PARTS LIST
ITEM QTY PART DESCRIPTION
1 1 1-1/2" OD x .120 Wall x 84-3/4 A-Pillar RH
2 1 1-1/2" OD x .120 Wall x 84-3/4 A-Pillar LH
3 1 1-1/2" OD x .120 Wall x 129-1/16 Main Hoop
D 4 1 1-1/2" OD x .120 Wall x 37 Halo Bar D
6 11 5 1 1-1/2" OD x .120 Wall x 46-1/2 Dash Bar
6 2 1-1/2" OD x .120 Wall x 23-1/4 Belt Mount Bars
1
7 1 1-1/2" OD x .120 Wall x 46-1/2 Hoop Spacer Bar
8 1 1-1/2" OD x .120 Wall x 48 Door Bar
4 9 2 1-1/2" OD x .120 Wall x 26 Door Bar Brace
10 1 1-1/2" OD x .120 Wall 57-1/4 Diagonal Hoop Brace
10 11 2 1-1/2" OD x .120 Wall x 72 Rear Support Braces
22
2 9
1103 16
7 3
38 16 48 4
37 223 4
B B
7111 16
571 4
463 4
3213 16
267 16
DRAWN
Phil Hare 6/19/2009
CHECKED
A n1
1
2 QA
TITLE
A
45 461 2 MFG
461 2 48 APPROVED
48 491 2
SIZE DWG NO REV
413 8
^ 257 16
1013 16
D D
75.2°
R71 2
R71 2
117 8 117 8
C C
^
21 8 14.8°
R71 2 R71 2
1
Total Length for Main Hoop: 129 16"
3
46 4 46 Allow additional 1" at either end for field fitting.
405 8
381 2 Typ.
B 27 B
27 Typ.
27
71 2 Typ.
101 2 Typ.
DRAWN
Phil Hare 6/19/2009
45 CHECKED
A QA
TITLE
A
461 2 Main Hoop
MFG
48 APPROVED
SIZE DWG NO REV
41.0° 26
^
7
D 5 8 D
41.0°
R71 2
191 16
13.9°
166.1° C
SECTION B-B
C SCALE 1/4
C C
2315 16 51.0°
^
73 8
R71 2
163.5°
B B
3
B Total Length for A-Pillar: 84 4"
46
Allow additional 1" at either end for field fitting.
SECTION C-C
Two Required: SCALE 1/4
1 x Left Hand
1 x Right Hand
267 16 267 16
267 16
DRAWN
Phil Hare 6/19/2009
CHECKED
A QA
TITLE
A
MFG
483 4 APPROVED
SIZE DWG NO REV