You are on page 1of 5

SOUTHERN RAILWAy

Headquarters Office,
S&T Projects Wing,
ParkTown,Chennai-3

No.SG.136/1/Projects/Policy/Vol VII .Dated: 19/11/2018

Dy.CSTE/P /MS
Dy.CSTE/P /TPJ
Dy.CSTE/P /PT}
Dy.CSTE/OFC/MAS

Sub: Procedure order for floating and finalizing. of composite tenders for
S&T Project/Works.

A copy of Joint Proced:ure Order signed by PCSTE,PCE & PCEE for procedure
order for floating and finalizing of composite tenders for S&T Project/Works in terms
of Railway Board's eircular No.2007ISIG/SGF/2 dated 23/04;/2007, is enclosed Jar
information and necessary action.

End: As above.

.LAKSHMI NARASIMHA~W \ l't


SSTE/P/II/HQ
For CSTE/ PROJECTS .
./"
Copy to: tCSTE PCE PCEE

Signature Not
Verified
Digitally signed by
GUGULOTH
YUGENDER
Date: 2022.10.17
18:50:13 IST
Reason: IREPS-CRIS
Location: New Delhi
JOINT PROCEDUR.E ORDER

PROCEDURE ORDER FOR FLOATING AND FIi\fALISING OF COMPOSJTE TENDERS


FOR S&T PROJECTM'ORKS IN TERMS 0= RAILWAY SOARD'S CIRCULAR
No.2007/SIG/SGF/2 DATED 23-04-2007.
'.

1.0 Preamble: Railway Board has issued a policy circular no. 20071SIG/~GFi2 dated
23.04.2007 communicating their guidelines that Railways may float and finalise the
composite tenders for works at wayside stations and IBSs accordingly.

1.1 During the monthly progress review rneetinqs GM!S.Rly has suggested toexecute
the sanctioned LC gate works by floating composite tenders as these works involves
S&T, Civil Engg, Electrical Engg depts. Thescope.of works covered under these
composite tenders for LC gates, IPS,IBS, AFTC, MSDACetc. are, S&T. Civil Engg
(Building) and Electocal (General) works under plan heads 29. 16.anct.:~3. a~sed .on
the guidelines issued by the above Railway Board .circularahd· as per the
instructions of GM this Joint Procedure Order is being· issued for implementation.

2.0 GENERAL ! "

2.1 The Composite Tender for types of S & T projects sha.llinclude all sOb-works the of
ProjectsM'orks in a single contract so that various sub-works/activities ate properly
matched and dovetailed and the overall project management..is effective to
complete the project in time. . .

2.2 Broadly major components of a Composite Tender may ihctude:-

i) Field survey and assessments of requirements.


ii) System design, Documentation and Approval.
Iii) Site preparation and construction of Service Buildings/Structures.
iv) Electrification of Service Buildings.
v) Supply/Provision of furniture. and accessory items:
vi) Instaifation and testing of the Main·' ProjectfNork of signalling and or
Telecommunications (S&T) system. .
vii) Commissioning and handing over of tha MaIn Project of S & T system for
operational use.
viii) Monitoring and maintenance of the Projec: (or 9 weeks (2 months) after
commissioning and putting to operational use.
ix} Completion Documents. .

2.3 Each project/work be planned, design finalise anp activities or wor~s:d[mtifjed


such that these can be included in the following modules ·ofthe composite tender
schedule. .,
,f
"1 ;,' .-i ...• ,

2.3.1 Sigll~iing W.QFl<sSchedule:..


a)~?~·~uP6IY::···. ".:.'~~;
, ." ".
b) ;; t'Work~j'" ....•.':',•.. ",~.-.'.:'".'
. ::'1 "',:. ;:.' .: '.~-; ' ~'.":. "?'~;!": ~·.f' .... ",

2.3.2 Te}e6,m'W~~:Schedu~~'~:Y'
a) Supply.
b) Works .
..

2.3.3 E~'gi~~~h9' W~rkS·Schedule'. <.. -,'. .


a) Foundation and tonstitlct"loriofservice buildings/structures.
b) Supply of steel and cement. .
c) Steel/wood work.
d)' : ,Y'J,~tersupply & Sani~ary and Drainage arrangements (if any)

2,3.4 Electrj~al Works SChedule


a) Electrification of the service buildings/structures.
b) l[lst~lIatlon:of stand along AC units.
c) Provision of Power Cable, AT etc.

2,3.5 Miscellaneous Schedule


a) field ~urvey
b), ;,,:;" S¥st~o:l design
c} '~.::,:;/.ooriWtientatlon. ...' .4.

0)."" :,·ffa1nthg .
.. ·,:-r ... .... .
2.3.6 A ,po~mp..r:~t).e~siveBar: ·.bhartlPERT chart interlinking ail the activities in their
sequence, ]orming part of the above schedules from 2.3.1 to 2.3.5 of the S&T
Project~cirks will be prepared before the commencement of works for proper
monitoring of progress of works.

2.4 The Composite S '& T ''Contr~cl sbould beso finaUzedthat the main contractor is
obliged to execute Civil & ElectrfMI. Engineering Works either himself (if he has
the expertise, experience and approval) or through experlenced and approved
contractorsfor
. ::
such works in the Division.

2.5 CSTEICSTE (Proj.) or CSTE(C) would be over all responsible for preparation of
tender schedule/papers for the award, handling of the composite contracts.
supervision, timely completion of·3& T projectslwork and for liaison from time to,
time with' EngIneer for 'the purposes of approval of design and drawings of the
bUildings/structures and with Electrical Engineer for electrical sub-works of the
composite contracts.

2.6 Foran optimum progress of a Conposite S & T contract, the main contractor may
sub,G9JitrfJc.t·sub-WOrks Qf buildings/structures. electrification of buildings etc. to
su~ntraetor(s) with the approvalottbe Railway. .

2.7 .For construcuon of all buildings/structures detail guidelines and instructions that
. may befssued by ChIef EngineElr of the Railway, RDSO/Board on the subje
fromtime to time to be followed,

~. "
~~
2

------'----=---~
....
-.~'~~--'----~--~----.-- ---- --_ -
..
;:" .. '---' ,

2.8 Likewise for Electrical sub-works. detail gLlidelineslinstructions that may be


issued by Chief Electrical Engineer of the Railway; ROSO/Board on the, subject
from time to time to be followed. .... . .•.
,. ....•.',~: \...·'i-.· .~.', :

3.0 SIGNALLING, TELECOMMUNICATION AND MISCELLANEOUSM09ULES:-

These shall be prepared as per the detailed {luidelines .already av~I~51~ ·thrqugh
Manuals and RDSO/Railway Board Instructions on ..each type,:.~f· work and
technology. . ' .'.
, ,

4.0 ENGINEERING MODULES '" .


4.1 Site plans for each service building be approved at the, divlslonal level,

4.2 Detailed building drawings including foundation and RCC details etc., should be
got prepared and approved from Engineerinu Branch (Construction or Open Line
as the case may be). .. . .. .

4.3 StandardlTypicalfTie-plans, if any. and which have been in Lise and approved by
.,. the Division for the concerned stafions/sections should be adopted, .

4.4 Based on the drawings, the schedule and quantities must be worked out by
SE/SSE (Works) for each stage of the engineering work of service buHding/tower.
'. :':" . '.. , ... ",
4.5 Based on the Engineering SOR (updated) and basic rates of ste.elw.rk.~~!JPply of
steel and cement. wood work etc., prevailinu on the Division, the basic cost of the
service building/structure be worked out by SElSSE{Worksl and approved by the
Nominated Engineedng Offlcerto form part of the Engineering work schedule ..
.~ .', > "'-''':-~.'
.. ' .
4.6 Supervision and check ..~
..
'

.-'.
'. ~ "

4..6.1 Section Engineer (SE/Senior Section ErlgiOeer (SSE), Junior Engineer (JE)
(Works)rnay bemade responsible for superVision, check of the work and' keeping
record in the field book at each of the levels of the service building work:

a) Foundation level
b) Plinth level
'.
c) Lintel level
d) Roof casting
"-
.
e) Final completion
.•.
4.6.2. Before taking over the structures from contractor, joint inspection tO'be ;done by
JElSE {works} and SE (Sig.) I SE (Tele) so as 10 ensure that service building is in the
conformity with the technical requirements of use' departments.

4,6,3 For supervision and check at officer level, AXEN/ADEN or XEN/DEN .qe deployed
for projects or combination of Projects I \Vork~of substantial value;'The'existing
setup will be utilized. "

3
.•
; ,,' ".-t":",' ','
4.7 '"Payme'ni:(.··

4.7.1' The measurements of the works must be recorded IMhe'MB In accordance with
the,1ftstr\ictionofEngg. Code by SE I~SE (Works) ..
.'~·il~:::':;'J~~:~~t~.},~1".·., I·
f
<... '." :;.' ' -
4.7.2 ;!est.~~Uhe
. t. '. • .• ', .. :- .'.~ - :. "-: '
levsfofAXEN/ADEN
/' .~ '. .'
.

5.0 .:~l~~:~~eALSCH~~~LES
5.1 ~'~c~ifi.;'ti~n of S&T service~lIdings covering provision of lights. fans/exhaust
fan~ etc may be included as apart schedule of the composite S&T tenders.

5.2 ~AU the generat'ElectricaHtlill'Tls: shc:>uld·becohfirming to relevant BIS. The quantity


, schedules shall be prepared based on the approved site plan by Sr. DEE/D~~
(G).

5.3 The .mam contractor I Electrica' sub-contractor shall have requisite electrical
licence} certificate for executing electrical works.

5.4 All electrical works will be inspe;tedand fitness for charging/commissioning will
be done-,bySr,
. ..;"
OEElDEE(G)or his nominated representative .

5.7 supervi$1On and check

5.7.1 S~e supervtston J shall t>~by JFJSE (Elec) of DiviSion/Construction Unit and
re~idln.g ofthe-same. in the field oooks.
~ ::.,;~'~~~';,~;;.\~'-,;~.,. ~ ._~-·I~'!- .,.... ' •. '.

5.7.2, THe;'fit\a"r.ihspection "and acceptance of the work shall be by SE (Elec) of the


Q!vi~i~1'!~r;ldc;~plet~()Q .certificate.issued.
. . '., .

5.8 Payfri-ent·
f,:~·:r_~.'.\.
5.8.1 Measurements of the work must be recorded in the MB in accordance with the
instructions of Engineering Code by SE (Elec).
\ ", '.' . ..: ';...... '; '--'

5.8.2 Test check at the Jevel ofAXEElAJEE.

6.0 HANDING OVER

6.1 The cOmpletion drawings for Engir eering and Electrical portion of the composite
S&T Contract must be prepared lased on the stipulations of the Engineering
Code/Manual and Elect.rical Manuals' which shall include Site Registers, Field
Books, Completion Drawings.etc,
...•. "

~re-. "
,
.
"
"

,~ ..
- ",