"

I
Florida BullrTee Girder Proposed Kentucky State Girder
Nebraska Type 4A
dimensions in () are in millimeters dimensions in () are in millimeters

Fig. 3. Standard girders used by individual states.

examples of shapes used by a number CURRENT AND requirement for longer spans is the
of states and Canadian provinces are EMERGING DESIGN highway overpass. In the past, these
given. Complete dimensions and sec- bridges were constructed in four rela-
PRACTICES tively short spans of 60 to 80ft (18 to
tion properties of these girders are
contained in Appendix A. The Cana- Design for continuity in bridges is 24 m) each. Now, federal highway
dian girders are produced by Con- increasing for several reasons. The regulations call for the elimination of
Force Structures Limited for use in most common reason for introducing the shoulder piers. This change re-
British Columbia. continuity is to eliminate expansion quires that the bridge be constructed
In the near future, all projects in- joints in the deck. Experience has of two spans. To continue to gain mar-
volving federal participation will be shown that joints in a bridge deck re- ket share, it is essential that precast,
required to use metric units. 6 Although quire costly maintenance. When these prestressed concrete girders stretch to
girders with "soft" metric units will be joints are eliminated, the bridge deck lengths previously reserved for struc-
usable, the girder discussed here was is made continuous and the girders are tural steel.
designed in "hard" metric units, where connected longitudinally with cast-in- Although most existing standard
the actual dimensions are in round place joints. Thus, they act as continu- girders are being used in continuous
metric figures since new forms are re- ous beams for loads applied subse- bridges, they were initially designed
quired anyway . quent to the joint gaining adequate for use in simple span structures. In
Response to the survey conducted as strength, such as superimposed dead co ntinuous applications, the girders
part of this project revealed there is and live loads. are subj ected to negative bending mo-
now considerable interest, among Another major reason for introduc- ments at levels that often control their
bridge design professionals and fabri- ing continuity is that it allows a given design , especially when the girders are
cators, in the development of an opti- girder to span greater lengths than if it made continuous before the cast-in-
mum girder shape for continuous were simply supported. Engineers are place deck weight is introduced. Insuf-
spans . This response leads to opti- being challenged to design bridges ficient compression area in the bottom
mism regarding expeditious imple- with longer spans and improved seis- of the girder and web widths too small
mentation of the NU girder series. mic resistance. A good example of the to accommodate continuity post-

28 PCI JOURNAL
tensioning are common limitations to
0.8 L 0.2L l.OL
increased span length and/or trans- 'I
' I
verse girder spacing. An exception Post-tensioning continuity t~ndon
to this is the Florida bulb tee (see Fig.
3). It is the only existing standard
girder developed for continuous spans
and is believed to be one of the most Pretensioned Strands
efficient girders available today.
There are many ways in which con-
tinuity has been achieved in precast 7.5 in. (191 mm)
concrete girder bridges . The most
widely used method for achieving con-
tinuity is to place conventional mild
steel reinforcement in the cast-in-place
deck to resist the negative moment
over the pier. This is the most conve-
nient splicing method; however, the
Splice of PIT ducts
span is limited to the length of girder Partial Cross-Section at Interior Girder
that can be transported to the construc-
tion site and the continuity is only ef- Fig. 4. Span configuration and post-tensioning layout of system used in
fective for a small portion of the total shape optimization.
dead load plus the live load. State
transportation agencies have limita- girders continuous are described in de- mization of precast, prestressed con-
tions based on length and/or weight. In tail in Refs. 7 and 8. crete bridge girders was developed by
most areas of the United States, Lounis and Cohn." This is a v!lluable
this limits the maximum span to about theoretical approach since it rationally
120 ft (37 m). One drawback to this RESEARCH OBJECTIVES produces information on the relative
type of construction is that cracks de- AND PLAN importance of various cross section
velop near the top surface of the deck components for given design and cost
The main objective of this project
in the pier area due to negative conti- criteria. This study was done for simple
was to develop a metric precast, pre-
nuity moments. Exposure of the cracks spans, 10 to 45 m (32.8 to 147.6 ft),
stressed concrete girder that is not
to traffic and de-icing chemicals can only structurally efficient, but one that with pretensioned concrete girders.
promote rapid deck deterioration. It showed that at the give n span
is as easy as possible to manufacture,
The second method that is becoming transport and erect. The girder devel- range the maximum feasible girder
more widely used is full length post- oped must produce a cost effective spacing is 3.38 m (11.1 ft) with a min-
tensioning (see Fig. 4). Resistance to bridge system - including girder, imum deck slab thickness of 225 mm
negative bending moment•. as well as slab, substructure and approach. (8.9 in.), and that the optimal design
to positive bending moment, is pro- does not necessarily require maximum
vided by post-tensioned tendons that tendon eccentricity. The findings of
are stressed after placement of the Previous Studies
this study were considered in this pro-
cast-in-place diaphragm and, often, A report by Rabbat et al., in 1982,9 ject. However, emphasis was placed
after the deck is placed. This provides focused on existing standard girder on aspects relating to continuous span
greater resistance to loads and allows sections and analyzed the structural ef- design , multi-stage prestressing (i.e.,
longer spans than the conventionally ficiency and cost effectiveness of these pretensioning combined with post-ten-
reinforced joint. Cracking in the deck girders when used in simple span sioning), impact of top flange width
over the pier is virtually eliminated. structures. The study demonstrated that on deck slab design, and girder fabri-
When full-length post-tensioning is the AASHTO/PCI bulb tees were the cation, transportation and erection.
provided, significantly fewer preten- best shapes available for simple span
sioning strands are required for posi- applications and that increased girder
tive moment resistance. Pretensioning spacing provides improved superstruc- Parametric Study
is required only to support the weight ture economy . The Florida bulb tee, A computer spreadsheet was devel-
of the girder itself and the weight of developed by the Florida Department oped to perform a parametric study to
the cast-in-place deck, if it is placed of Transportation in the mid-1980s 10 determine the most structurally effi-
before post-tensioning. The reduced was the result of further develop- cient section. Survey responses from
pretensioning requirement can help re- ment of the AASHTO/PCI bulb tees to nearly 90 state engineers, bridge con-
duce excessive camber and the need account for continuity by post- sultants, precast manufacturers and
for high strength of concrete at release. tensioning. This project expands on the form makers led the authors to weigh
Several other methods that have work presented in Refs. 9 and 10. heavily the non-quantifiable issues
been used to make precast concrete An approach to mathematical opti- concerning girder fabrication, trans-

May-June 1994 29
)

Table 1. Relative costs used for girder comparison. design experts toward greater empha-
sis on ultimate strength criteria,
Item Cost
strength design was used for optimiza-
Precast girder concrete - including all reinforcing bars, labor, and overhead $320 per cu yd tion. "Working stress" or "service
Accessories and hauling - includes PVC, coil ties, coil rod, bearing pads, load" allowable concrete stresses were
bearing plates, lifting loops, prestress hold-downs and transportation $ 1075 per girder satisfied at all construction stages.
Girder prestress - strand, labor and overhead $1.14perlb With these criteria, structural effi-
Post-tensioning - materials, labor and overhead $1.50 per lb ciency is maximized when the girder
Cast-in-place deck $200 per cu yd shape simultaneously reaches ultimate
$0.55 per lb
strength capacity in both the positive
Mild steel reinforcing bars (includjng epoxy coated bars)
and negative moment regions under
Note: I lb =0.4536 kgf; I cu yd =0.7646 m3.
dead load plus maximum live load
conditions.
portation and erection. For example, Concrete stresses specified in Subsec-
limitations were placed on the bottom tion 9.15.2 of the AASHTO Standard
FEATURES OF THE
slope of the top flange to allow ease of Specifications for Highway Bridges' 2
form stripping during fabrication, on were used with the exception that the OPTIMUM GIRDER SHAPE
the edge thickness of the top flange to allowable compression stress after The proposed Nebraska University
prevent damage during transportation losses was taken to be 0.60J;, where Girder Series is shown in Figs. 5 and
and handling, and on the maximum fd is the compressive strength of the 6. T he new shape is designated:
width of the bottom flange to accom- concrete at 28 days. NU2000 for Nebraska University,
modate existing precasting beds. Cost Superimposed dead load of 23 psf 2000 mm (78.7 in.) deep; NU2000PT
considerations were a controlling fac- ( 1.1 kPa) was assumed. HS-25 truck designates a section with widened web
tor in the identification of the opti- loading was used in the analysis with for post-tensioning applications.
mum girder shape. impact and distribution factors com- For all the girders examined in the
Girder optimization was based on puted pursuant to AASHTO Subsec- parametric study, the factor limiting
analysis of an interior girder in a con- tions 3.8.1 and 3.23.2.2, respectively.' 2 the maximum span length achievable
tinuous bridge of two equal spans. The Cost analysis was based on average at a given girder spacing was the max-
design adopted the system featured in relative values provided by precast imum reinforcement index in the neg-
the appendix to Ref. 7. The system concrete manufacturers from across ative moment section, as described
consists of a double cantilever pier the United States. These costs are tab- below. Up to these maximum achiev-
segment and two field segments that ulated in Table 1. Note that these are able span lengths, service load stresses
are initially erected as simply sup- costs used for comparison between were within allowable limits. There-
ported. The girders are made continu- precast girders in this study. They are fore, optimization depended heavily
ous by a cast-in-place splice and full not intended to be used to predict the on increasing the available compres-
length post-tensioning as illustrated in actual cost of construction. sion area in the bottom flange to keep
Fig.4. The 0.5 in. (12.7 mrn) diameter, 270 the reinforcement index below the
For purposes of optimization, the ksi (1862 MPa), low-relaxation pre- maximum allowed.
girder shape and span length were tensioning strand was assumed to re- Early in the project a non-prismatic
made variable with a constant girder sist 1.2 times the unfactored girder and shape was considered. However, a
spacing of 10 ft (3 m). The length of deck slab weight to provide a factor of prismatic shape was finally selected
the field segments was determined safety for the additional flexural for ease of fabrication, handling and
such that the midspan of the field seg- stresses due to transportation and erec- transportation; difficulty in standardiz-
ments corresponded with 4/IO of the tion and to provide allowance for con- ing shape transition and widespread
total span length. In this way, the struction loads. The 0.6 in. (15 .2 mm) industry resistance to non-prismatic
points of maximum flexure during diameter, 270 ksi (1862 MPa), low- girders were also factors. This deci-
shipping and erection correspond with relaxation post-tensioning strand was sion prevented a "perfect" solution in
the points of maximum flexure in the designed to resist the remainder of the which ultimate strength capability is
final structure. This allows the most loads. Initial stress of 189 ksi (1303 reached simultaneously in both maxi-
efficient use of flexural reinforcement. MPa) was assumed in all prestressing mum positive and negative moment
Precast girder concrete strength was strands, with assumed pretensioning sections at the maximum achievable
taken as 4000 psi (27.6 MPa) at re- loss of 10 ksi (69 MPa) at erection of span length.
lease and 6000 psi (41.4 MPa) at 28 the girder and additional loss of 19 ksi Due to the importance of the depth of
days. The 7.5 in. (191 mm) cast-in- ( 131 MPa) due to time-dependent ef- the girder and its impact on substruc-
place deck concrete strength was taken fects at the final stage. Assumed post- ture and approach costs, an effort was
as 3000 psi (20.7 MPa) at 7 days and tensioning loss due to time-dependent made to minimize the girder depth re-
3500 psi (24.1 MPa) at 28 days. Both effects was 29 ksi (200 MPa) at the quired to achieve a given span length.
girder and cast-in-place concretes final stage. Also, for the same span length and su-
were assumed to be of normal weight. Due to the trend of concrete bridge perstructure depth, the higher load ca-

30 PCI JOURNAL
of the depths as needed for its use.
For example, NDOR has adopted for
immediate use NUl!OO, NU1350 and
NU2000 girders. It also anticipates
eventual use of the NU1600 and
NU2400 girders . It should be noted
that the top and bottom flange dimen-
2000 sions are identical for the entire se-
(78.7) ries. This allows the use of only one
set of forms with web extension pan-
els. The concrete surface "seams" at
form panel joints have not been found
to be aesthetically objectionable.
(38.4)
Aesthetics is becoming a greater
concern, and many designers are of
Pretensioned System Post-Tensioned System the opinion that I-girders are less at-
NU2000 NU2000PT
(midspan prestress layout) (midspan prestress layout) tractive than box girders. This is
mainly because the sharp angles where
dimensions are expressed as mm(in.)
flanges join the web and on the out-
Fig. 5. Dimensions of the NU girders. side edge of flanges are considered
unsightly, especially when viewed
under bright sunlight. In an effort to
improve its appearance, the NU girder
series wa s designed with circular

XX
curves, rather than sharp angles at the
edges of the flanges and at the points
where the flanges join the web. The
circular curves at the junctures of the
1350 (53.1)
flanges and the web have a radius of
750 (29.5) 900 (35.4) 1100 (43.3)
200 mm (7.9 in.); at the outside flange
edges, the radius is 50 mm (2 in.). An-
other important benefit of the circular
curve between the web and the bottom
flange is that it facilitates placement
and consolidation of concrete.
The cross-sectional area of the bot-
tom flange is the most important factor
in determining the maximum achiev-
able span length of a given girder. In
the negative moment area the limiting
24 00( 94.5)
factor was the maximum reinforcement
1600 (63.0) 1800 (70.9) 2000 (78.7)
index, as dictated by AASHTO Sub-
dimensions are expressed as mm(in.) section 9 .18.1'2 and the requirement in
Subsection 18.8.1 of the ACI Building
Fig. 6. The NU girder series.
Code and Commentary.13
The maximum reinforcement index
pacity of the NU girder is beneficial in projects that were originally con - in the ACI Code corresponds to
bridge replacement applications. structed with existing girder shapes. 0.85a!dP ~ 0.36./3 1, where a is the depth
This study was initially conducted Further investigations have resulted in of the rectangular compression block,
on a series of girder depths beginning the following series of depths : 750, dP is the distance from the extreme
at 1600 mm (63 in.) and increasing in 900, 1100, 1350, 1600, 1800, 2000, compression fiber to the centroid of
400 mm (15 .7 in.) increments up to and 2400 mm (29.5, 35.4, 43.3, 53.1 , the prestressed steel, and./3 1 is the ratio
2800 mm (110 in.). However, after 63, 70.9, 78.7, and 94.5 in.). of the compression block depth to the
presentation of the results to several The new depths will add flexibility neutral axis depth . The National Co-
state agencies, it became apparent that because of the smaller increments be- operative Highway Research Project
a strong need exists in the entire range tween depths, and because of the 12-33 resulted in new bridge design
of existing !-girder depths and that close match with existing girder specification s known as the LRFD
new girder depths should be suitable depths used by most states. Obvi- Specifications.'• In the LRFD Specifi-
for bridge replacement and widening ously, each state would adopt as many cations, Section 5.7.3.3, this relation-

May-June 1994 31
ship is cld. ~ 0.42, where c is the neu- ing bearing pads for wide flanged mild steel reinforcement and perhaps
tral axis depth = a/j3 1 and de is the ef- girders. A pad that is as wide at the draped pretensioning strand. Several
fective depth of the combined pre- bottom flange is not only unnecessary, manufacturers and bridge designers
stressed and non-prestressed steel but also may cause splitting in the have offered their assurance that ,
areas. Due to difficulty in determining flange. It is recommended that the pad based on experience with a number of
d. , the authors chose to rely on re- width not exceed 24 in . (610 mm). recent projects, there would be no dif-
search performed by Skogman et al. 15 This width is comparable to that used ficulty with concrete placement in this
In their report, Skogman et al. have with AASHTO standard girders. situation . In fact, recent bridges in
shown that the maximum reinforce- The slope of the top part of the bot- Canada, notably the Esker Overpass, 17
ment index can be approximated by tom flange was dictated by two conflict- have 150 mm (5.9 in.) webs. It should
c/h ~ 0.36; where h is the total girder ing requirements. It had to be as shal- be noted that a narrower or wider web
depth . This limit gives identical results low as possible to keep the maximum can be easily manufactured by moving
to those of the LRFD Specifications concrete area low in the girder to gain the side forms inward or outward.
when de = 0.86h. the greatest structural efficiency. On the The study has shown that the top
It was found that for a given total other hand, it had to be steep enough to flange area should be minimized and
cross-sectional area and a given bot- allow good consolidation of concrete. its width maximized. A large cross-
tom flange area, the girder with the Extensive investigation of current prac- sectional area in the top flange has
wider bottom flange has better struc- tices convinced the researchers that a been found unnecessary. The concrete
tural efficiency . This is because a slope of about 1 to 3 was practical, i.e., deck , in composite action with the
greater number of pretensioning 140 mm (5.5 in.) vertically over a hori- girder, provides the required compres-
strands can be placed in the bottom zontal distance of 412.5 mm (16.2 in.). sion resistance. By minimizing the
row of the wider flanged section and It should be kept in mind that the area of the top flange, significant sav-
thus at the greatest eccentricity from widespread use of superplasticizers and ings in costs can be made.
the centroid of the concrete section. improved production techniques make The wider the top flange, the
This allows the wider flanged section a unnecessary the very steep 1 to 1 slope smaller the effective span length of the
greater positive moment resistance for of early girder shapes. deck for a given cross-sectional area.
a given area of pretensioning strand. This study has confirmed earlier This reduces the required deck thick-
The drive toward longer spans and studies that structural efficiency is in- ness and material costs. In addition,
wider girder spacing has caused an in- creased when the web width is de - the wider top flange reduces the form-
creased use of high strength concrete. creased . The web of the proposed work cost of the deck slab and pro-
This increases the required pretension- girder was thus set to accommodate vides a convenient worker platform
ing force and thus the area of preten- the required reinforcement: a 75 mm during construction.
sioned steel. To accommodate this , (3 in.) diameter post-tensioning duct, The top flange should not be too
specification of 0.6 in. (15.2 mm) two 12.5 mm (0.5 in.) draped preten- wide, however. Wide top flanges re-
diameter strand instead of 0 .5 in . sioning strands, 12.5 mm (0.5 in.) di- quire additional cast-in-place concrete
(12 .7 mm) diameter strand is likely ameter stirrups for shear reinforce- to accommodate cross-slope and su-
to increase in the future. This is consis- ment and two 25 mm (1 in.) concrete perelevation of the deck. Also, wide
tent with the trend in Japan 16 and else- covers - a total of 175 mm (6.9 in.). top flanges must have increased aver-
where. The additional bulk in the bot- It is not necessary to use strand drap- age thickness if the bottom surface
tom flange of the NU girders allows ing, especially when post-tensioning is slope is to be maintained for conve-
them to accommodate the increased utilized. Debonding (shielding) of nience in forrnwork removal. The NU
area of strand and resulting pretension- some of the strands at girder ends is a girder has a top flange width of 1250
ing forces better than existing girders. cost-effective method of satisfying mm (49.2 in.). This is approximately
For the greatest structural efficiency, working stress design requirements. the same as the Florida bulb tee, 183
the bottom flange was made as wide as When no draped strands are used, a 50 mm (7.2 in.) wider than the AASHTO/
can be accommodated in existing mm (2 in.) wide space becomes avail- PCI bulb tee and 742 mm (29.2 in.)
plants. The edge thickness is deep able for larger post-tensioning ducts wider than the AASHTO Type IV.
enough to allow two rows of preten- and/or clear cover. The NU girder top flange edge
sioning strands at 2 in. (50.8 mm) on Some bridge design professionals thickness was initially set at 75 mm
center with 2 in. (50.8 mm) of vertical have expressed concern that the web (3 in.) and later reduced to 65 mm
and horizontal concrete cover. This al- width of 175 mm (6.9 in.) is too thin. (2.6 in.). Some bridge designers are
lows enough area for sufficient strand Many designers have not used girders uncomfortable with a top flange thick-
to be placed when using the girder in with webs less than 8 in. (203 mm) ness of less than 3 in. (76.2 mm) de-
an application in which pretensioning wide and are uncomfortable with the spite the record of the Florida bulb tee,
only, with no post-tensioning, is used. thinner webs. Others are concerned which has a top flange edge thickness
This results in a bottom flange width that precast concrete manufacturers of only 2 in. (50 mm). A thicker edge,
of 1000 mm (39.4 in .) and an edge will have difficulty with concrete if required, can be easily accommo-
thickness of 135 mm (5.3 in.). placement in the thinner webs that dated by minor adjustments of the top
Caution must be taken when design- contain post-tensioning hardware, flange edge forms.

32 PCI JOURNAL
being performed at the University of
Minnesota by Dr. French and her asso-
1225 . ciates. The longer spans achievable by
use of high strength concrete require
an increased number of prestressing
strands. The NU girder is better suited
for use with high strength concrete
than existing standard girders due to
its bulky bottom flange that allows
20mm cl. accommodation of a large number of
( +3, -0) prestressing strands.
Conventional, non-prestressed rein-
forcement is required for such effects as
vertical shear, horizontal composite
action shear, end zone stresses, confine-
ment of bottom flange concrete and
transverse bending of the top flange.
0
0 Traditionally, individually tied reinforc-
0
N ing bars have been used for !-girders.
The recent success of the use of
welded wire fabric in double tees and
WWF1, WWF2 OR WWF3 some box girder sections has led to
consideration of its use in 1-girders. In
cooperation with HDR Engineering
Inc. , the authors developed the details
shown in Figs. 7 and 8. Most of the re-
inforcement, with the exception of the
#3 "cap" and end zone reinforcement
WWF4
(not shown), consists of prefabricated
welded wire fabric. These details have
I WWF4
been found to meet all design require-
975
ments for the Valley West Bridge, the
TYPICAL SECTION REINFORCEMENT - NU 2000
design of which ha s recently been
completed in Nebraska. The project
features NU2000 girders with spans
Fig. 7. Auxiliary reinforcement details. ranging from 135 to 150 ft (41.1 to
45 .7 m) and transverse spacing of 9 ft
7 in. (2.92 m).
The area of the top flange can be concrete strengths higher than the con- Welded wire fabric with the same
minimized while maintaining the de- ventional 5000 to 6000 psi (34.5 to size and spacing of wires has been
sired width and edge thickness by 41.4 MPa) will figure prominently in found to meet the requirements in
minimizing the slope of the bottom the future of 1-girder bridge construc- other bridge designs. When girders
surface of the top flange. Only a small tion . In fact, NDOR ha s recently wi,t:h a different depth are used, only
slope is required to facilitate stripping adopted a new standard girder strength the depth of the vertical mesh of the
of the concrete forms from the com- of 7500 psi (51.7 MPa) and cast-in- reinforcement need be adjusted. Use
pleted girder. The flange bottom slope place deck strength of 5000 psi (34.5 of welded wire fabric is expected to
was initially set at about 1 to 22. After MPa) , instead of the old 5000 and greatly simplify production. It is antic-
trial production of full-scale NU2000 3500 psi (34.5 and 24.1 MPa) values. ipated that standard sizes of welded
girder segments, this slope was in- Recent studies'9·" have concluded that wire fabric will emerge.
creased to 1 to 12. the use of high strength concrete in AASHTO requires that all vertical
Lateral stability of the NU girder prestressed girder bridges is not only steel reinforcement be extended into
was evaluated by Mast using a com- feasible but also economical, espe- the cast-in-place concrete deck. Some
puter model he developed. " His analy- cially when durability and life-cycle states require additional dowel rein-
sis for stability during transportation costs are considered. forcement near the outside edges of
and erection indicated that its perfor- The use of high strength concrete in wide flanges. This has been found un-
mance was superior to girders with bridge !-girders has been explored by necessary for horizontal shear resis-
narrower bottom flanges. Castrodale et al., 22 and a project in- tance or for composite action, and may
The girder concrete strength was not volving testing of full-sized high cause complications with future deck
varied in this study. Clearly, 28-day strength concrete bridge girders is removal and replacement.

May-June 1994 33
SPLICED POST-
TENSIONED GIRDER 2
WIRE OESIGNA TION AREA (in . 2 ) (mm )
PERFORMANCE
04 0.04 (26)
06 0.06 (39)
The following discussion demon- 08 0.08 (52)
strates how the proposed girder per- 014 0.14 (90)
forms relative to some of the com- 04 wires at
monly used girders in the United States 0 100mm ctrs.
0 (1080mm long)
and Canada. The two- span spliced-
girder system shown in Fig. 4 is used in
the comparisons in this section. The
Florida bulb tee and the girder pro-
posed for the state of Kentucky are be- f/)
Q) 014 wires WWF4
'-
lieved to be the most modem girders in "i (100mm ctrs. - WWF1)
the United States, specifically devel-
l()
(150mm ctrs. - WWF2)
N 0
c:::i 0 c (250mm ctrs. - WWF3)
oped for continuous post-tensioned CXl
<0
:0 08 wires at
.3 / 150mm ctrs.
bridge applications. Other sections are ·c;.
c
the Canadian girders, the AASHTO/ E
I I I 04 ct i
I I I
PCI bulb tee, and the AASHTO Type <0
L---J------I Iong_itudinal
VI. These girders were used for perfor-
0
~
w1res --r---+--j
mance comparisons. i 150 i 150 i 520 i 150. i .150. i
Each of the standard girders exam-
ined has a different web width. To pro- 1175 max.
vide a meaningful comparison between WWF5
the girders analyzed, the overall widths 0
0
were adjusted to produce a constant

. ~nw
web width of 175 mm (6.9 in.). The di-
mensions and section properties of the
girders with these modifications are
contained in Appendix A.
d~
WWF1, WWF2 & WWF3 (#3 Bar)
At a girder spacing of 10 ft (3 m),
the minimum deck thickness of 7.5 in.
(191 mm) governed for all the girders. Fig. 8. Auxiliary reinforcement details.
Due to this, the advantage of reduced
deck thickness associated with wider
top flanges has not been accounted for
in this analysis. The NU girder would Span length (m}
have compared more favorably had a 39.6 42.7 45.7 48.8

wider girder spacing been used.


In the bridge system analyzed, the -NU1800(70.91
-o-- Flo<iclaBT72" (1829nvn)
maximum reinforcement index in the - · - AASHTO Type VI (1829 mm)
negative moment section was the fac- Reinforcerrent index - AASHTDIPO BT 72" (1829 mm)

tor that limited achievable span length - Proposed Ksnlucky BT 1800 [70.91
~ Canadllol1728 (68.0")
for all girders considered. In Fig. 9, the
-Canadian 2000 mm [78.7j
relationship of the reinforcement index AI sections"wid1hs modified "produce
vs. span length for the girders is 175..., (6.91 ..t>.

shown. With the exception of the much 130 140 150 160
Span length (ft.}
deeper Canadian 2000 girder, the
NU1800 has the highest achievable Fig. 9. Reinforcement index vs. span length for the system in Fig. 4 with a girder
span length, 157 ft (47.9 m), even spacing of 10 ft (3 m).
though some of the girders have larger
cross-sectional areas.
The girders were also compared for BT 72" and the Canadian 1728 girders girder's economy comes primarily
the relative cost of a bridge super- are economical in the shorter span from the fact that it is 200 mm (7.9
structure constructed using each ranges . However, at approximately in.) deeper than the other girders pre-
girder. Fig. 10 shows the superstruc- the same depth of 72 in. (1829 mm), sented in Fig. 10.
ture cost at various span lengths and a the NU girder outperforms all other Another way to illustrate the capac-
constant girder spacing of 10 ft (3 m). girders in terms of overall span range ity and economy of the NU girder is
It can be seen that the AASHTO/PCI and economy. The Canadian 2000 presented in Table 2. The same as-

34 PCI JOURNAL
sumptions used in generating Figs. 9
Span length (m)
and 10 are used here, except the girder
2136.6 39.6 42.7 45.7 48.8
spacing is variable. Also, the proper- 226
ties of the Canadian 1728 and 2000 _..._ NU1800 (10.9')
girders were interpolated to produce a 20 215 --()-- -BT72" (1829nwn)
"Canadian 1800" shape in order to ~ MSHTO TJ110V1(182911111)
19 205
keep the depth of all girders constant. -+- MSHTOI!'CIBT72"(1829nwn)
cost ($/sq. ft.) cost ($/sq. m)
For a given span length, the table con- ~ Prapooed Konlucky BT 11110 (70.9')
18 194
tains the maximum spacing possible -+- c..flan 1728 (68.0')
for ~ach girder and the corresponding 17 183 -+-- ~2000(78. 7")

unit cost. AI_._,_.,...,.....


The table shows that the NU girder 16 172 175 ... (8.9') Wlb.

is more economical than other existing 120 130 140 150 160
Span length (ft.)
shapes when its full capacity is uti-
lized. It also demonstrates the possi- Fig. 10. Cost vs. span length for the system shown in Fig. 4 with a girder spacing
bility of using 1800 mm (70.9 in.) of 10 ft (3 m).
deep precast concrete girders to
economically span 170 ft (51.8 m)
at a reasonably wide spacing of 8 ft
(2.4 m). Obviously, longer spans are
Girder spacing (m)
possible. However, feasibility of trans-
1.8 2.4 3 3.7
porting the field segment, which is 80 150 .7
percent of the span length, must be
considered.
140 2.7

GIRDER PERFORMANCE 130

WITH CONVENTIONAL
DECK REINFORCING 120

BAR CONTINUITY Max span (II) Max spa~ (m)

110
The NU girders outperform existing
standard girders, even in systems with
pretensioned girders made continuous 100
by adding mild steel reinforcement in
the cast-in-place deck. In this system, 90
the majority of the load is applied to a
simple span configuration. Only the
superimposed dead load and the live 80 24.4
6.6 7.9 9.2
load are applied after co ntinuity is 6 8 10 12
achieved.
Gilder spacing (II)
The figures being referred to in the
following discussion make the same Fig. 11. Span capability vs. girder spacing for a two-span bridge with continuity
assumptions regarding material prop- achieved by deck reinforcing bars.

Table 2. Maximum spacing and corresponding unit cost for various span lengths of a two-span spliced girder bridge.
Span, ft 140 150 160 170
Spacing Cost Spaci ng Cost Spacing Cost Spacing Cost
Girder (ft) ($per sq ft) (ft) ($ per sq ft) (ft) ($ per sq ft) (ft) ($per sq ft)
NUI800 13.02 16.85 11.1 9 18.15 9.57 20.04 8. 15 22.39
Florida BT 72" 12.00 16.96 10.30 18.5 1 8.94 20.53 7.48 23.05
AAS HTO Type VI 13.38 17.53 11 .42 18.75 9.53 20.96 8.00 23.67
AAS HTOIPCI BT 72" 10.00 17.31 8.47 19.25 7.1 6 21 .67 6. 11 24.52
Proposed Kentucky BT 1800 12.47 17.31 10.7 1 19.10 9.08 2 1.22 7.82 23.40
Canadian 1800 11 .53 17.1 3 9.73 18.73 8.24 20.87 6.91 23.61

Note: I ft =0.3 m; $ 1.00 per sq ft =$ 10.75tm2.


May-J une 1994 35
CONCLUSIONS
Girder spacing (m)

1.8 2.4 37 43 1. Precast concrete 1-girder systems


200 61
are the most widely used methods for

180 ~ 54.9
constructing bridges in the 70 to 120 ft
(21 to 36m) span range .
..............
~ .......__
b)
2. The main objective of this study
~

--
180 ~.
48.8
~
r--.. ~ .......__ was to develop a metric 1-girder shape

--- --- ---


Max span (ft) Maxspan(m)
that is highly efficient in continuous
140 r-..... 42.7
span applications and that will extend
~
the span capabilities of the popular 1-
120 36.6
(a) pretensioned girders with deck rebar girder bridge system.
(b) pretensioned girders with continuity post-tensioning 3. This study has produced a new 1-
100 30.5 girder shape, called the NU girder, that
10 12 14 has dimensions in "hard" metric units
Girder spacing (ft)
and has the following main features:
Fig. 12. Span capability vs . girder spacing for two methods used for achieving (a) Girder depths of 750, 900, 1100,
continuity. 1350, 1600, 1800, 2000, and 2400 mm
(29.5, 35.4, 43.3, 53.1 , 63, 70.9, 78.7,
and 94.5 in.) that cover the entire
erties and loads as the comparison of ( 1829 mm) bulb tee. It can span up to range of depths;
Figs. 9 and 10, except that precast 160 ft (48.8 m) at 10 ft (3.0 m). The (b) Large bottom flange allowing in-
concrete strength at release was taken corresponding bulb tee span is 141 ft creased strand placement capacity for
as 5500 psi (37.9 MPa) and 28-day (43 m) (see Fig. 9). simple spans and increased negative
strength was 7500 psi (51.7 MPa); moment capacity for continuous spans;
cast-in-place deck concrete strength at (c) Constant top and bottom flange
7 days was taken as 4000 psi (27.6
IMPLEMENTATION dimensions for various girder depths
MPa) and 28-day strength was 5000 PLANS to allow the use of only one set of pan-
psi (34.5 MPa). The Nebraska Department of Roads elized steel forms, where web height
Fig. 11 demonstrates the relative is now specifying the use of NU gird- can be adjusted with addition or dele-
span capabilities of the Nebraska Type ers in all precast !-girder construction. tion of form panels;
4A, the AASHTO Type IV, and the In addition, it has awarded the Uni- (d) Wide top flange to allow for bet-
NU1350 girders. For a given span versity of Nebraska a two-year re- ter worker platform and shorter deck
length of 120 ft (36.6 m), the three search project to develop implementa- slab span; and
types can have spacing as much as 6.6, tion details. (e) Curves, rather than straight line
7.9, and 9.2 ft (2, 2.4, and 2.8 m), re- This project will comprise the com- ftllets, to allow for easy placement of
spectively. A good indicator of girder p letion of design details, including concrete and for improved bridge su-
efficiency is the equivalent solid slab shear, deflection and end-zone design. perstructure appearance.
thickness, which is the girder cross- Also required will be the preparation 4. The proposed NU girders have
sectional area divided by the spacing. of preliminary design aids that estab- been shown to span further than any
For the 120 ft (36.6 m) span consid- lish the girder size and spacing re- other standard !-girder shape in exis-
ered, the NU girder equivalent slab quired for given span and loading tence, which makes it a strong competi-
thickness of 6.82 in. (173 mm) is sig- conditions . The study will examine tor for bridges currently in the exclusive
nificantly less than that of the the economics and structural effi- domain of structural steel, i.e., spans in
AASHTO Type IV (8.32 in., 211 ciency of various methods for achiev- the 200 to 300ft (61 to 91 m) range, and
mm), and the Nebraska Type 4A (8.13 ing continuity. for bridge replacement projects where
in., 207 mm). The NU girder can be The Salem West Bridge, in Richard- higher load capacities are generally re-
shown to be similarly superior in sim- son County, Nebraska, is scheduled quired for the same structural depth.
ple span applications. for construction in the second half of 5. The span capability of the NU
Fig. 12 illustrates the advantages of 1994. It is a three-span bridge, with girders is superior to existing standard
the post-tensioned system used for op- spans of about 78ft (23.8 m). The sys- girders in all types of 1-girder bridge
timization compared to the system tem consists of pretensioned NUllOO systems including simple span de-
with mild steel reinforcement in the girders made continuous by mild steel signs, applications where continuity is
deck. At all girder spacings, the post- reinforcement in the cast-in-place achieved by mild steel reinforcement
tensioned system increases the span deck. in the cast-in-place deck, and in sys-
capability by about 15 percent. Note Since the beginning of this project, tems that utilize full-length continuity
the very large span capacity of the several states have expressed interest post-tensioning.
NU1800 girder, which is slightly shal- in the study and a desire to update 6. Regardless of the 1-girder shape
lower than the AASHTO/PCI 72 in. their current standard girder shapes. used, when girder continuity is irnple-

36 PCI JOURNAL
mented before the cast-in-place deck REFERENCES
is placed , e .g., by means of post-
tensioning, the span capability can be I. Dunker, Kenneth F. , and Rabbat , Highway and Transportation Offi-
increased by as much as 15 percent. Basile G ., " Performance of Pre- cials, Washington, D.C., 1992.
7. To improve fabrication produc- stressed Concrete Highway Bridges in 13. ACI Committee 318, "Building Code
tivity, welded wire fabric, rather than the United States - The First 40 Requirements for Reinforced Con-
individually tied reinforcing bars , is Years," PCI JOURNAL, V. 37, No.3 , crete (ACI 318-89) and Commentary
used to resist vertical shear, horizontal May-June 1992, pp. 48-64. (ACI 318R-89)," American Concrete
composite action shear, and other ef- 2. Standard Plans for Highway Bridges, Institute, Detroit, MI , November
fects. With increased use of welded U.S. Department of Commerce, Bu- 1989.
wire fabric, it is anticipated that stan- reau of Public Roads , Washington , 14. " Draft LRFD Specification s and
dard sizes will be manufactured. D.C., 1956. Commentary," Draft No. 4, prepared
8. The Nebraska Department of 3. Standard Plans for Highway Bridges, by Modjeski and Masters Consulting
Concrete Superstructures, V. l, U.S . Engineers as part of the National Co-
Roads has already adopted the NU
Department of Transportation, Fed- operative Highway Research Project,
girder series and is now specifying
eral Highway Administration, Wash- Transportation Research Board ,
NU girders in all precast 1-girder con- ington, D.C., January 1990. Washington, D.C., March 1993.
struction. The first bridge using NU
4. Anderson, Arthur R. , "Systems Con- 15. Skogman, Brian C. , Tadros, Maher
girders is scheduled for construction in
cepts for Precast and Prestressed K., and Grasmick, Ronald, "Ductility
the second half of 1994. Concrete Bridge Construction," Spe- of Reinforced and Prestressed Con-
cial Report 132, Highway Research crete Flexural Members," PCI JOUR-
Board, Washington, D.C. , 1972. NAL , V . 33 , No . 6, November-
ACKNOWLEDGMENT December 1988, pp. 94-107.
5. Koretzky , Heinz P ., "Precast Pre-
The authors wish to thank the Pre- stressed Bridges," Preliminary Re- 16. Yamane , Takashi K., and Arumu-
cast/Prestressed Concrete Institute and port, Pennsylvania Department of gasaamy, P., "Short to Medium Span
the Center for Infrastructure Research Transportation, Harrisburg, PA, 1980. Prestressed Concrete Bridges in
at the University of Nebraska for pro- 6. "Metric Conversion Activities of Japan," PCI JOURNAL, V. 39, No. 2,
viding the funding for this project. Federal Government Agencies in March-Aprill994, pp. 74-100.
The Precast Concrete Association of Compliance with P.L. 100-418, Sec- 17. Mills , Donald, Chow, Kenneth T.,
Nebraska, in particular Larry Fischer tion 5164, Metric Usage," Report and Marshal, Scott L., "Design-Con-
prepared by the Congressional Re- struction of Esker Overhead," PCI
and Morrie Workman, has been instru-
search Service, Library of Congress, JOURNAL, V. 36, No. 5, September-
mental in making this theoretical de-
Washington, D.C. , November 1991. October 1991 , pp. 44-51.
velopment a reality . Their helpful sug-
7. Abdei-Karim, Ahmad, and Tadros , 18. Mast, Robert F., "Lateral Stability of
gestions and willingness to keep an
Maher K ., " State-of-the-Art of Long Prestressed Concrete Beams -
open mind throughout the duration of Precast-Prestressed Spliced-Girder Part 2," PCI JOURNAL, V. 38, No. I ,
this project are greatly appreciated. Bridges," PCI Special Publication January-February 1993, pp. 70-88.
Special thanks go to Lyman Sponsored by PCI Committee on 19. Roller, John J ., Martin, Barney T. ,
Freemon , Nebraska Department of Bridges, Precast/Prestressed Concrete Russell, Henry G., and Bruce, Robert
Roads, whose leadership and encour- Institute, Chicago, IL, 1993, 133 pp. N., Jr. , "Performance of Prestressed
agement has led Nebraska to imple- 8. Abdei-Karim, Ahmad, and Tadros, High Strength Concrete Bridge Gird-
ment advancements in precast con- Maher K., "Design and Construction ers," PCI JOURNAL, V. 38, No. 3,
crete bridge technology . A note of of Spliced !-Girder Bridges," PCI May-June 1993, pp. 34-45.
thanks to Jeff Curren, HDR Engineer- JOURNAL, V. 37, No.4, July-August 20. Durning , Timothy A. , and Rear ,
ing Inc ., who designed the welded 1992, pp. 114-122. Kenneth B., "Braker Lane Bridge -
wire fabric reinforcement details . 9. Rabbat, Basile G., and Russell, Henry High Strength Concrete in Pre-
Many other individuals deserve a G., "Optimized Sections for Precast, stressed Bridge Girders," PCI JOUR-
mention of appreciation for the infor- Prestressed Bridge Girders ," PCI NAL, V . 38, No. 3, May-June 1993,
JOURNAL, V. 27, No.4, July-August pp. 46-51.
mation and guidance they provided on
1982, pp. 88-104. 21. Dolan, Charles W. , Ballinger, Craig
several occasions throughout the
10. Garcia, Antonio M., "Florida' s Long A., and LaFraugh, Robert W., "High
progress of this project. They include
Span Bridges : New Forms , New Strength Prestressed Concrete Bridge
Robert F. Mast, Jagdish C. Nijhawan,
Horizon s," PCI JOURNAL, V. 38, Girder PerformaJce, " PCI JOUR-
Paul Johal , Basile G. Rabbat, Leo No.4, July-August 1993, pp. 34-49. NAL, V. 38, No. 3, May-June 1993,
Spaans, Mohsen Shahawy, Richard R.
ll. Lounis, Z., and Cohn, M. Z., "Opti- pp. 88-97.
lmper, Reid W. Castrodale and Alex mization of Precast Prestressed Con- 22. Castrodale, W., Burns , Ned H. , and
Aswad. The authors also wish to thank crete Bridge Girder Systems," PCI Kreger, Michael E., "A Study of Pre-
all those who responded to the survey. JOURNAL, V. 38, No. 4, July-August tensioned High Strength Concrete
Finally , the authors wish to express 1993, pp. 60-78. Girders in Composite Highway
their appreciation to Deborah Derrick 12. AASHTO, Standard Specifications Bridges," Center for Transportation
and David Salmon for their editorial for Highway Bridges, Fifteenth Edi- Research , University of Texas at
work on this manuscript. tion, American Association of State Austin, Austin, TX, January 1988.

May-June 1994 37
APPENDIX A- SECTION PROPERTIES
OF STANDARD AND MODIFIED GIRDERS

Table A 1. Section properties of standard girders.


!-sections

Agency Type 01 02 03 04 05 06 81 82 83 84 A I Yb
I
Type I 28 4 3 - 5 5 12 16 6 - 276 22,750 12.6
Type II 36 6 3 - 6 6 12 18 6 - 369 50,980 15.8
Type Ill 45 7 4.5 - 7.5 7 16 22 7 I:J - 560 125,390 20.3
AASHTO
Type IV 54 8 6 - 9 8 20 26 8 - 786 260,730 24.7
Type V 63 5 3 4 10 8 42 28 8 4 1013 521 , 180 32.0
Type VI 72 5 3 4 10 8 42 28 8 4 1085 I 733,320 36.4

BT-54 54 3.5 2 2 4.5 6 42 26 6 2 659 268,077 27.6


AASHTOIPCI BT-63 63 3.5 2 2 4.5 6 42 26 6 2 713 392,638 32. 1
I
BT-72 72 3.5 2 2 4.5 6 42 26 6 2 767 545,894 36.6

Washington Series 14 73.5 2.875 2.625 2 3 6 42 24 5 2 674 514,3 12 9.2

Colorado G72 72 9.5 1.5 2 3.5 6.5 28 24 5 2 760 557,552 39.2


I
1728 mm 68.0 5.0 2.5 - 3.5 7 23.6 28.0 5.0 - 673 428,127 I 31.2
Canada
2000 mm 78.7 3.9 3.9 - 5.5 7. 1 33.5 28.0 5.5 - 820 701 ,533 37.4

Type 4A 54 5 4.5 - 7 24 24 6.5 - 644 236,105 I 25 .9


Nebraska
BT-lA 75 3
I 2 I
I
2 6.75 :.75 1 30 26
I 6 2 760 I 564,754
I
35.6

!-sections with curved surfaces

Agency Type 01 02 03 04 05 81 82 83 Rl R2 I R3 R4 A I Yb

Florida BT-72 72 2 4 5.5 7.5 48 30 6.5 8 8


I 0 0
I 901 638,672 J 34.4
Kentucky* BT- 1800 70.9 3 3.9 6.9 8.9 59.1 27.6 7.1 7.5 7.5 1 0 7.5 1,010 702,828 36.5

NU750 29.5 2.6 1.8 I 5.5 5.3 48.2 38.4 5.9 7.9 7.9 2.0 2.0 614 69,403 13.6
NU900 35 .4 2.6 1.8 5.5 5.3 48.2 38.4 5.9 7.9 7.9 2.0 2.0 649 11 0,444 16.1
NUIIOO 43.3 2.6 1.8 5.5 5.3 48.2 38.4 5.9 7.9 7.9 2.0 2.0 695 182,550 19.6
Nebraska NU 1350 53.1 2.6 1.8 5.5 5.3 48.2 38.4 5.9 7.9 7.9 2.0 2.0 753 302,743 23.9
University NU1600 63.0 2.6 1.8 5.5 5.3 48.2 38.4 5.9 7.9 7.9 I 2.0 2.0 812 459,057 28.4
NU1800 70.9 2.6 1.8 5.5 5.3 48.2 38.4 5.9 7.9 7.9 2.0 2.0 858 6 12,059 32.0
NU2000 78.7 2.6 1.8 5.5 5.3 48.2 38.4 5.9 7.9 2.0 905 791,498 35.7
7.9 1 2.0 I
NU2400 94.5 2.6 1.8 5.5 5.3 48.2 38.4 5.9 7.9 7.9 2.0 2.0 998 1,235,547 43.0
1 1
I
*Kentucky girder section properties were computed from a straight line approximation of curved surface.
Note: I in. = 25.4 mm.

38 PCI JOURNAL
Table A2 . Section properties of modified girders.
!-sections

Agency Type Dl D2 D3 D4 DS D6 81 82 83 84 A I Yb

AASHTO Type VI 72 5 3 4 10 8 42.9 26.9 6.9 4 1,006 699,093 36.4

AASHTO/PCJ BT-72 72 3.5 2 2 4 .5 6 42.9 26.9 6.9 2 832 573,909 36.6

Canada 1728mm 68.0 5.0 2.5 - 3.5 7 25.5 29.9 6.9 - 802 478,762 31.7
2000 mm 78.7 3.9 3.9 - 5.5 7.1 34.9 29.4 6.9 - 930 758,791 37.6
"

!-sections with curved surfaces

Agency Type Dl D2 D3 D4 DS 81 82 83 Rl R2 R3 R4 A I Yb

Florida BT-72 72 2 4 5.5 7.5 48.4 30.4 6.9 8 8 0 0 930 651,190 34.4

Kentucky * BT- 1800 70.9 3 3.9 6.9 8.9 58.9 27.6 6.9 7.5 7.5 0 7.5 996 696,975 36.5

NU750 29.5 2.6 1.8 5.5 5.3 49.2 39.4 6.9 7.9 7.9 2.0 2.0 643 7 1,554 13.6
NU900 35.4 2.6 1.8 5.5 5.3 49.2 39.4 6.9 7.9 7.9 2.0 2.0 684 114,178 16.2
NUIIOO 43.3 2.6 1.8 5.5 5.3 49.2 39.4 6.9 7.9 7.9 2.0 2.0 738 189,390 19.7
Nebraska NU1350 53.1 2.6 1.8 5.5 5.3 49.2 39.4 6.9 7.9 7.9 2.0 2.0 806 315,398 24. 1
University NU1600 63 .0 2.6 1.8 5.5 5.3 49.2 39.4 6.9 7.9 7.9 2.0 2 .0 874 480,111 28.6
NUI800 70.9 2.6 1.8 5.5 5.3 49.2 39.4 6.9 7.9 7.9 2.0 2.0 928 642,003 32.3
NU2000 78 .7 2.6 1.8 5.5 5.3 49.2 39.4 6.9 7.9 7.9 2.0 2.0 982 832,521 36.0
NU2400 94.5 2.6 1.8 5.5 5.3 49.2 39.4 6.9 7.9 7.9 2.0 2.0 1,09 1 1,306,244 43.4
*Kentucky girder section properties were computed from a straight line approxi mation of curved surface.
Note: I in. = 25.4 mm.

01

OS
06

I-Section !-Section with curved surfaces

Fig. A1 . Notation for dimensions contained in Tables A1 and A2 .

May-June 1994 39

You might also like