You are on page 1of 1

UPS Checklist

Southco - Ranjangaon
Client : Inspection Report No
Consultant : Date
Package : Electrical Inspection Request No
Vendor : Date
Description of Work :
Wing : Dwg.Ref.No Rev : Inspection Request
Floor : Details : Inspected by By Time
Location
Sl.
Description Yes No Remarks
No
1 Check the specifications of UPS as per the approval
2 Ensure that the equipment is lowered down slung by lifting hooks
only
3 Check for the physical damages if any during transit
4
Ensure that while shifting the equipment it is inched only on rollers

5 Panel installation as per drawing, line & level, alignment of panel,


clearance between wall/partition
6
Check the cable entry provision for incoming and outgoing

7 check the instrument relays


8 Check the indications and meters
9 Check the batteries & specifications
10 Check the meters ( Volt, Amps, Frequency,KWH,Phase indicator,
running Hrs , Battery charger etc )
11 check the UPS remote panel
12 check the remote panel breakers
13 Check the mountings of UPS
14 Check the earthing
15 Check the exhaust fan condition

Observations if any :

The above works have been completed and checked and are ready for inspection
Vendor : Consultant : CBRE :

Signature : Signature : Signature :

Name : Name : Name :

Format No. F029-QC-Ch-118/Rev01/Oct2013

CBRE South Asia Pvt. Ltd. Project Management, India 1 of 1