Professional Documents
Culture Documents
YEMEN LNG
Project
Pipeline
PRE-COMMISSIONING MANUAL
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 2 of 32
Table of Contents
1 INTRODUCTION............................................................................................................. 4
2 REFERENCE DOCUMENTS..........................................................................................4
4 SAFETY.......................................................................................................................... 5
5 RESPONSIBILITY...........................................................................................................5
6 PRE-COMMISSIONING METHODOLOGY.....................................................................6
6.1 SCOPE OF WORK AND ACTIVITIES......................................................................6
6.1.1 Conformity Check.............................................................................................6
6.1.2 Static / de-energized tests.................................................................................7
6.1.3 Piping Test (Test Pack).....................................................................................7
6.2 READY FOR COMMISSIONING (RFC)...................................................................8
6.3 STATUS INDEX.......................................................................................................9
6.4 PRE-COMMISSIONING PUNCHLIST......................................................................9
6.5 SEQUENCE OF EVENTS......................................................................................10
6.6 PRE-COMMISSIONING DOSSIER........................................................................10
7 PRE-COMMISSIONING PROCEDURES......................................................................10
7.1 EXCEPTIONS AND SPECIAL CASES..................................................................11
7.2 ELECTRICAL PRE-COMMISSIONING..................................................................11
7.2.1 Cables (Multicores/ multipairs, Field, LV Cables)............................................12
7.2.2 Junction/ Marshalling Box...............................................................................13
7.2.3 Earthing and Bonding......................................................................................14
7.2.4 Batteries.......................................................................................................... 14
7.2.5 Distribution Boards..........................................................................................15
7.2.6 Cable Trays.....................................................................................................16
7.2.7 Thermo Electric Generators (TEGs)................................................................16
7.2.8 Cathodic Protection System............................................................................16
7.3 INSTRUMENT PRE-COMMISSIONING................................................................16
7.3.1 Flow Element (Orifice Plate)............................................................................17
7.3.2 Control Valves and Accessories (Modulating).................................................17
7.3.3 Actuated Valves and Accessories (ESDV, MOVs, GHOVs)...........................17
7.3.4 Relief Valve.....................................................................................................18
7.3.5 Instrument Packages......................................................................................18
7.3.6 Instrument (Analog Input/Output)....................................................................18
7.3.7 Instrument (Switched/ Digital Output)..............................................................19
7.3.8 Instrument Tube/Pipe (Pneumatic, Impulse)...................................................19
7.3.9 Fire, Smoke and Gas Detection......................................................................19
7.4 MECHANICAL AND PIPING PRE-COMMISSIONING...........................................19
7.4.1 Mechanical Equipment Packages...................................................................19
7.4.2 KPU Gas Metering Package...........................................................................20
7.4.3 Vent Stack Package........................................................................................20
7.4.4 Pig Launchers, Pig Receivers.........................................................................20
7.4.5 NDT Clearance...............................................................................................20
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 3 of 32
APPENDICES
Appendix A – Pre-Commissioning Reference Document List...........................................24
Appendix B – CONTRACTOR’S Pre-commissioning Team..............................................25
Appendix C – Ready for Commissioning Certificate (RFCC)............................................26
Appendix D – Mechanism Flowchart.................................................................................27
Appendix E – Electrical Pre-commissioning Forms...........................................................28
Appendix F – Instrument Pre-commissioning Forms.........................................................29
Appendix G – Mechanical & Piping Pre-commissioning Forms.........................................30
Appendix H – Telecommunications Pre-commissioning Forms........................................31
Appendix I – Safety Pre-commissioning Forms................................................................32
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 4 of 32
1 INTRODUCTION
This manual aims to outline the general requirements and guidelines for the pre-
commissioning phase of the work, as well as provide the information and support
documents required to carry out the activities to be undertaken by the CONTRACTOR
to ensure that the pipeline, facilities, and stations are pre-commissioned in accordance
to project specifications.
2 REFERENCE DOCUMENTS
This document has been based on the latest revisions of the following documents:
GS EXP 101 Pre-commissioning and Commissioning Specification
GS EXP 103 Pre-commissioning and Commissioning Technical Preparation
GS EXP 105 Pre-commissioning Execution
YE-001-20-SOC-LIS-09286 Systems and Subsystems List
YE-001-20-SOC-DRW-09287 Systems and Subsystems Definitions and Limits
YE-001-20-SOC-PRC-09284 Punchlist Management System
YE-001-20-SOC-PRC-09285 Company Witnessing/Notification Procedure
YE-001-20-MOC-LIS-09263 Pre-commissioning Check lists and Test Sheets
YE-001-20-MOC-LIS-09262 Pre-commissioning Status Index
YE-001-20-MOC-PRC-09283 Handover Completion Dossier Layout Design
YE-001-20-SOC-PRC-09303 RFC & RFSU Handover & Acceptance
YE-001-20-SOC-MAN-09302 IPCIS Administration, Maintenance & Back-Up Manual
YE-001-20-MOC-PLN-09070 HS Plan
YE-001-20-MOC-PLN-09005 Project QA/QC Plan
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 5 of 32
4 SAFETY
Safety of both personnel and plant will be the priority throughout the pre-commissioning
phase. Thus, the CONTRACTOR shall only use competent and experienced personnel
to carry out the pre-commissioning in each discipline.
All Health and Safety Procedures for the YLNG project must be adhered to before and
during the execution of all pre-commissioning activities.
5 RESPONSIBILITY
Key personnel responsible for the effective execution and completion of pre-
commissioning activities will include but not be limited to:
o Responsible for ensuring that the pre-commissioning activities are in accordance with
the CONTRACT and project requirements and specifications.
o Ensure that installation, construction, conformity verifications, calibrations and
testings are carried out in conformance with the design and project requirements.
o Ensure that the subsystems are mechanically complete and are Ready for
Commissioning in a safe manner.
o Complete check lists and test sheets according to his relevant discipline for
completion of the Pre-commissioning Dossier
o Involvement in generating the punchlist items as required
o Coordinates with CPY Construction Authority of the approval and acceptance of the
pre-commissioning activities performed.
o Mark up the installation drawings as installed on site
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 6 of 32
QA / QC Engineer
o Ensure that installation, construction, conformity verifications, calibrations and
testings are carried out in conformance with the inspection and test plans and project
requirements.
o Ensures issues of test packages, certifications, calibrations of instruments and tools.
6 PRE-COMMISSIONING METHODOLOGY
o Check List
Conformity checks shall be carried out in accordance to the OPERCOM Check
Lists (CCK) for a specific discipline. These check lists define the exact scope of
work that shall be systematically performed on every item of equipment or on
selected packages and constitute the support documents to report the checks
performed.
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 7 of 32
One check list is filled in per subsystem and per type of equipment for each
discipline.
Any check which is not satisfactory, if not immediately and properly corrected by
the CONTRACTOR shall be included in the CTR’s punch list and CTR shall take all
necessary actions to have the item cleared. If the remedial work does not fall in the
CONTRACTOR’s SOW (such as defect on equipment free issued by COMPANY),
CTR shall report it to the COMPANY, include in the CPY’s punchlist and the
COMPANY shall be responsible in clearing the item with assistance from the CTR
as required.
The Check List will be transmitted to the CTR Construction Supervisor in charge of
the concerned discipline who will review the checks, date, and sign the appropriate
signatory boxes. Upon completion, the signature of CPY Construction Authority
should be obtained for approval of the checks carried out.
o Test Sheet
CONTRACTOR’s Discipline engineers should ensure that all checks have been
completed prior to carrying out any test. He shall ensure that the worksite is clean
and that all test equipment is available to properly execute the test.
If the test cannot be completed or failed to obtain satisfactory results due to any
defects, the CONTRACTOR shall treat the defect the same manner as described in
6.1.1.
After completing the Test Sheet, it shall be reviewed and signed by CTR
Construction Authority and CTR Commissioning Authority. The signature of the
CPY Construction Authority should be obtained for approval and acceptance of the
test performed.
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 8 of 32
The Test Packs breakdown may not fully match with a hierarchical sub-system
breakdown. CTR Pre-commissioning Team shall provide Tests Pack dossiers
referenced with associated sub-system, with listing of the lines included (PID
identification) and the Test Pack dossier for approval and acceptance of the
COMPANY.
Piping test packages should be pre-fixed with a two letter identification such as “TP”
indicating Test Pack and should carry the number of the subsystems (e.g. 33512)
plus the number of the test section (e.g. 26A) to be tested. As an example: TP-
33512+26A.
RFCC (see sample form in Appendix C) facilitates the handover of the sub-system
between Construction (CONTRACTOR and/or VENDORS) and the party responsible
for Commissioning, in this case, CONTRACTOR Commissioning Authority validated
by the COMPANY Commissioning Authority. This certificate is achieved through the
cross-inspection by the CTR and CPY Commissioning Authorities of the subsystem
facilities, actual witnessing by the CTR and CPY Commissioning Authorities of at
least critical pre-commissioning activities, the establishment of the mutually agreed
punchlist (if any), and the thorough review of the pre-commissioning dossier.
The transfer for a given subsystem will take place when the subsystem has reached
the “Ready for Commissioning” (RFC) status, i.e. when:
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 9 of 32
o The Pre-commissioning (RFC) Dossier has been compiled, submitted for review
and approval of CONTRACTOR and COMPANY Construction and
Commissioning Authorities.
Refer to “RFC & RFSU Handover & Acceptance” document number YE-001-20-SOC-
PRC-09303.
The completion data of each task is recorded on the status index so that it is a
working document used to follow up the work progress. It is therefore, the summary
of all the pre-commissioning scope of work recorded and monitored in IPCIS.
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 10 of 32
c. All completed check lists and test sheets, marked-up drawings, and punchlists
raised (if any) and all required reports and documents should be compiled to
form the Pre-commissioning Dossier (RFC Dossier).
d. The CTR Construction Authority then reviews the Pre-commissioning dossier,
issues and signs the RFC validating the completion of the work.
e. The CTR Commissioning Authority reviews the dossier for acceptability and
when satisfied, countersigns the RFCC.
f. RFCC should then be issued to CPY Construction Authority for approval and
acceptance and countersigned by the CPY Commissioning Authority.
Each subsystem shall have the following: an individual RFCC, Subsystem Punchlist (if
any), and shall be compiled in a separate pre-commissioning dossier. The pre-
commissioning dossier, upon completion will form part of the Handover Completion
Dossier (HCD).
7 PRE-COMMISSIONING PROCEDURES
This section provides the basic information and procedures required to carry out pre-
commissioning activities on site in a planned, safe and efficient manner. This however
does not intend to be fully comprehensive and hence shall be used in conjunction with
the appropriate technical specifications. This covers the simplified pre-commissioning
scope of work applicable for each discipline.
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 11 of 32
The only packages to which the reduced scope applies are specifically listed as such
in the CONTRACT. Packages to be pre-commissioned will be identified in the pre-
commissioning Status Index. The reduced scope shall be the following:
o A single package Check List shall be performed, instead of various equipment
Check lists. Mechanical Package will be recorded in the Mechanical Check List
C-ZM-01-M whereas Electrical and Instrument package will be recorded in C-
ZM-01-E and C-ZM-01-I respectively.
o The pre-commissioning Tests will be limited to:
- Electrical: insulation and continuity tests
- Instrument: calibration and cables continuity tests between the item of
equipment and the marshalling cabinet in the Technical or Control Room,
telecom/SCADA shelter of all equipment related to safety: alarm and
shutdown devices, safety valves, etc.
- Mechanical/Piping: alignment of all equipment and flushing of all piping
reinstated on site by the CONTRACTOR.
o Building, Shelters and Structures (includes Fences, Roof beams, Security Doors
foundations, and Gates)
- All checks and inspections related to structural works (steel, roofs, gates,
etc) shall be recorded in the mechanical pre-commissioning check list C-
QX-01. The CTR Construction Authority should ensure that inspections
have been completed prior to submitting for approval to the CTR
Commissioning Authority. The CTR Construction Authority should check
the installation against design specifications, requirements and approved
drawings. The acceptance of the forms will form part of the Pre-
commissioning Dossier.
The inspection and test procedures in this section are confined and may not
necessarily cover all electrical equipment and circuits included in the design.
Equipments and/or subsystems that have a stand-alone pre-commissioning procedure
should be referred to their specific procedure.
Pre-commissioning activities for electrical equipment and systems shown in the single
line diagrams shall be carried out with good engineering practice and in accordance
with contractual requirements, project specifications, one line diagrams, cable lists,
equipment list, and vendor drawings and specifications.
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 12 of 32
For the case of LV cables, electrical pre-commissioning checklist C-PX-09 and test
sheet T-PX-09 will be used to record all the data for the insulation resistance and
continuity tests.
The following inspection and test procedures are applicable to all cable sizes
and types (including multicore cables). All cables shall be tested in
accordance with the specified Standards and Codes of Practice.
Insulation Resistance
The CTR Electrical Engineer shall carry out and record all data for the insulation
resistance and continuity tests with the cable ends glanded and prepared but not
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 13 of 32
connected. On completion of the tests, the cable will be connected and all core
marking shall be checked for correctness.
The insulation resistance of all buried cables shall be measured before and after
backfilling. Buried cables shall also be tested for security of overheat by
measurement of the armouring insulation resistance after consolidation of the back
filling.
Continuity tests shall be carried out for each core and each core number, test
number, and test results shall be reported in the Test Sheet. Continuity tests shall
cover the whole cable circuit as indicated on the trouble-shooting diagrams, from
the initial point (generally control room marshalling cabinets) to the final element on
the field irrespective of the multicore subsystem limits.
Testing
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 14 of 32
a. Each separate earthing point, which may consist of one or more electrodes,
shall be tested with a standard earth test whenever practical.
b. The resistance as measured from any part of the system to the main earth
point should not normally exceed the values noted below and tests shall be
carried out to confirm this and should be witnessed by COMPANY:
i. Electrical Earthing - 1 ohm.
ii. Static Bonding - 10 ohms.
iii. Earth Loop - Onsite
c. The minimum number of bolted connections has been included but adequate
provision has been made for testing purposes
d. All bolted connections have been fitted with anti-vibration locking devices, and
that the materials used are such as to minimise risk of corrosion
e. The resistance before and after connection of each earth electrode shall be
measured and also the resistance to earth of all points including transformer
neutrals, centre taps, earth bars etc.
f. The impedance of the earth loop for all classes of earth (power, instrument,
etc) shall be measured and recorded and verified by COMPANY.
7.2.4 Batteries
All battery checks shall be recorded in the C-PX-17 pre-commissioning form and all
tests results shall be recorded in T-PX-17. The pre-commissioning tests to be
performed on batteries are designed to allow the charge and discharge tests and
also as maintenance record.
Testing
Only the following will be done under this test in preparation for commissioning and
initial charging.
a. When all inspection and tests and the specific gravity of the electrolyte have
been checked, the batteries may be given their initial charge. Specific gravity
of the electrolyte shall be checked before charging. COMPANY to witness.
b. Each cell voltage shall be recorded.
c. Each battery voltage shall be recorded.
d. Battery bank voltage shall be recorded.
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 15 of 32
e. Check the operation of the battery earth fault alarm (where fitted), and
measure the earth current flowing for a zero impedance earth fault. Ensure
that the measured value is below the drop off current level for all shutdown
relays.
f. Check the operation of all alarms and trips including the main supply and
charge failure alarms and the battery charger rectifier failure alarms and trips
(where fitted) and compare against manufacturer’s data.
g. Carry out the battery discharge test following the Vendor procedures and
instructions.
Testing
a. Enter all nameplate details on to the test sheet.
b. Review the equipment with respect to the datasheet and verify compliance.
c. All outgoing circuit breakers are to be checked for mechanical operation and
also checked against design documents to ensure correct rating for the circuit
and results to be recorded in the test sheet.
d. Carry out the insulation resistance tests on all distribution board, main circuits
and also any control wiring.
e. Carry out an earth return path impedance test and record the value on the
Test Sheet.
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 16 of 32
supports and there should be no welding permitted. All checks performed shall be
recorded in the pre-commissioning check lists C-PX-30.
As a general rule, checks related to various types of equipment shall not be reported
on the same Check List. The check list C-JX-04 shall be used for different types of
instruments indicated in Appendix F. A general test sheet form T-JX-00 will be used to
report any checks and inspections and required tests on instrumentation equipment
except for equipments that have a specific test sheet.
Preliminary review of the installation site for the orifice plate should be carried out at
a suitable point in construction to ensure that requirements identified on the PID,
hookup diagrams and specification (particularly with reference to straight lengths of
pipe / turbulent flow and vibration) have been satisfied. Orifice plates should be
examined for flatness and to ensure that they are undamaged and installed in good
position.
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 17 of 32
Prior to operation the valve seat shall be checked for cleanliness. All auxiliary
equipment mounted with the valve shall be calibrated/function checked and all test
results recorded on the test sheet.
Control valves with other types of actuator, e.g. piston operators, air cylinder
operators, electro/hydraulic or electric motor operators should be tested for stroking
and failure action in accordance with the manufacturer's instructions. All valve
accessories shall be checked for correct function, this shall include limit switches,
solenoid valves and any associated test over-ride facilities.
The instrumentation engineer should inspect the condition of the valve and
accessories, including cleanliness of the seat, and the correct position and
orientation, review the valve and accessories with respect to the datasheet and
valve dataplates and check / complete the instrument datasheet number in the test
sheet. In addition whenever limit switches are installed on actuated valves they
shall be adjusted as per the VENDOR recommendations.
All relief valves shall be tested on air or nitrogen and adjusted to commence to
open at the cold test pressure. This cold test pressure shall include the corrections
for service conditions or back pressure or temperature, or both.
The seat leakage test shall be carried out in accordance with ANSI B 147.1 and API
527 with an applied pressure under the disc of 90% of the cold test pressure and
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 18 of 32
will be conducted using the test bench equipment approved by COMPANY. The
acceptance criteria shall be as follows:
- Resilient seat seals - zero leakage
- Metal Seats - less than 5 bubbles per minute.
Should any valve not conform to the test requirements listed on the data sheet, it
shall be brought to the attention of the COMPANY prior to remedial work being
carried out on the valve. For safety valves installed on hydraulic packages/systems,
valves shall be removed for testing only when requested by the certifying authority
to avoid contamination of hydraulic circuits. The COMPANY shall make available to
the certifying authority, original factory test certificates for all valves falling into this
category.
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 19 of 32
In the case of areas with potentially explosive atmospheres or fire, checks must be
carried out to components, and should be installed in compliance with appropriate
codes. All checks shall be reported in the pre-commissioning check list C-ZM-01-M
and all tests shall be recorded in the general test sheet T-MX-00.
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 20 of 32
Each completed cleaning tests shall be recorded in the Cleaning and Gauging Test
Sheet T-MX-04 and the Cleaning Index Test Sheet Form T-MX-23 shall summarize
all the cleaning tests performed. A copy of the cleaning and gauging pre-
commissioning form with complete information filled up by the CTR Piping Test
Engineer should be included in the piping test pack when submitted for review prior
to hydrotstatic testing.
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 21 of 32
The pressure tests to be performed on each test section shall be recorded in the
mechanical pre-commissioning test sheet T-MX-03 and all hydrostatic tests
performed shall be recorded in the Pressure Test Index form T-MX-21. This form
shall be included in the piping test pack prepared by construction team and where
the original will be filed in the pre-commissioning dossier of the subsystem.
For each test, the following documents shall be completed and shall be included in
the pre-commissioning dossier:
o Pressure test notice
o Colored Isometrics and PIDs for test plans, where
- Blue: indicate lines to be flushed
- Green: indicate items to be removed
- Red: flanges to be disconnected
- Orange: items to be isolated
- Yellow: temporary installation (supports, spools, etc)
o Inspection clearance certificate (indicating all inspection checks and test
sheets have been carried out on the piping to be tested and that they are
satisfactory)
o Acceptance certificate for calibration of instruments
o Test acceptance certificate
o Original recorder chart
o Pre-commissioning check lists and test sheets.
o Test Logs
After satisfactory completion of the hydrostatic testing, the test sheet shall be
signed by the CTR’s Construction Authority and by the CPY Construction Authority
for the acceptance of the test.
Upon completion, the test sheet shall form part of the piping test pack acceptance
documentation and on completion the original will be issued by the CONTRACTOR
and filed in the pre-commissioning dossier of the subsystem.
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 22 of 32
will vary for valve type, size and service, the COMPANY Engineer will inform the
CONTRACTOR of his requirements for the test. The CONTRACTOR must at all
times, have all relevant documentation available for review by the COMPANY
Engineer.
YE-001-20-617-PRC-11477 Factory Acceptance Test (FAT) Plan for Testing at CTR Site (TEGs)
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 24 of 32
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 25 of 32
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 26 of 32
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 27 of 32
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 28 of 32
Discipline: ELECTRICAL
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 30 of 32
Discipline: TELECOMMUNICATIONS
Form No. Description/ Designation
C-IX-31 Telecom PA/ GA Equipment
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 31 of 32
Discipline: SAFETY
Form No. Description/ Designation
C-YX-08 Portable Fire Fighting Equipment
C-QX-03 Safety Signs
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.
Document number
PRE-COMMISSIONING MANUAL YE-001-20-SOC-MAN-09261
Revision : 06 Status : IFC
Document Type : PRC System / Subsystem : 99 Discipline : PLR Rev Date : 10/04/08
Contractor document number : N/A Page 32 of 32
This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written
authorisation from the Company.