DETYRE KURSI
Lenda: Teknik Kantieri

Punoi: Teba Spahiu


Pranoi: ING. Diana Bardhi
OBJEKTI; RIKONSTRUKSION I BANESES INDIVIDUALE TRE KATE
Asresa; FARKE E VOGEL. Bashkia Tirane
Zhvilluesi; BAJRAM KASTRATI
PREVENTIV PUNIMESH

Analizes
NR /Man Pershkrimi i punimeve Njesia Sasia Çmimi Vlera

A. PUNIME PRISHJE
1 2.426 Prishje mur tulle pa pastrim m3 32 620 19,840
Shuma A Leke 19,840
B. PUNIME NDERTIMI
1. PUNIME DHEU
Shuma 1 Leke 0
2. PUNIME BETON ARME
Shuma 2 0
3. PUNIME MURATURE
1 2.70/2 Mure tulle I lehtesuar t=25 cm m3 35 7950 278,250
Mur me tulle me 6 vrima, t=12cm, h~3m, llaç perzier
2 2.86 m3 16 9017 144,272
M15
Shuma 3 Leke 422,522
4. PUNIME HIDROIZOLIMI (mbulese)

2.197 Hidroizolim me emulsion bitumi dhe 2 shtrese k katrama m2 116 1232 142,879

2.239/a Shtrese termoizoluese me polisterol t=10 cm m2 116 2658 308,340


Ulluk shkarkimi vertikal me llamarine xingat Ø 100
2.209 ml 10 693 6,930
mm
2.206/b Kasete shkarkimi me llamarine bakri 1.0mm cope 1 3224 3,224
Shuma 4 leke 461,373
5. PUNIME SHTRESASH
1 2.262/1 Shtrese betoni c7/10 m3 16 6662 106,592
2 2.267/b Shtrim veshje pllake gres porcelan m2 351 2446 858,546
3 2.273/1 Davancal graniti t=2cm "ROSA BETA" m2 13 7506 97,578
Shuma 5 Leke 1,062,716
6. PUNIME SUVATIMI DHE VESHJE
1 2.300 Suvatim I tavani m2 234 765 179,010
2 2.303/1 Suvatim I mureve brenda m2 772 562 433,864
Veshje fasade me polisterol kompakt jeshil t=5cm +
3 2.358/b m2 273 2700 737,100
rrjete + suva.grafiato
4 an Montim wallpanel pvc. m2 90 2800 252,000
Shuma 6 Leke 1,601,974
7. DYER DHE DRITARE
19 2.383/1 F.V Dyer dru importi cilesi e dyte m2 23 8500 196,860
20 2.395/1 FV.dyer dritare duralumil dopio xham m2 56 15000 840,000
Shuma 7 Leke 1,036,860
8. PUNIME TE NDRYSHME…( te parashikuara )
21 2.404 Bojatisje hidoplastike brenda m2 281 185 51,985
Shuma 8 Leke 51,985
SHUMA B (1÷8) Leke 4,637,430
C. PUNIME ELEKTRIKE
1 2.485/4 F.V. Celes ndricimi 16A 2 polar cope 6 471 2,826
2 2.485/1 F.V. Celes ndricimi 16A 1 polar cope 18 443 7,974
3 2.485/6 F.V. Celes ndricimi 16A tip buton cope 15 1533 22,995
4 2.485/6 F.V. Celes ndricimi 16A invertitor/deviat cope 12 1533 18,396
5 2.485/d F.V. Prize Shuko universale 16A e bardhe cope 30 510 15,300
6 2.485/a F.V Priza bivalente 220V 10A 2P-T cope 12 585 7,020
7 Analize F.V. Prize TV Fundore cope 18 631 11,363
8 Analize F.V. Shperndares TV 1/6 cope 8 1527 12,214
9 Analize F.V. Prize Interneti Cat6 cope 3 937 2,811
10 Analize F.V. Koke interneti Cat6 cope 3 55 164
11 Analize F.V. Prize Telefoni Cat5 cope 3 937 2,811
12 Analize F.V. Prize TV-SAT cope 3 942 2,827
13 Analize F.V. Kuti,suport,pllaket,3M, B/M cope 12 350 4,200
14 2.487/d F.V. Kuti,suport,pllaket,4M, B/M cope 12 407 4,884
15 Analize Tape fallso cope 10 48 476
16 2.487 Kuti shperndarese B/M PT5 cope 21 121 2,541
17 2.487 Kuti shperndarese B/M PT7 cope 9 121 1,089
18 2.487 Kuti shperndarese B/M PT9 cope 6 121 726
19 Analize F.V.Kabell FG7OM1,3x1.5mm2 m 180 168 30,276
20 Analize F.V.Kabell FG7OM1,3x2.5mm2 m 750 238 178,275
21 Analize F.V.Kabell FG7OM1, 3x4mm2 m 36 343 12,359
22 Analize F.V.Kabell FG7OM1, 5x2.5mm2 m 150 368 55,260
23 Analize F.V.Kabell FG7OM1, 5x4mm2 m 65 410 26,650
24 Analize F.V.Kabell FG7OM1, 5x6mm2 m 25 465 11,625
26 Analize Bashkuse per tub fleksibel d=25/32 m 300 35 10,440
Shuma C Leke 445,503
PUMIME MEKANIKE.
1.PUNIME HVAC (NGROHJE-VENTILIM)
Shuma 1 Leke 0
2. PUNIME MN Z (MBROJTJA NGA ZJARRI )
F.v. Dedektor Tymi DRP-100 cope 12 3000 36,000
F.v. Fikse zjarri 6 kg cope 4 4500 18,000
Shuma 2 Leke 54,000
SHUMA D (1÷2) Leke 108,000
E. PUNIME HIDRAULIKE
F.V Tuba e rakorderi ujesjellesi PPR d=20~32mm, PN
1 2.491/c ml 45 330 14,850
16
2 2.491/b F.v Tub dhe rekorderi polipropyleni Pn-16 Dn-25 ml 30 304 9,120
3 2.491/b F.v Tub dhe rekorderi polipropyleni Pn-16 Dn-20 ml 30 304 9,120
4 2.494/2 F.V saracineska bronzi Ø 1 " = 25 mm cope 12 1305 15,660
5 2.494 F.V saracineska bronzi Ø 1/2 " = 15 mm cope 4 795 3,180
6 An F.v kontator Pn-16 Dn-1 " cope 4 5362 21,448
7 An F.v Xhunto polipropylen Pn-20 Dn-32x1 " cope 4 400 1,600
8 An F.v Brryle polipropylenPn-16 Dn-32x1 " cope 4 220 880
9 An F.v Tape polipropylen Pn-20 Dn-20 cope 4 100 400
10 An F.v tub PVC Dn-125 ml 9 1250 11,250
11 2.521 F.v tub PVC Dn-110 ml 9 1194 10,746
12 An F.v tub PVC Dn-50 ml 52 350 18,200
13 An F.v Brrage PVC Dn -110x110x110-45 ° cope 8 400 3,200
14 An F.v Brrage PVC Dn -110x50x110-45 ° cope 8 400 3,200
15 An F.v Brrage PVC Dn -50x50x50-45 ° cope 4 200 800
16 An F.v Brryle PVC Dn -110x110-45 ° cope 4 350 1,400
17 An F.v Brryle PVC Dn -110x110-90 ° cope 4 350 1,400
18 An F.v Brryle PVC Dn -50x50-45 ° cope 8 250 2,000
19 An F.v Brryle PVC Dn -50x50-90 ° cope 4 250 1,000
20 An F.v Pj pastrimi PVC Dn -110 cope 4 550 2,200
21 2.515 F.V pilete dyshemeje Ø 50 mm cope 4 1925 7,700
SHUMA E Leke 139,354
TOTAL (A+B+C+D+E) Leke 5,350,127
Fond rezerve 3 % 160,504
SHUMA 5,510,631
TVSH 20% 1,102,126
TOTAL SHUMA 6,612,757
PREVENTIVOI ;
ING,GEZIM SEFERI
GRAFIKU I PUNIMEVE
MUAJ

PERSHKRIMI I PUNIMEVE 1 2 3 4 5 6 7 8 9 10 11 12

PUNIME PRISHJE,GERMIM DHEU ------------

PUNIME BETON /ARME -------------------------------

PUNIME CATI ------- ----- --

PUNIME SUVATIMI ----------------------------------------------------------------

PUNIME SHTRESASH ------------------------------------------------------------------

BOJATISJE SISTEMIM TERRENI ------------------------

PERGATITI: Teba Spahiu