Professional Documents
Culture Documents
Submitted by
Guided by
Dr. P. N. Ghumare
2022 – 2023
SAVITRIBAI PHULE PUNE UNIVERSITY, PUNE
MET's Institute of Engineering, Adgaon, Nashik-422003
Civil Engineering Department
CERTIFICATE
This is to certify that the report entitled “Analysis Of Construction Productivity In
Relation With Information Technology” submitted by students as per the
requirement to award a degree of Bachelor of Civil Engineering. It is submitted in the
partial fulfilment of the prescribed syllabus of Savitribai Phule Pune University, Pune
for the academic year 2022– 2023.
DECLARATION
I hereby declare that this submission is my work and that, to the best of
my knowledge and belief, it contains no material previously published or
written by another person, which has been accepted for the award of any
other degree or diploma of the university or other institute of higher
learning, except where due acknowledgement has been made in the text.
Date:
Place: Nashik
We have taken efforts in this project. However, it would not have been possible
without the kind support and help of many individual and organizations. We would
like to extend our sincere thanks to all of them. It gives us proud privilege to complete
the project on “Analysis Of Construction Productivity In Relation With
Information Technology”
We are highly indebted to our internal guide Dr. P. N. Ghumare Sir for his guidance
and constant supervision as well as for providing necessary information regarding the
project and for his support in completing the project.
We are also extremely grateful to our respected H.O.D. (Civil Department) Dr. P. N.
Ghumare Sir for providing all facilities and every help for smooth progress of project
work. We also extend our sincere thanks to Principal of MET’s Institute of
Engineering Dr. V. P. Vani Sir for extending all kind of cooperation during the
1course.
We express our sincere thanks to staff of department of Civil Engineering for kind
cooperation and support. Lastly, we are thankful to all those who have helped us
directly or indirectly to complete this project work.
ABSTRACT
In past few years, information technology has been impacting industries,
economics, the way of life and even the culture throughout the world. Productivity has
been attracting much attention as an important indicator of economics, and numerous
researchers have investigated the relationship between information technology and
productivity. Construction is one of the largest industries, but the relationship between
information technology and construction productivity is rarely known. The major
objective of this work is to determine the extent to which information technology is
used, specifically the use of information technology to automate and integrate
construct-on project work functions, is related to construction productivity. Initially
the relationship between information technology and construction productivity on a
national-level basis will be done. Second, the comparison of the relationship between
information technology’ contribution to value added growth and productivity in the
construction industry with other industries. And then performance of a series of
statistical analyses to investigate the relationship between construction productivity
and automation and integration applications at the construction project level will be
done. In order to leverage the relative importance of technology on each work
function, regression analyses will also be performed to obtain a further understanding
of the relationship. This analysis could provide construction companies an indication
about information technology usage priority and deployment in their work.
TABLE OF CONTENTS
LIST OF GRAPHS................................................................................................................................ 3
LIST OF FIGURES............................................................................................................................... 4
CHAPTER 1 INTRODUCTION.......................................................................................................... 1
1.1 PROLOGUE:...................................................................................................................................1
1.1.1 The development of Information and Communication Technology in Construction...............1
1.1.2 Computer Aided Design and Visualization...............................................................................3
1.1.3 Current Information Technologies for the Construction Sector...............................................3
1.1.4 Building Engineering Applications............................................................................................4
1.1.5 Computer Aided Cost Estimation..............................................................................................5
1.1.6 Planning, Scheduling and Site Management...........................................................................5
1.1.7 Computer Aided Facilities Management..................................................................................6
1.1.8 Business and Information Management..................................................................................6
1.1.9 Integration................................................................................................................................6
1.1.10 Current Communication Technologies for the Construction Sector.......................................7
1.2 PROBLEM STATEMENT:....................................................................................................................8
1.3 OBJECTIVES:...................................................................................................................................9
1.4 SCOPE OF WORK:...........................................................................................................................9
1.5 LIMITATIONS OF STUDY:.................................................................................................................10
CHAPTER 3 METHODOLOGY....................................................................................................... 19
3.1 PROCEDURE:................................................................................................................................20
3.1.1 Data Collection.......................................................................................................................20
3.1.2 Pilot Study...............................................................................................................................21
3.1.3 Measuring Factors and Related Labour Productivity.............................................................21
3.1.4 Construction Labour Productivity Prediction Methods..........................................................22
3.1.5 Validation Procedure..............................................................................................................24
CHAPTER 5 CONCLUSION............................................................................................................ 50
5.1 CONCLUSION................................................................................................................................50
5.2 RECOMMENDATIONS.....................................................................................................................50
5.2.1 Material Acquisition...............................................................................................................51
5.2.2 Apply Tool and equipment management program................................................................51
5.2.3 Site layout that is well-designed............................................................................................51
5.2.4 Employees should receive training.........................................................................................51
5.2.5 Partnership Stakeholder.........................................................................................................52
5.2.6 Excellent Interaction...............................................................................................................52
REFERENCES................................................................................................................................... 53
APPENDIX....................................................................................................................................... 55
List of Tables
TABLE 3.1 FACTORS AFFECTING LABOUR PRODUCTIVITY FOR CONCRETE WORKS .......23
TABLE 4.1 GOOGLE FORM OF QUESSTIONAIRE SURVEY...............................................25
TABLE 4.2 DAILY OBSERVATION OF SLAB FORMWORK................................................27
TABLE 4.3 TOTAL ACTIVITY ORGANISATION...............................................................29
TABLE 4.4 ACTIVITY PERCENTAGE FOR SLAB FORMWORK..........................................30
TABLE 4.5 HOURLY DISTRIBUTION OF SLAB FORMWORK ACTIVITY............................31
TABLE 4.6 RESULT OF CONSTRUCTION LABOUR PRODUCTIVITY FOR SLAB FORMWORK
...............................................................................................................................33
TABLE 4.7 DATA SET FOR SLAB FORMWORK ACTIVITIES..............................................34
TABLE 4.8 CORRELATION: WORK SAMPLING PROPORTION WITH CLP FOR
COLUMN FORMWORK ACTIVITY.........................................................................37
TABLE 4.9 TOLERANCE AND VARIANCE INFLATION FACTOR FOR INDEPENDENT
VARIABLES............................................................................................................38
TABLE 4.10 REGRESSION MODEL SUMMARY................................................................39
TABLE 4.11 COEFFICIENT OF INDEPENDENT VARIABLES..............................................43
TABLE 4.12 DESCRIPTIVE: STATISTICS FOR SLAB FORMWORK....................................45
TABLE 4.13 NUMBER OF OBSERVATIONS FOR EACH VARIABLE...................................47
TABLE 4.14 ACTUAL PRODUCTIVITY AND PREDICTED CLP FOR COLUMN FORMWORK
ACTIVITIES.............................................................................................................47
TABLE 4.15 PERFORMANCE OF MULTIVARIABLE REGRESSION MODEL.......................48
List of Graphs
GRAPH 4.1 PIE CHART ILLUSTRATING SLAB FORMWORK ACTIVITY RESULTS............30
GRAPH 4.2 GRAPH OF PREDICTED CONSTRUCTION LABOUR PRODUCTIVITY FOR SLAB
CONCRETING..........................................................................................................44
List of Figures
FIGURE 1.1 CONSTRUCTION PROCESS AND IT APPLICATIONS.........................................4
FIGURE 1.2 EVOLUTION OF INTERNET RELATED COMMUNICATION TECHNOLOGIES.......8
CHAPTER 1 INTRODUCTION
1.1 Prologue:
Information technology (IT) can be defined as the use of electronic machines
and programs for the processing, storage, transfer and presentation of information. As
the indicator of the third industrial revolution, information technology has been
impacting the economy, the culture and the way of human’s life throughout the world.
Productivity is of central importance to the health of
Indian economy. With the increasing application of IT in almost all industries,
understanding the relationship. between IT and productivity is necessary to improve
the effectiveness of IT in improving productivity. Many researchers have investigated
the relationship at the following three levels of analysis: 1) national-level, 2) industry-
level and 3) firm- or project-level. The focus of these research efforts is to investigate
if IT expenditures or related applications in the construction industry contributes to or
is associated with productivity improvement. The national-level analysis, comparing
the IT usage and productivity across different countries, has the potential to identify if
the countries with advanced IT development and application in construction
experienced more rapid construction productivity improvement than construction
industries in countries with relatively less IT application. The industry-level analysis
has the potential to compare the effectiveness of IT application in construction with
that of other industries and the resulting impact on the industries’ productivity.
isolation. These tools play to the enormous strengths of computers in the rapid analysis
of complex data sets –analysis which is frequently impossible if manually attempted.
Thus standalone applications dependent on numerical analysis, ranging from finite
element analysis to critical path analysis, had been developed by the 1960s.
Information flows between these types of application continued to use traditional
information technologies such as the paper-based engineering drawing.
During the 1970s, a new form of graphical manipulation developed to aid the
creation of engineering drawings –computer aided design (CAD). Again, the output
from these systems largely relied on traditional technologies for communication
between different applications. The construction industry was at the forefront of these
developments. By the fourteenth century, scaled technical drawings –probably the
most important information technology of the last millennium after the printed book
itself- were well established for use on religious and royal building projects. During
the 1970s, large public sector projects –usually relying on extensive standardization
and prefabrication- offered the opportunity to develop CAD systems. However, the
demise of the large public sector construction programmes which have been essential
to the development of ICT applications in every industrial sector meant that this initial
momentum was lost (Howard 1998). The 1980s saw the development of the personal
computer (PC) which dramatically reduced the cost of computing power, and enabled
a much wider diffusion of computers within the industry, while the processing power
of computers continued to grow exponentially. Most importantly, site offices could
now be equipped with computers.
The development of communication technologies has taken an independent
path. In comparison to computer technologies, developments were earlier and more
profound. The telegraph and, more importantly, the telephone, greatly improved
communication capabilities. The fax and photocopier are more recent innovations
which have had a significant impact. Nonetheless, these communication technologies
did not allow any further manipulation of the received data. It was not until the 1970s
that they began to be connected to computers to provide integrated systems for the
direct communication of information between computer systems. The development of
Local and Wide Area Networks (LANs and WANs) proceeded steadily, but
interconnectivity between computers was transformed by the breathless diffusion of
the internet during the 1990s. It is this rapid development of the interconnection
between communication and information technologies over the last 20 years that has
both opened up tremendous new opportunities and posed new technical challenges.
indicate the main application areas for the existing discrete software packages in the
construction supply chain.
have been developed for energy analysis, HVAC design, structural analysis, lighting
simulation, etc. The benefit of these applications is that they allow designers to
evaluate alternative design solutions in order to reach optimum design.
Examples of this software are: ATEAN from Carrier, and CARGASW from
Climasoft, that offer comprehensive range of software options for climatic energy
design; CALCULUX for lighting and building services design, CYPE INGENIEROS
S.A. for structural design, COSMOS for finite elements analysis, DUCTSIZE from
Elite Software for electricity and water nets design.
some applications like JobMaster, ICON, GEST, and Presto Control, are designed to
log and track internal processes during the construction phase.
1.1.9 Integration
From the first software applications, many different tools were developed.
They use their own data formats, which are not compatible with each other. As a
result, data cannot be electronically exchanged between them. In recent years, there is
an increasing awareness of the need for integrated construction processes and many
research projects are investigating related issues. During the last two decades,
advances in object oriented programming, database systems and product data
modelling technologies have provided a solid platform for integration. Data standards
are being developed first by the International Standards Organizations (STEP), and
then by the International Alliance for Interoperability (IFC). At present, these
standards are still evolving. An integrated project database covering the whole life
cycle of construction projects remains a future prospect.
cost in a direct proportion. It can either benefit or reduce a project’s profit, making it
of vital interest to the construction industry for its success.
1.3 Objectives:
Objectives of this study include:
1. Deciphering Construction Labor Productivity through the Power of Regression
Analysis
2. Clash of Productivity: Comparing Conventional and Advanced Techniques in
Construction
3. Validating Construction Productivity: Ensuring Accuracy and Reliability
and to minimise the wastage of other resources as well (which is also the key
philosophy of Lean Construction), it is extremely crucial that the productivity of the
resources involved in any project is closely monitored and suitable actions are taken
for their improvement.
Some research were conducted to determine the extent, if any, to which integration
and automation (IA) technologies contributed to project success. The researchers
divided the project life cycle into six phases: front end, design, procurement,
construction management, construction execution and
startup/operations/maintenances. Each phase was composed of work functions, some
of which represented project tasks (for possible automation), and some of which
represented task-to-task integration links.
Through statistical analyses, research has indicated that:
The schedule success-technology relationship was stronger than that for cost;
Higher levels of project schedule success were particularly associated with
high levels of technology utilization for building, medium-sized, and
expansion projects;
Higher levels of project schedule success were associated with high levels of
technology usage in the front-end phase, particularly for building and medium-
sized projects.
The researchers developed an IA (integration and automation) index ranging
from 0 to 10 according to its use level on each of work functions.
in the sector. This framework also identifies the key forces that influence and impact
upon ICT usage in the construction sector, especially the interplay of key pivotal
forces (through the competing push-pull continuum). A series of different scenarios
for ICT uptake, adoption and diffusion are envisioned. These were developed with the
help of industry experts in order to embed relevance and establish priorities against
tangible indicators. This framework presents a future state ICT vision for SME's, one
which places direct emphasis on SMEs' perspectives (operational and strategic) and
their future business aspirations.
for complete usage of technology within the construction firms to ease their own work.
The study shows that firms are still reluctant in investing fully into ICT tools. Those
handful of firms implementing tools are also seen upgrading and maintaining the
technology on regular basis. This study analysed that from stakeholder‟s point of
view, ICT usage in construction is increased and is quite better than last ten years And
also feel that current political policies are quite favourable but still need to improvise
for effective implementation of ICT in this industry. It is observed that industry
perspective is changing and many are willing to adapt this new technology and are
eager to use the tools.
adopting speedy communication tools to get efficient work done. System maintenance,
security and lack of software knowledge are the few challenges in E-Business usage in
construction industry.
analysis of automation and digitization levels of each phase, it was found that they are
mostly interconnected among project life-cycle phases through the use of BIM. This is
because the initiation phase includes surveys and studies resulting in the draft
investment program and solution. The following phase, i.e., the design phase, mainly
leans and streams towards the BIM concept, which enhances and enables the
generation of schedules to cover the aspects of planning. Since the topic is
continuously developing, this research could be conducted in the near future to
determine the advancements in comparison to the current conclusions.
CHAPTER 3 METHODOLOGY
Proper research method is important to start methodology presents the
route map to continue the scientific investigation. At the end of the pervious chapter a
framework on literature review and related theories to the purpose and research
questions of the thesis has been presented. This chapter describes research process,
research design and also explains type, approach and strategy of this research. Sample
selection, method of collecting data, reliability and validity of this study are other
issues which are discussed in this chapter.
The flowchart below shows the analysis methodology adopted for the
following project work.
3.1 Procedure:
The data collected can be classified as primary data versus secondary data.
Primary data are gathered and generated for the project at hand, but secondary data
were gathered for other purposes and now are used in the recent project .usually the
secondary data are found inside the company, libraries, research centers, internet and
etc… This study used both primary and secondary data.
3.1.1.5 Documentation
Different types of documents such as examples, statistics, registration and
official publication, letter journals and branch literature are employed to collect data
3.1.1.6 Questionnaire
The recognizable proof and assessment of factors that impact labour
productivity rates of concrete construction activities are required to create the models.
Numerous studies will be conducted to define and describe factors affecting labour
productivity. This will be used to develop the questionnaire form, which involves
factors affecting the labour productivity rates of concrete construction activities.
The data in this method will be gathered by sending questions to the respondents.
Questionnaires can be distributed in paper form or by email, fax and etc…there is no
explanation or influence of researcher in this method. Also, questionnaire is not to be
more long and exhaustive, because these happens cause the questions not to be
answered.
the worker hour is included as data. The production rates will be estimated according
to:
( Workerm days )=
FCS ( Workers ) X t F (days )
FP 3
CQ (m¿ ¿3)¿
( )
Worker days SCS ( Workers ) X t s (days )
SFP =
ts SQ (m¿¿ 3)¿
CPP
( m
3
=
)
Worker days PCS ( Workers ) X t C (days)
CQ(m¿¿ 3) ¿
Where:
FP: Formwork productivity,
SFP: Steel fixing productivity,
CPP: Concrete pouring and finishing productivity,
FCS: Formwork crew size,
SCS: Steel crew size,
PCS: Pouring crew size,
t F : Formwork assembly duration,
t s: Steel fixing duration,
t C: Concrete pouring duration,
CQ: Concrete quantity, and
SQ: Steel quantity.
Where:,
∅ ( x ) : the high-dimensionality feature space nonlinearly mapped from the input space,
b: the term of bias, an w: the weight vector.
value; distant points, on the other hand, are not influential as much as close
neighbouring points. A radius base function is used for calculating the neighbouring
point influence level.
As mentioned, GRNN is able to build a model with a relatively small dataset and has
the capability to handle outliers. There are two main disadvantages associated with
GRNN; it needs considerable calculations to evaluate new points and is not able to
ignore unrelated inputs without assistance and needs major algorithm modifications.
Consequently, this method is not a choice for problems with a substantial number of
predictor variables. A GRNN algorithm can be enhanced by advancing GRNN in two
ways: using clustering versions of GRNN and applying parallel calculations to take
advantage of GRNN structure characteristics.
∑ ( pi−oi ) (oi−o)
i=1
R=
√∑
N N
( p i−o i) 2
∑ (o i−o)2
i=1 i=1
√
N
RMSE= ∑ ( pi−oi)2
i =1
N
MSE=∑ ( p i−o i)
2
i=1
N
1
MAE= ∑ | pi−oi|
N i=1
The questionnaire survey was constructed where various experienced and some
inexperienced people from civil engineering background were asked questions using
Google form of which responses are collected and the effect of every parameter is
described through graphical format.
The results of all the 53 responses for each factor is as shown below in graphical
format in Appendix.
Work day14 day15 day16 day17 day18 day19 day20 day21 day22 day23 day24 day25 D
Sampling
Direct 32 35 19 24 33 27 22 17 23 26 24 25
Work
Preparatory 5 7 6 5 8 2 8 7 7 5 8 8
Work
Tools and 8 9 5 6 7 9 5 2 6 5 9 6
Equipment
Material 9 6 8 10 10 3 12 11 12 10 7 4
Handling
Waiting 16 13 9 14 9 4 10 12 16 15 10 9
Travel 4 7 7 11 5 5 8 12 5 4 6 5
Personal 9 4 3 3 6 1 2 7 7 9 8 4
Work day27 day28 day29 day30 day31 day32 day33 day34 day35 day36 day37 day38
Sampling
Direct 22 31 25 23 24 26 27 17 31 23 20 16
Work
Preparatory 8 6 5 8 4 7 4 4 9 4 5 4
Work
Tools and 4 9 10 11 5 7 9 9 9 6 4 6
Equipment
Material 10 8 8 4 8 5 5 8 6 5 8 7
Handling
Waiting 12 14 12 6 10 8 8 7 11 14 7 10
Travel 6 10 9 3 3 3 7 6 10 8 6 2
Personal 3 5 3 2 1 3 6 3 2 3 3 5
Total
Observation
Summary of Activity Result
Table 4.2 shows that there is a day to day variation of observation for the following possible reason. First, the characteristic being observed is not
the workers, but instead the workers’ behavior in the work at any one time. Hence, the worker's behavior that is being observed may change from
time to time. Second, the number of workers that are being observed may vary due to the scope of work, absenteeism of workers, and completion
time of activity. Finally, observer bias during observation may cause these variations. The number of observations in each box on the example
observation worksheet (Table 4.2) is summed and the result is placed in the right column of Table 4.2. These values are added to
Direct Work(DW) = 𝐷W(𝐷1 + 𝐷2 + 𝐷3 + ⋯ 𝐷38) = 32 + 22 + 31 + ⋯ 16 = 965
Preparatory Work(PW) = 𝑃W(𝐷1 + 𝐷2 + 𝐷3 + ⋯ 𝐷38) = 9 + 9 + 6 + ⋯ 4 = 244
Tool and Equipment(TE) = 𝑇𝐸(𝐷1 + 𝐷2 + 𝐷3 + ⋯ 𝐷38) = 12 + 3 + 2 + ⋯ 6 = 252
Material Handling(MH) = 𝑀W(𝐷1 + 𝐷2 + 𝐷3 + ⋯ 𝐷38), = 7 + 10 + 9 + ⋯ 7 = 288
This calculation is repeated for all activities and the result is reported in Table 4.3
Table 4.4 Total Activity Organisation
Craft workers spend approximately 3 hours (0.38 x 8 hrs.) of their day directly
installing materials to advance the project, as the site visited uses eight-hour shifts.
Supportive and delayed activities take up the remaining 5 hours per day. The
calculation is repeated similarly for the other work sampling categories (preparatory
work, tool and equipment, material handling, waiting, travel, and personal) and
reported in the right-hand column of table no. 4.4.
Table 4.5 Activity Percentage for Slab Formwork
Travel 6.67%
9.74%
Direct work
Waiting 37.89%
14.92%
Material handling
11.31%
Tools and equipment Preparatory work
9.89% 9.58%
Figure 4.1 Pie Chart Illustrating Slab Formwork Activity Results
Graph
Graph 4 .1 Pie Chart Illustrating Slab Formwork Activity Results, displays a pie chart
that illustrates the proportion of time spent on different categories of labour, and
reducing one category would result in more available time for direct-work activities.
Graph 4 .1 Pie Chart Illustrating Slab Formwork Activity Resultsdisplays the pie
chart for the example utilizing the results from Table 4.4
Time
8am-9am 9am- 10am- 11am-12pm lunc 1pm-2pm 2pm-3pm 3pm-4pm 4pm-5pm
10am 11am h
WS HA P HA P HA P HA P HA P HA P HA P HA P
X1 67 25% 96 36% 115 39% 109 34% 81 28% 103 35% 141 42% 80 30%
X2 53 20% 45 17% 30 10% 30 9% 53 18% 34 11% 23 7% 28 10%
X3 29 11% 28 10% 30 10% 30 9% 26 9% 31 10% 33 10% 33 12%
X4 47 18% 33 12% 27 9% 29 9% 39 14% 34 11% 33 10% 27 10%
X5 33 12% 28 11% 46 16% 78 24% 49 17% 46 15% 53 16% 48 18%
X6 19 7% 23 8% 29 10% 32 10% 16 6% 31 10% 31 9% 42 15%
X7 18 7% 17 6% 20 7% 18 6% 26 9% 19 7% 20 6% 14 5%
Sum 267 270 297 325 291 297 334 271
-
HA= stands for Hourly Activity, P= Percentage of slab formwork activities
Analysis Of Construction Productivity In Relation With Information Technology Page 31
MET's Institute of Engineering, Adgaon, Nashik
Observtion X1 X2 X3 X4 X5 X6 X7 CLP
Date
1 0.45 0.17 0.06 0.11 0.15 0.11 0.02 1.33
Each daily productivity was taken from Table 3.9 and each work sampling
proportion is calculated from Table 3.6 by taking the ratio of each work sampling
observation to total observation for that day. For example, for day one, the direct
work proportion calculated as
Day One Work Observation 32
Day One ( Direct Work )= = =0.45
Day OneTotal number of work observations 78
4.7.1 Normailty:
Dependent variables must be uniformly distributed across the board and for
each unit of measure. This suggests that the variable has a normal distribution and is
linearly related to the explanatory variables. The distribution of the residuals (the
difference between the actual and the expected productivity within the model) should
be rather normal if the relationships are linear and the variable is usually distributed
for each value of the variable. This is frequently evaluated by using a graph of the
standardized residuals' histogram. Since the marginal distribution of the residuals
follows a normal distribution, the histogram's form in the Figure serves as an example.
Therefore, activities involving column formwork do not break the notion of normality.
The graph of a histogram for slab concreting shown in appendix explains a similar
result.
4.7.2 Homoscedasticity:
The distribution of the explanatory variables should have nearly similar variability for
each predictor value. The residuals can be plotted against the outcome (productivity)
values and the explanatory variables to verify this assumption. If the model accurately
matches the information, when standard observed productivity is plotted against
expected productivity, the information would type a line from the lower-left to the
upper-right corner. That point should be a straight diagonal line from bottom left to
prime right in the Norman likelihood (probability) map. This would suggest that
activities involving column formwork do not significantly deviate from
homoscedasticity. The slab concreting normal likelihood graph shown in the appendix
demonstrates a comparable outcome.
4.7.3 Linearity:
The distribution of the explanatory variables should have nearly similar variability for
each predictor value. The residuals can be plotted against the outcome (productivity)
values and the explanatory variables to verify this assumption. If the model accurately
matches the information, when standard observed productivity is plotted against
expected productivity, the information would type a line from the lower-left to the
upper-right corner. That point should be a straight diagonal line from bottom left to
prime right in the Norman likelihood (probability) map. This would suggest that
activities involving column formwork do not significantly deviate from
homoscedasticity. The slab concreting normal likelihood graph shown in the appendix
demonstrates a comparable outcome
4.7.4 Correlation Analysis (R):
A correlation analysis had a correlation coefficient whose values vary from -1 to
+1. A correlation of positive one indicates that the two variables are faultlessly
related during a positive linear manner, and a correlation of negative one indicates
that two variables are perfectly related during a negative linear manner, whereas a
correlation of zero indicates that there's no linear relationship between the two
variables being studied. The take a look at multiple regressions is to ascertain
correlations between dependent and independent variables different from zero. Table
4.7 illustrates that each one activity has a correlation different from zero indicating
that assumption of correlation is achieved. For column formwork activity, the
strongest correlation may be seen from the inverse relationship between productivity,
and travel, and waiting. Therefore, productivity tends to increase when waiting and
travel on-site diminishes, which could be attributed to time available for work wasted
rather than the direct installing of material.
Table 4.9 Correlation: Work Sampling Proportion with CLP for column
formwork Activity
X1 X2 X3 X4 X5 X6 X7 K
X1 Pearson Correlation 1
X2 Pearson Correlation .262 1
Sig. (2-tailed) .038
X3 Pearson Correlation -.12 -.01 1
Sig. (2-tailed) .367 .978
X4 Pearson Correlation .34 -.05 -.067 1
Sig. (2-tailed) .006 .672 .599
X5 Pearson Correlation -.23 -.27 -.021 .227 1
Sig. (2-tailed) .077 .035 .873 .073
X6 Pearson Correlation -.36 -.25 .073 .279 .912 1
Sig. (2-tailed) .03 .045 .571 .027 .000
X7 Pearson Correlation -.54 -.14 -.084 .274 .425 .544 1
4.7.5 Multicollinearity
Predictor variables that are highly connected are said to be multicollinear.
There is a distribution of predictive power when independent variables are
multicollinear. This may have the paradoxical result that while the regression model
accurately predicts the dependent variable in this case, productivity, none of the
predictor factors significantly affects this prediction. As a result, while they may not
each significantly contribute to the model individually, they may explain a large
portion of the dependent variables together. Therefore, multicollinearity has the effect
of decreasing the predictive ability of each independent variable by the degree to
which it is related with the other independent variables. That is, once the others have
been taken into account, none of the predictor variables may still make a distinctive
and meaningful contribution to the prediction model. It is possible to request the
display of "Tolerance" and "variance inflation factor (VIF)" values for each predictor
in multivariable linear regression in order to check for multicollinearity (See Table
4.8).
Table 4.10 Tolerance and Variance Inflation Factor for Independent Variables
1
Tool and Equipment .901 1.11
0
Material Handling .772 1.29
5
Waiting .675 1.48
3
Travel .715 1.40
0
Personal .743 1.34
6
Slab Direct Work .470 2.12
Formwork 6
Preparatory Work .643 1.55
4
Tool and Equipment .586 1.70
6
Material Handling .613 1.63
2
Waiting .539 1.85
5
Travel .561 1.78
2
Personal .461 2.17
0
Slab Direct Work .470 2.12
Concreting 6
Preparatory Work .643 1.55
4
Tool and Equipment .586 1.70
6
Material Handling .613 1.63
2
Waiting .539 1.85
5
Travel .561 1.78
2
Personal .461 2.17
0
The proportion of the predictor's variance that cannot be explained by the other
predictors is given a tolerance value. In the following, extremely low numbers suggest
"overlap" or the sharing of predictive power. Less than 0.10 values might warrant
additional research. The variance inflation factor (VIF), which is calculated as
"1/tolerance," suggests that predictor variables with VIF values higher than 10 may be
worth further investigation.
The findings for this study are shown in Table 4.7 with labelled coefficients. As
indicated in Table 4.8, the tolerance value for each independent variable is larger than
0.1 and the VIF is less than 10, showing that multicollinearity is not an issue.
4.7.8 R-square
R-square, often known as the coefficient of determination, is a gauge of how
strong the prediction equation is. R-square, which measures the relationship between
the observed value of the dependent variable and the expected value predicted by the
fitted regression line, is the square of the correlation coefficient. In order to acquire R-
square, the researcher first computes the predicted value and then squares the
correlation coefficient between the predicted value and observed values. R-square
equals one (perfect linear relationship) if all of the observations fall on the regression
line. The absence of a linear relationship between the predictor and dependent
variables is indicated by an R-square of zero. Larger R 2 values, on the other hand,
show that the model is better at explaining variation in the dependent variable.
According to Table 4.9, the R-square value for this study's column formwork
activities was 96.3 percent, which is fairly high and demonstrates the model's strong
predictability. Changes in material handling, waiting, and transit for column formwork
operations can account for 96.3% of the variation in construction labour productivity.
The remaining 3.7% of the variation in labour productivity in the construction industry
is thought to be the result of random variability.
Additionally, the respective R-square values for the slab formwork and slab
concreting operations were 20.2% and 37.7%. This finding demonstrates that the
independent variable only accounts for 20.2% and 37.7% of construction labour
productivity. The prediction error is likely to be substantial given the low R-square
value, making the activity models insufficient for predicting actual construction labour
productivity.
4.7.9 F-Test
The F-test measures the relationship between the regression's mean square and the
residual's mean square (the residual being the discrepancy between the observed and
expected). By indicating that at least one of the independent factors is a significant
predictor of the outcome variable, the F-test functions as a preliminary screening.
Since the F statistic's significance value is less than 0.05, the variation explained by
the model is not just random variation. In this study, Table 4.9 must be examined in
order to determine the result's statistical significance. This test establishes that there
are several R in the population that differ from zero. The analysis is statistically
significant for column formwork, slab formwork, and slab concreting (Sig =.0, which
indicates p.05).
Taking slab formwork activities as an example, the standard error for the coefficient
on material handling is 0.45, which is much less than half the value of the coefficient
(3.92), so the estimated effect of material handling is still statistically significant in its
difference from zero.
4.7.10.5 T-Ratio
T- Ratio is the ratio between coefficient and standard error that tells how large the
coefficient concerning how much it varies in repetitive sampling. If the coefficient
differs a lot in repeated sampling, then its T-statistic will be smaller, and if it varies
little in repeated sampling, then its T-statistic will be larger. T-Test used to identify
whether the predictor significantly correlates to construction labor productivity or not
at a pre-established confidence level of 95%.
For this study, column formwork, slab formwork, and slab concreting activities had a
non-zero coefficient. Alt/hough slab formwork and slab concreting activities
statistically significant accord to the coefficients test, these models are limited to
predict construction labor productivity due to low R- square value. The model
comprised the entire significant explanatory variables shown as below:
Domain, CLP = {X4, X5 and X6}:[5 %< X4<=18%], [1 %< X5<=23%] and [3 %<
X6<= 18%]
the appendix. So the value of predicted construction labour productivity for slab
concreting activities calculated within this range as shown below.
Predicted (K ) at (x2 = 16%) = – 5.6X2 + 1.026, −5.6 𝑥 0.16 + 1.026 = 0.13
(minimum value)
Predicted (K )at (x2 = 5%) = – 5.6X2 + 1.026 = −5.6𝑥 0.05 + 1.026 = 0.76
𝑚aximum value)
Therefore, the value of predicted construction labour productivity for slab concreting
activities was between 0.13 and 0.76 M 3 per hour as shown in Figure 4.10. However,
the value of actual construction labour productivity were 0.14 and 0.96 M3 per hour.
The residual is its actual construction labour productivity minus its predicted
construction labour productivity, 0.96 -.76= 0.2and 0.14 –0.13= 0.01. It’s the portion
of the dependent variable (in this case, construction labour productivity) that is not
predicted by the explanatory variable (in this case, preparatory work). Random chance
of observation affects predicted construction labour productivity, and the residual
reflects the influence of these other factor.
remaining 10% because of the cross-validation sample as shown in Table 4.12. Next,
statistical regression on the larger sample is run; predicted scores are generated for
smaller cross-validation samples using the regression coefficients produced by the
analysis. Finally, predicted construction labor productivity (CLP) and actual
construction labor productivity (CLP) are correlated to find R-square for the smaller
sample. A large discrepancy between R- square for smaller and larger samples
indicates over fitting and lack of generalizability of the results of the analysis.
For this study, the correlation coefficient between predicted construction labor
productivity (CLP) and actual construction labor productivity equal to 99.5%, 45.8%,
and 19.2 % for column formwork, slab formwork, and slab concreting activities. This
result indicates that the predicted construction labor productivity of column formwork
activities are highly correlated (correlation greater than 50%) and closer to the actual
construction labor productivity.
However, for slab formwork and slab concreting activities, the correlation between
predicted construction labor productivity (CLP) and actual construction labor
productivity is low.
The coefficients of determination (R2) between predicted and actual CLP were 99.1%,
24.1%, and 7.8% for column formwork, slab formwork, and slab concreting
respectively as shown in Table 4.12. For column formwork, the cross-validation
sample is better predicted by the regression equation than the sample that generated
the equation. Consequently, output for column formwork activity fitted to actual
measurements. In addition, for slab formwork and slab concreting activities, the
coefficients of determination are low, errors are expected to be high, and the
usefulness of activity models for predicting actual construction labor productivity is
inadequate.
Furthermore, the mean absolute percentage error between predicted and actual
construction labor productivity (CLP) was 4.19%, 52.7%, and 76.7% for column
formwork, slab formwork, and slab concreting activities respectively. In this case,
column formwork activities had low mean absolute percentage error and high
accuracy percentage. Therefore, this model is better to predict construction labor
productivity. Contrary to this, slab formwork and slab concreting had high mean
absolute percentage error and low accuracy percentage so the model is limited to
predict construction labor productivity.
Table 4.15 Actual Productivity and Predicted CLP for Column Formwork
Activities
Graph 4.3 Predicted and Actual Construction Labor Productivity for column
Formwork Activities
Graph
Graph 4.4
4.4 Predicted
Predicted and
and Actual
Actual Construction
Construction Labor
Labor Productivity
Productivity for
for column
column
Formwork Activities
CHAPTER 5 CONCLUSION
5.1 Conclusion
1) This study used multiple regression approaches to create a construction labour
productivity model for formwork, reinforcing, and concreting tasks. The model for
concrete activity and reinforcement, however, has limited ability to forecast
construction labour productivity. The ability to estimate construction labour
productivity using slab and shear wall formwork activity was restricted, even for
formwork trade categories.
2) The column formwork activity model had a high degree of accuracy (95.81%) and
was well predicted.
3) In this study, a construction productivity estimate model for column formwork
activity was developed using three significant variables (material handling,
waiting, and personal).
4) Direct work and labour productivity in construction did not significantly
correspond. Therefore, in order to increase labour productivity in the construction
industry, management should concentrate on both direct work and other work
sampling activities.
5) The main reasons for delays in the study area include waiting and locating
materials, poor site planning, crew disobedience, insufficient or incomplete
drawings, inappropriate crew size and skill level, and waiting for other crews and
tools.
5.2 Recommendations
In order to meet the needs of today, let alone those of tomorrow, construction is a
collaborative activity that incorporates the skills and experience of many individuals.
Field research, survey findings, and observable issues all point to a number of issues
that have an impact on labour productivity in the construction industry. Poor site
layout, crew disobedience to instructions, finding materials, inadequate or missing
drawings, an insufficient team size, low crew skill levels, excessive preparation work,
waiting for supplies from other crews, and tools are some of these. The following
suggestion is made to address the issues affecting labourers' productivity in
construction enterprises.
REFERENCES
[1] “ Information Technologies applications for Construction.” In LIFE CYCLE
DOCUMENT MANAGEMENT SYSTEM FOR CONSTRUCTION, 37-46.
[2] Ahuja, Vanita, Jay Yang, and Ravi Shankar. “Study of ICT adoption for building
project management in the Indian construction industry.” Automation in
Construction (Elseveir) 18 (2009): 415-423.
[3] Bartake, Monali, Y S Patil, and R. M. Swamy. “Study of Barriers in Implementing
ICT in Indian Construction Industry.” International Journal of Research and
Scientific Innovation (IJRSI) 6, no. 11 (November 2019): 149-152.
[4] Begić, Hana, Mario Galić, and Zlata Dolaček-Alduk. “DIGITALIZATION AND
AUTOMATION IN CONSTRUCTION PROJECT’S LIFE-CYCLE: A
REVIEW.” Journal of Information Technology in Construction (ITCon) 27
(2022): 441-460.
[5] Cherian, Tisha Meriam, and L. Aravindh Kumaran. “E-Business in Construction
Industry: Opportunities and Challenges.” Indian Journal of Science and
Technology 9, no. 32 (August 2016): 1-6.
[6] Gaith, Farag H., Amiruddin Ismail, and Khalim A. R. “Application and efficacy of
information technology in construction industry.” Scientific Research and Essays
(Academic Journals) 7, no. 38 (August 2012): 3223-3242.
[7] Ghalia, A., and Rateb J. Sweis. “The relationship between information technology
adoption and job satisfaction in contracting companies in Jordan.” Journal of
Information Technology in Construction 15 (2010): 44-63.
[8] Kasim, N. B., and Peniel Ang Ern Soon. “The Awareness Of ICT Implementation
For Materials Management In Construction Projects.” International Journal of
Computer and Communication Technology (https://www.interscience.in/) 2, no. 3
(2011): 158-168.
[9] Kasim, Narimah. “ICT Implementation for Materials Management in Construction
Projects: Case Studies.” KICEM Journal of Construction Engineering and Project
Management 1, no. 1 (2011): 31-36.
[10] Sawhney, Anil, K Kamal Mukherjee, Pour Farzad Rahimian, and Steven Jack
Goulding. “Scenarioe thinking approach for leveraging ICT to support SMEs in
APPENDIX
Graph
Average hourly Ws
Direct Preparatory work Tools and Material handling Waiting Travel Personal CLP
work equipm
0.34 0.08 0.11 0.10 0.19 0.12 0.09 0.54
0.41 0.13 0.03 0.15 0.14 0.07 - 0.85
0.33 0.11 0.08 0.13 0.19 0.13 0.10 0.53
0.41 0.07 0.08 0.15 0.13 0.07 0.02 0.88
0.33 0.05 0.11 0.12 0.20 0.15 0.13 0.48
0.34 0.07 0.06 0.13 0.14 0.07 0.08 0.81
0.43 0.14 0.10 0.10 0.08 0.05 - 0.99
0.33 0.10 0.03 0.13 0.19 0.13 0.10 0.51
0.33 0.09 0.09 0.13 0.19 0.13 0.10 0.54
0.38 0.10 0.09 0.15 0.17 0.11 0.07 0.63
0.35 0.10 0.11 0.17 0.18 0.11 0.08 0.59
0.39 0.06 0.13 0.14 0.16 0.10 0.05 0.70
0.33 0.11 0.12 0.17 0.23 0.17 0.16 0.42
0.42 0.02 0.13 0.08 0.15 0.08 0.01 0.74
0.39 0.08 0.06 0.10 0.08 0.04 0.06 1.02
0.56 0.13 0.10 0.09 0.15 0.08 0.01 0.74
0.38 0.05 0.06 0.11 0.17 0.11 0.06 0.63
0.44 0.17 0.09 0.10 0.15 0.08 0.02 0.74
0.43 0.09 0.13 0.07 0.15 0.08 0.03 0.74
0.39 0.09 0.08 0.09 0.13 0.06 0.02 0.88
0.33 0.11 0.18 0.08 0.19 0.14 0.10 0.51
0.37 0.13 0.10 0.13 0.18 0.11 0.08 0.59
0.40 0.11 0.08 0.05 0.16 0.09 0.04 0.70
0.31 0.07 0.12 0.15 0.11 0.05 0.06 0.88
0.39 0.05 0.08 0.11 0.17 0.10 0.06 0.66
0.41 0.13 0.11 0.07 0.11 0.05 0.07 0.89
0.39 0.13 0.13 0.09 0.17 0.10 0.05 0.66
0.41 0.10 0.13 0.14 0.16 0.09 0.03 0.72
0.37 0.06 0.05 0.10 0.18 0.11 0.08 0.59
0.35 0.07 0.14 0.11 0.14 0.07 0.04 0.81
0.37 0.13 0.09 0.12 0.11 0.05 0.08 0.88
0.39 0.07 0.16 0.11 0.17 0.10 0.05 0.70
0.33 0.06 0.11 0.11 0.19 0.12 0.10 0.54
0.42 0.09 0.11 0.07 0.16 0.09 0.03 0.73
0.44 0.15 0.09 0.10 0.13 0.06 0.05 0.88
0.34 0.12 0.06 0.15 0.08 0.05 0.05 0.97
0.40 0.07 0.15 0.15 0.16 0.10 0.05 0.70
0.41 0.12 0.08 0.15 0.16 0.09 0.04 0.72
0.38 0.06 0.03 0.11 0.17 0.10 0.06 0.65
0.43 0.11 0.17 0.15 0.15 0.09 0.03 0.73
0.32 0.15 0.13 0.15 0.14 0.07 - 0.83
0.36 0.08 0.08 0.13 0.13 0.06 0.08 0.88
0.38 0.10 0.12 0.15 0.13 0.07 0.05 0.88
0.36 0.08 0.11 0.10 0.13 0.06 0.10 0.88
0.38 0.11 0.12 0.15 0.12 0.06 0.03 0.88
0.41 0.13 0.14 0.07 0.16 0.09 0.03 0.72
0.34 0.12 0.09 0.09 0.14 0.08 0.03 0.74
0.34 0.12 0.05 0.08 0.18 0.11 0.09 0.56
0.43 0.13 0.12 0.06 0.09 0.05 0.02 0.96
0.44 0.07 0.10 0.10 0.03 0.04 0.04 1.05
0.42 0.11 0.10 0.07 0.11 0.05 0.08 0.89
0.39 0.10 0.03 0.15 0.17 0.10 0.06 0.66
0.41 0.10 0.13 0.13 0.16 0.09 0.04 0.71
0.47 0.05 0.05 0.07 0.13 0.06 0.04 0.88
0.40 0.13 0.12 0.16 0.14 0.07 0.05 0.85
0.34 0.05 0.10 0.11 0.18 0.11 0.08 0.58
0.50 0.12 0.07 0.08 0.15 0.08 0.02 0.74
0.34 0.12 0.16 0.09 0.01 0.03 0.03 1.07
0.37 0.05 0.12 0.15 0.18 0.11 0.07 0.60
0.34 0.08 0.17 0.10 0.18 0.12 0.09 0.55
0.38 0.13 0.13 0.11 0.13 0.06 0.08 0.88
0.26 0.12 0.17 0.07 0.18 0.15 0.09 1.07
0.34 0.10 0.22 0.15 0.18 0.12 0.09 0.55
0.50 0.08 0.11 0.09 0.14 0.08 0.04 0.76
0.41 0.11 0.17 0.05 0.15 0.08 - 0.74
0.38 0.13 0.08 0.11 0.17 0.11 0.07 0.63
0.40 0.13 0.10 0.11 0.16 0.10 0.05 0.70
0.31 0.05 0.11 0.07 0.13 0.06 0.06 0.88
0.33 0.08 0.07 0.14 0.20 0.16 0.14 0.47
0.36 0.07 0.16 0.13 0.18 0.11 0.08 0.59
0.33 0.10 0.14 0.17 0.23 0.17 0.15 0.46
0.40 0.12 0.09 0.18 0.16 0.10 0.05 0.70
C.1 Calculating Actual Errors for Activity Percentage for Column Formwork,
slab concreting
With the activity percentages calculated, the actual error of each percentage may be
calculated using the binomial distribution.
z 2 p( 1− p)
d= 1/ 2
n
where d is the error, Zα/2 = 1.96 corresponding to a confidence level of 95%, p is the
activity percentage being considered, and n is the total number of observations. For
this particular case, the total number of observations is 1271.
X1 X2 X3 X4 X5 X6 X7 K
X1 Pearson 1
Correlation
Sig. (2-tailed)
X2 Pearson -.065 1
Correlation
Sig. (2-tailed) .697
X3 Pearson -.026 -.034 1
Correlation
Sig. (2-tailed) .876 .841
X4 Pearson -.113 -.005 -.268 1
Correlation
Sig. (2-tailed) .501 .976 .104
X5 Pearson -.226 .111 -.096 -.288 1
Correlation
Sig. (2-tailed) .172 .509 .567 .079
X6 Pearson -.303 -.095 -.247 .095 -.244 1
Correlation
Sig. (2-tailed) .064 .570 .136 .569 .140
X7 Pearson -.288 -.446** -.158 -.123 -.084 .001 1
Correlation
Sig. (2-tailed) .079 .005 .343 .463 .617 .998
K Pearson .352* -.166 .192 -.450** .149 -.139 -.178 1
Correlation
Sig. (2-tailed) .030 .319 .248 .005 .372 .404 .285
*. Correlation is significant at the 0.05 level (2-tailed).
Table E-2 Correlation: Work Sampling Proportion with CLP for shear wall
Formwork Activity
X1 X2 X3 X4 X5 X6 X7 K
X1 Pearson 1
Correlation
Sig. (2-tailed)
X2 Pearson -.259* 1
Correlation
Sig. (2-tailed) .028
X3 Pearson -.125 .041 1
Correlation
Sig. (2-tailed) .297 .731
X4 Pearson -.286* -.010 -.044 1
Correlation
Sig. (2-tailed) .015 .930 .714
X5 Pearson -.236* -.010 .001 -.093 1
Correlation
Sig. (2-tailed) .046 .932 .995 .439
X6 Pearson -.34** .119 -.041 .076 -.282* 1
Correlation
Sig. (2-tailed) .004 .320 .732 .524 .016
X7 Pearson -.062 -.251* -.173 -.172 -.174 .034 1
Correlation
Sig. (2-tailed) .606 .033 .146 .150 .144 .778
K Pearson .109 -.034 -.93 .015 .066 -.027 .128 1
Correlation
Sig. (2-tailed) .361 .775 .06 .903 .584 .822 .284
*. Correlation is significant at the 0.05 level (2-tailed).
X1 X2 X3 X4 X5 X6 X7 K
X1 Pearson 1
Correlation
X2 Pearson -.278 1
Correlation
Sig. (2-tailed) .101
X3 Pearson -.396* .099 1
Correlation
Sig. (2-tailed) .017 .567
X4 Pearson -.325 -.279 -.326 1
Correlation
Sig. (2-tailed) .053 .100 .053
X5 Pearson -.267 -.086 .201 -.100 1
Correlation
Sig. (2-tailed) .116 .618 .239 .563
X6 Pearson -.326 -.140 -.022 .118 .37* 1
Correlation
Sig. (2-tailed) .052 .416 .899 .494 .025
X7 Pearson -.533** -.208 -.063 .513** .115 .134 1
Correlation
Sig. (2-tailed) .001 .224 .715 .001 .504 .437
X1 X2 X3 X4 X5 X6 X7 K
X1 Pearson Correlation 1
X1 X2 X3 X4 X5 X6 X7 K
X1 Pearson 1
Correlation
X2 Pearson -.277* 1
Correlation
Sig. (2-tailed) .047
X3 Pearson .007 -.134 1
Correlation
Sig. (2-tailed) .959 .343
X4 Pearson -.409 **
-.082 -.176 1
Correlation
Sig. (2-tailed) .003 .563 .211
X5 Pearson .031 -.065 -.186 -.292* 1
Correlation
Sig. (2-tailed) .826 .649 .186 .035
X6 Pearson -.178 -.011 -.369** -.108 .204 1
Correlation
Sig. (2-tailed) .206 .939 .007 .448 .148
X7 Pearson -.141 -.181 -.050 -.117 -.197 .185 1
Correlation
Sig. (2-tailed) .323 .203 .726 .414 .165 .195
K Pearson .459** -.121 -.028 -.321* .177 -.027 -.070 1
Correlation
Sig. (2-tailed) .001 .395 .841 .020 .211 .848 .627
*. Correlation is significant at the 0.05 level (2-tailed).
X1 X2 X3 X4 X5 X6 X7 K
X1 Pearson 1
Correlation
Sig. (2-tailed)
X2 Pearson .152 1
Correlation
Sig. (2-tailed) .303
X3 Pearson -.010 -.168 1
Correlation
Sig. (2-tailed) .947 .254
X4 Pearson -.051 -.036 -.037 1
Correlation
Sig. (2-tailed) .728 .806 .804
X5 Pearson -.264 .084 -.201 -.371** 1
Correlation
Sig. (2-tailed) .070 .573 .170 .009
X6 Pearson .215 -.004 -.41** -.104 .182 1
Correlation
Sig. (2-tailed) .143 .979 .004 .481 .215
X7 Pearson .325* -.107 -.069 -.126 -.190 .195 1
Correlation
Sig. (2-tailed) .024 .468 .640 .392 .197 .184
K Pearson .131 -.161 -.276 -.207 .012 .081 -.012 1
Correlation
Sig. (2-tailed) .375 .275 .057 .158 .936 .584 .933
*. Correlation is significant at the 0.05 level (2-tailed).
X1 X2 X3 X4 X5 X6 X7 K
X1 Pearson 1
Correlation
Sig. (2-tailed)
X2 Pearson .063
Correlation
Sig. (2-tailed) .804
X3 Pearson .147 -.042 1
Correlation
Sig. (2-tailed) .562 .870
X4 Pearson .592** .083 .312 1
Correlation
Sig. (2-tailed) .010 .743 .207
X5 Pearson .014 -.260 -.158 -.223 1
Correlation
Sig. (2-tailed) .955 .297 .530 .373
X6 Pearson .260 .002 .120 .265 .538 1
Correlation
Sig. (2-tailed) .298 .992 .635 .289 .021
X7 Pearson -.294 .251 -.528 -.50 .298 -.207 1 -.
Correlation
Sig. (2-tailed) .252 .331 .029 .041 .245 .426
.
K Pearson .111 .199 .222 .176 .007 .364 -.299 1
Correlation
Sig. (2-tailed) .660 .429 .375 .484 .979 .138 .244
*. Correlation is significant at the 0.05 level (2-tailed).
Figure E-4 Histogram of Residuals with Normal curve for Slab Concreting
Activities
Figure E-5 Normal Probability Plots Regression standard Residual for Slab
Concreting Activities
Figure E-6 Scatter Plot of Predicted Values vs. Residuals Slab for Concreting
Activities