You are on page 1of 60

REKAPITULASI ENGINEER'S ESTIMATE

PEKERJAAN :
LOKASI :
TAHUN : 2021

NO URAIAN PEKERJAAN HARGA (Rp)

A Plating/Landscaping -
2,0 Shrubs -

Jumlah -
PPn 10% -
Jumlah -
Dibulatkan -

Terbilang : Seratus Dua Puluh Juta Rupiah

Jambi, 2021

Direktur
PEKERJAAN :
LOKASI :
TAHUN : 2021

NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA


(RP) (RP)

A Plating/Landscaping
1 Tree 25 tree
1.1 Tabebuya (Yellow)-(Tabebuia aurea) 46 tree
1 Kamboja Bali (White)-(Plumeria rubra)
2,0 Shrubs
2.1 Hanjuang (Cordyline fruticosa) 21 tree
2.2 Palem Merah (Cyrtostachys lakka) 6 tree
2 Pisang Bedak (Calathea lutea) 335 tree
3,0 Bushes
3.1 Canna Presiden (Canna indica) 180 tree
3.2 Palem Wregu (Raphis humilis) 343 tree
3 Tradescantia (Tradescantia) 45 tree
4,0 Ground Cover
4.1 Lily Brazil (Dianella tasmanica) 189 tree
4.2 Lantana (Lantana camara) 166 tree
4.3 Bakung Lily (Hymenocalis littoralis) 604 tree
4 Rumput Gajah Mini (Pennisetum Purpureum) 490 m2
5,0 Vines
5.1 Ceguk Wudani (Combretum indicum) 18 tree
5.2 Lonicera Rambat (Lonicera japanica) 18 tree
5 Lee Kuan Yew (Vernonia eliptica) 34 tree
6,0 BOX PLANTER (G1) 106 unit 350,000.00 37,100,000.00
7,0 BOX PLANTER (G2) 3 unit 320,000.00 960,000.00
8,0 RAILING TANK & BRC 80 unit

Planting Media
1 Sand 23 m3 90,000.00 2,070,000.00
2 Gravel 110.4 m3 400,000.00 44,160,000.00
3 Fertile Soil 230.81 m3
4 Small Gravel 23.05 m3 450,000.00 10,372,500.00
5 Growth Subtrate 18,52 m3

1 Plan Vertical Garden (P1) Uk.1.900x2.400 4.56 m2 450,000.00 2,052,000.00


2 Plan Vertical Garden (P2) Uk.1.900x2.400 4.56 m2 450,000.00 2,052,000.00
3 Plan Vertical Garden (P3) Uk.5.430x2.640 14.34 m2 450,000.00 6,450,840.00
RENCANA ANGGARAN BIAYA

PEKERJAAN :
LOKASI :
TAHUN :

NO URAIAN PEKERJAAN VOLUME SAT

A Plating/Landscaping
1 Tree
2 Tabebuya Kuning 25 tree
3 Kamboja Bali Putih 46
4 Shrubs
5 Hanjuang 21 tree
6 Palm Merah 6 tree
7 Pisang Bedak(Calatea) 335 tree
8 Bushes
9 Cana Presiden 180 tree
10 Palm Wregu 343 tree
11 Tradescantia 45 tree
12 Ground Cover
13 Lily Brazil 189 tree
14 Lamtana 166 tree
15 Bakung 604 tree
16 Rumput Gajah Mini 490 m2
17 Vines
18 Ceguk Wudani 18 tree
19 Lonicera Rambat 18 tree
20 Lee Kuan Yew 34 tree
21 BOX PLANTER (G1) 106 unit
22 BOX PLANTER (G2) 3 unit
23 RAILING TANK & BRC 80 unit

Planting Media
1 Sand 23 m3
2 Gravel 110.4 m3
3 Fertile Soil 230.81 m3
4 Small Gravel 23.05 m3
5 Growth Subtrate 18,52 m3

1 Plan Vertical Garden (P1) Uk.1.900x2.400 4.56 m2


2 Plan Vertical Garden (P2) Uk.1.900x2.401 4.56 m2
3 Plan Vertical Garden (P3) Uk.1.900x2.400 4.56 m2
4 Plan Vertical Garden (P4) Uk.5.430x2.640 14.34 m2

PP
AYA

HARGA SATUAN JUMLAH HARGA


(RP) (RP)

Rp 150,000 3,750,000.00
Rp 500,000 23,000,000.00
-
Rp 15,000 315,000.00
Rp 170,000 1,020,000.00
Rp 25,000 8,375,000.00
-
Rp 25,000 4,500,000.00
Rp 110,000 37,730,000.00
15000 675,000.00
-
Rp 12,000 2,268,000.00
Rp 12,000 1,992,000.00
Rp 18,000 10,872,000.00
Rp 65,000 31,850,000.00
-
Rp 85,000 1,530,000.00
Rp 75,000 1,350,000.00
Rp 20,000 680,000.00
Rp 350,000 37,100,000.00
Rp 320,000 960,000.00
-
-
-
Rp 90,000 2,070,000.00
Rp 400,000 44,160,000.00
-
Rp 450,000 10,372,500.00
#VALUE!
-
Rp 850,000 3,876,000.00 154 17cmx17cm 1m=36
Rp 850,000 3,876,000.00
Rp 850,000 3,876,000.00
Rp 850,000 12,184,920.00 480

Jumlah 248,382,420.00
PPN 11% 27,322,066.20
Total 275,704,486.20
-

18,520.00
3,704.00
ANALISA HARGA SATUAN PEKERJAAN
Koefisien Tenaga Kerja & Koefisien Bahan

A.2.3.1 PEKERJAAN TANAH

A. 2.3.1.10b Pengurugan 1 M3 tanah dipadatkan


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.8300 90,000.00 74,700.00
Mandor OH 0.0600 135,000.00 8,100.00
JUMLAH TENAGA KERJA 82,800.00
B BAHAN
Tanah Urug M3 1.2000 80,000.00 96,000.00
JUMLAH HARGA BAHAN 96,000.00
C PERALATAN
Pemadat timbunan ( Stemper) Hari 0.0500 200,000.00 10,000.00
JUMLAH HARGA ALAT 10,000.00

D Jumlah (A+B+C) 188,800.00


E Overhead & Profit 10% x D 18,880.00
F Harga Satuan Pekerjaan (D+E) 207,680.00

A. 2.3.1.11 Pengurugan 1 M3 dengan pasir urug


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3000 90,000.00 27,000.00
Mandor OH 0.0100 135,000.00 1,350.00
JUMLAH TENAGA KERJA 28,350.00
B BAHAN
Pasir Urug M3 1.2000 130,000.00 156,000.00
JUMLAH HARGA BAHAN 156,000.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 184,350.00


E Overhead & Profit 10% x D 18,435.00
F Harga Satuan Pekerjaan (D+E) 202,785.00

A.4.1.1 PEKERJAAN BETON

A.4.1.1.4 Membuat 1 M3 lantai kerja beton mutu f'c = 7,4 Mpa (K.100), Slump (3-6) cm, w/c=0,87
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.2000 90,000.00 108,000.00
Tukang Batu OH 0.2000 130,000.00 26,000.00
Kepala Tukang OH 0.0200 145,000.00 2,900.00
Mandor OH 0.0600 135,000.00 8,100.00
JUMLAH TENAGA KERJA 145,000.00
B BAHAN
Semen Portlant Kg 230.0000 1,300.00 299,000.00
Pasir Beton Kg 893.0000 92.86 82,921.43
Kerikil (Maks. 30 mm) Kg 1,027.0000 250.00 256,750.00
Air Liter 200.0000 121.00 24,200.00
JUMLAH HARGA BAHAN 662,871.43
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 807,871.43


E Overhead & Profit 10% x D 80,787.14
F Harga Satuan Pekerjaan (D+E) 888,658.57

Page 6 of 60
A.4.1.1.5a Membuat 1 M3 Beton mutu f'c = 14,5 Mpa (K.175), Slump (12 ± 2) cm, w/c=0,66
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.6500 90,000.00 148,500.00
Tukang Batu OH 0.2750 130,000.00 35,750.00
Kepala Tukang OH 0.0280 145,000.00 4,060.00
Mandor OH 0.0830 135,000.00 11,205.00
JUMLAH TENAGA KERJA 199,515.00
B BAHAN
Semen Portlant Kg 326.0000 1,300.00 423,800.00
Pasir Beton Kg 760.0000 92.86 70,571.43
Split Kg 1,029.0000 250.00 257,250.00
Air Liter 215.0000 121.00 26,015.00
JUMLAH HARGA BAHAN 777,636.43
C PERALATAN
Molen 0,35 M3 Hari 0.200 250,000.00 50,000.00
JUMLAH HARGA ALAT 50,000.00

D Jumlah (A+B+C) 1,027,151.43


E Overhead & Profit 10% x D 102,715.14
F Harga Satuan Pekerjaan (D+E) 1,129,866.57

A.4.1.1.6 Membuat 1 M3 Beton mutu f'c = 16,9 Mpa (K 200), Slump (12 ± 2) cm, w/c=0,61
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.6500 90,000.00 148,500.00
Tukang Batu OH 0.2750 130,000.00 35,750.00
Kepala Tukang OH 0.0280 145,000.00 4,060.00
Mandor OH 0.0830 135,000.00 11,205.00
JUMLAH TENAGA KERJA 199,515.00
B BAHAN
Semen Portlant Kg 352.0000 1,300.00 457,600.00
Pasir Beton Kg 731.0000 92.86 67,878.57
Split Kg 1,031.0000 250.00 257,750.00
Air Liter 215.0000 121.00 26,015.00
JUMLAH HARGA BAHAN 809,243.57
C PERALATAN
Molen 0,35 M3 Hari 0.200 250,000.00 50,000.00
JUMLAH HARGA ALAT 50,000.00

D Jumlah (A+B+C) 1,058,758.57


E Overhead & Profit 10% x D 105,875.86
F Harga Satuan Pekerjaan (D+E) 1,164,634.43

A.4.1.1.8 Membuat 1 M3 Beton mutu f'c = 21,7 Mpa (K.250), Slump (12 ± 2) cm, w/c=0,56
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.6500 90,000.00 148,500.00
Tukang Batu OH 0.2750 130,000.00 35,750.00
Kepala Tukang OH 0.0280 145,000.00 4,060.00
Mandor OH 0.0830 135,000.00 11,205.00
JUMLAH TENAGA KERJA 199,515.00
B BAHAN
Semen Portlant Kg 384.0000 1,300.00 499,200.00
Pasir Beton Kg 692.0000 92.86 64,257.14
Split Kg 1,039.0000 250.00 259,750.00
Air Liter 215.0000 121.00 26,015.00
JUMLAH HARGA BAHAN 849,222.14
C PERALATAN
Molen 0,35 M3 Hari 0.200 250,000.00 50,000.00
JUMLAH HARGA ALAT 50,000.00

D Jumlah (A+B+C) 1,098,737.14


E Overhead & Profit 10% x D 109,873.71
F Harga Satuan Pekerjaan (D+E) 1,208,610.86

Page 7 of 60
A.4.1.1.8b Membuat 1 M3 Beton mutu f'c = 21,7 Mpa (K.250), Slump (12 ± 2) cm, w/c=0,56 (Readymix)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.6500 90,000.00 148,500.00
Tukang Batu OH 0.2750 130,000.00 35,750.00
Kepala Tukang OH 0.0280 145,000.00 4,060.00
Mandor OH 0.0830 135,000.00 11,205.00
JUMLAH TENAGA KERJA 199,515.00
B BAHAN
Semen Portlant Kg 384.0000 1,300.00 499,200.00
Pasir Beton Kg 692.0000 92.86 64,257.14
Split Kg 1,039.0000 250.00 259,750.00
Air Liter 215.0000 121.00 26,015.00
JUMLAH HARGA BAHAN 849,222.14
C PERALATAN
Con Pan Mixer (Batching Plan Mini) Jam 0.0926 649,119 60,103.62
Truck Mixer (Agitator) Jam 0.1759 625,396 110,035.05
Water Tank Jam 0.0382 281,591 10,743.43
Alat Bantu (Concrete Pump) Jam 1.0000 278,745 278,744.64
JUMLAH HARGA ALAT 459,626.74

D Jumlah (A+B+C) 1,508,363.88


E Overhead & Profit 10% x D 150,836.39
F Harga Satuan Pekerjaan (D+E) 1,659,200.27

A.4.1.1.10. Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.6500 90,000.00 148,500.00
Tukang Batu OH 0.2750 130,000.00 35,750.00
Kepala Tukang OH 0.0280 145,000.00 4,060.00
Mandor OH 0.0830 135,000.00 11,205.00
JUMLAH TENAGA KERJA 199,515.00
B BAHAN
Semen Portlant Kg 413.0000 1,300.00 536,900.00
Pasir Beton Kg 681.0000 92.86 63,235.71
Split Kg 1,021.0000 250.00 255,250.00
Air Liter 215.0000 121.00 26,015.00
JUMLAH HARGA BAHAN 881,400.71
C PERALATAN
Molen 0,35 M3 Hari 0.200 250,000.00 50,000.00
JUMLAH HARGA ALAT 50,000.00

D Jumlah (A+B+C) 1,130,915.71


E Overhead & Profit 10% x D 113,091.57
F Harga Satuan Pekerjaan (D+E) 1,244,007.29

Page 8 of 60
A.4.1.1.10b Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52 (Readymix)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.6500 90,000.00 148,500.00
Tukang Batu OH 0.2750 130,000.00 35,750.00
Kepala Tukang OH 0.0280 145,000.00 4,060.00
Mandor OH 0.0830 135,000.00 11,205.00
JUMLAH TENAGA KERJA 199,515.00
B BAHAN
Semen Portlant Kg 413.0000 1,300.00 536,900.00
Pasir Beton Kg 681.0000 92.86 63,235.71
Split Kg 1,021.0000 250.00 255,250.00
Air Liter 215.0000 121.00 26,015.00
JUMLAH HARGA BAHAN 881,400.71
C PERALATAN
Con Pan Mixer (Batching Plan Mini) Jam 0.0926 649,119 60,103.62
Truck Mixer (Agitator) Jam 0.1759 625,396 110,035.05
Water Tank Jam 0.0382 281,591 10,743.43
Alat Bantu (Concrete Pump) Jam 1.0000 278,745 278,744.64
JUMLAH HARGA ALAT 459,626.74

D Jumlah (A+B+C) 1,540,542.45


E Overhead & Profit 10% x D 154,054.25
F Harga Satuan Pekerjaan (D+E) 1,694,596.70

A.4.1.1.17 Pembesian 10 Kg dengan Besi Polos atau Besi Ulir


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0700 90,000.00 6,300.00
Tukang Besi OH 0.0700 130,000.00 9,100.00
Kepala Tukang OH 0.0070 145,000.00 1,015.00
Mandor OH 0.0040 135,000.00 540.00
JUMLAH TENAGA KERJA 16,955.00
B BAHAN
Besi Beton Kg 10.5000 14,000.00 147,000.00
Kawat Beton Kg 0.1500 20,000.00 3,000.00
JUMLAH HARGA BAHAN 150,000.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 166,955.00


E Overhead & Profit 10% x D 16,695.50
F Harga Satuan Pekerjaan (D+E) 183,650.50

A.4.1.1.19 Pemasangan 10 Kg kawat baja (Wiremesh)


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0250 90,000.00 2,250.00
Tukang Besi OH 0.0250 130,000.00 3,250.00
Kepala Tukang OH 0.0250 145,000.00 3,625.00
Mandor OH 0.0010 135,000.00 135.00
JUMLAH TENAGA KERJA 9,260.00
B BAHAN
Jaring Kawat Baja (dilas) Kg 10.2000 12,105.52 123,476.29
Kawat Beton Kg 0.0500 20,000.00 1,000.00
JUMLAH HARGA BAHAN 124,476.29
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 133,736.29


E Overhead & Profit 10% x D 13,373.63
F Harga Satuan Pekerjaan (D+E) 147,109.92

Page 9 of 60
A.4.1.1.20 Pemasangan 1 M2 Bekisting untuk pondasi
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.5200 90,000.00 46,800.00
Tukang Kayu OH 0.2600 130,000.00 33,800.00
Kepala Tukang OH 0.0260 145,000.00 3,770.00
Mandor OH 0.0260 135,000.00 3,510.00
JUMLAH TENAGA KERJA 87,880.00
B BAHAN
Kayu Klas III M3 0.0400 2,300,000.00 92,000.00
Paku Biasa 2"-5" Kg 0.3000 15,000.00 4,500.00
Minyak Bekisting Kg 0.1000 8,700.00 870.00
JUMLAH HARGA BAHAN 97,370.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 185,250.00


E Overhead & Profit 10% x D 18,525.00
F Harga Satuan Pekerjaan (D+E) 203,775.00

A.4.1.1.21 Pemasangan 1 M2 Bekisting untuk sloof


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.5200 90,000.00 46,800.00
Tukang Kayu OH 0.2600 130,000.00 33,800.00
Kepala Tukang OH 0.0260 145,000.00 3,770.00
Mandor OH 0.0260 135,000.00 3,510.00
JUMLAH TENAGA KERJA 87,880.00
B BAHAN
Kayu Klas III M3 0.0450 2,300,000.00 103,500.00
Paku Biasa 2"-5" Kg 0.3000 15,000.00 4,500.00
Minyak Bekisting Kg 0.1000 8,700.00 870.00
JUMLAH HARGA BAHAN 108,870.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 196,750.00


E Overhead & Profit 10% x D 19,675.00
F Harga Satuan Pekerjaan (D+E) 216,425.00

A.4.1.1.22 Pemasangan 1 M2 Bekisting untuk kolom


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.6600 90,000.00 59,400.00
Tukang Kayu OH 0.3300 130,000.00 42,900.00
Kepala Tukang OH 0.0330 145,000.00 4,785.00
Mandor OH 0.0330 135,000.00 4,455.00
JUMLAH TENAGA KERJA 111,540.00
B BAHAN
Kayu Klas III M3 0.0400 2,300,000.00 92,000.00
Paku Biasa 2"-5" Kg 0.4000 15,000.00 6,000.00
Minyak Bekisting Kg 0.2000 8,700.00 1,740.00
Balok Kayu Klas II M3 0.0150 3,500,000.00 52,500.00
Plywood Tebal 9 mm Lbr 0.3500 115,000.00 40,250.00
Kayu Dolken Ø 8-10 cm, P=400 cm Batang 2.0000 10,000.00 20,000.00
JUMLAH HARGA BAHAN 212,490.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 324,030.00


E Overhead & Profit 10% x D 32,403.00
F Harga Satuan Pekerjaan (D+E) 356,433.00

Page 10 of 60
A.4.1.1.23 Pemasangan 1 M2 Bekisting untuk balok
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.6600 90,000.00 59,400.00
Tukang Kayu OH 0.3300 130,000.00 42,900.00
Kepala Tukang OH 0.0330 145,000.00 4,785.00
Mandor OH 0.0330 135,000.00 4,455.00
JUMLAH TENAGA KERJA 111,540.00
B BAHAN
Kayu Klas III M3 0.0400 2,300,000.00 92,000.00
Paku Biasa 2"-5" Kg 0.4000 15,000.00 6,000.00
Minyak Bekisting Kg 0.2000 8,700.00 1,740.00
Balok Kayu Klas II M3 0.0180 3,500,000.00 63,000.00
Plywood Tebal 9 mm Lbr 0.3500 115,000.00 40,250.00
Kayu Dolken Ø 8-10 cm, P=400 cm Batang 2.0000 10,000.00 20,000.00
JUMLAH HARGA BAHAN 222,990.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 334,530.00


E Overhead & Profit 10% x D 33,453.00
F Harga Satuan Pekerjaan (D+E) 367,983.00

A.4.1.1.24 Pemasangan 1 M2 Bekisting untuk lantai


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.6600 90,000.00 59,400.00
Tukang Kayu OH 0.3300 130,000.00 42,900.00
Kepala Tukang OH 0.0330 145,000.00 4,785.00
Mandor OH 0.0330 135,000.00 4,455.00
JUMLAH TENAGA KERJA 111,540.00
B BAHAN
Kayu Klas III M3 0.0400 2,300,000.00 92,000.00
Paku Biasa 2"-5" Kg 0.4000 15,000.00 6,000.00
Minyak Bekisting Kg 0.2000 8,700.00 1,740.00
Balok Kayu Klas II M3 0.0150 3,500,000.00 52,500.00
Plywood Tebal 9 mm Lbr 0.3500 115,000.00 40,250.00
Kayu Dolken Ø 8-10 cm, P=400 cm Batang 6.0000 10,000.00 60,000.00
JUMLAH HARGA BAHAN 252,490.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 364,030.00


E Overhead & Profit 10% x D 36,403.00
F Harga Satuan Pekerjaan (D+E) 400,433.00

Page 11 of 60
A.4.1.1.25 Pemasangan 1 M2 Bekisting untuk dinding
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.6600 90,000.00 59,400.00
Tukang Kayu OH 0.3300 130,000.00 42,900.00
Kepala Tukang OH 0.0330 145,000.00 4,785.00
Mandor OH 0.0330 135,000.00 4,455.00
JUMLAH TENAGA KERJA 111,540.00
B BAHAN
Kayu Klas III M3 0.0300 2,300,000.00 69,000.00
Paku Biasa 2"-5" Kg 0.4000 15,000.00 6,000.00
Minyak Bekisting Kg 0.2000 8,700.00 1,740.00
Balok Kayu Klas II M3 0.0200 3,500,000.00 70,000.00
Plywood Tebal 9 mm Lbr 0.3500 115,000.00 40,250.00
Kayu Dolken Ø 8-10 cm, P=400 cm Batang 3.0000 10,000.00 30,000.00
JUMLAH HARGA BAHAN 216,990.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 328,530.00


E Overhead & Profit 10% x D 32,853.00
F Harga Satuan Pekerjaan (D+E) 361,383.00

A.4.1.1.26 Pemasangan 1 M2 Bekisting untuk Tangga


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.6600 90,000.00 59,400.00
Tukang Kayu OH 0.3300 130,000.00 42,900.00
Kepala Tukang OH 0.0330 145,000.00 4,785.00
Mandor OH 0.0330 135,000.00 4,455.00
JUMLAH TENAGA KERJA 111,540.00
B BAHAN
Kayu Klas III M3 0.0300 2,300,000.00 69,000.00
Paku Biasa 2"-5" Kg 0.4000 15,000.00 6,000.00
Minyak Bekisting Kg 0.1500 8,700.00 1,305.00
Balok Kayu Klas II M3 0.0150 3,500,000.00 52,500.00
Plywood Tebal 9 mm Lbr 0.3500 115,000.00 40,250.00
Kayu Dolken Ø 8-10 cm, P=400 cm Batang 2.0000 10,000.00 20,000.00
JUMLAH HARGA BAHAN 189,055.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 300,595.00


E Overhead & Profit 10% x D 30,059.50
F Harga Satuan Pekerjaan (D+E) 330,654.50

Page 12 of 60
A.4.1.1.28 Membuat 1 M3 pondasi beton bertulang (150 kg besi + bekisting)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 5.3000 90,000.00 477,000.00
Tukang Batu OH 0.2750 130,000.00 35,750.00
Tukang Kayu OH 1.3000 130,000.00 169,000.00
Tukang Besi OH 1.0500 130,000.00 136,500.00
Kepala Tukang OH 0.2620 145,000.00 37,990.00
Mandor OH 0.2650 135,000.00 35,775.00
JUMLAH TENAGA KERJA 892,015.00
B BAHAN
Kayu Klas III M3 0.2000 2,300,000.00 460,000.00
Paku Biasa 2"-5" Kg 1.5000 15,000.00 22,500.00
Minyak Bekisting Liter 0.4000 8,700.00 3,480.00
Besi Beton Kg 157.5000 14,000.00 2,205,000.00
Kawat Beton Kg 2.2500 20,000.00 45,000.00
Semen Portlant Kg 336.0000 1,300.00 436,800.00
Pasir Beton M3 0.5400 130,000.00 70,200.00
Kerikil M3 0.8100 450,000.00 364,500.00
JUMLAH HARGA BAHAN 3,607,480.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 4,499,495.00


E Overhead & Profit 10% x D 449,949.50
F Harga Satuan Pekerjaan (D+E) 4,949,444.50

A.4.1.1.29b Membuat 1 M3 sloof beton bertulang (150 kg besi + bekisting)


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 5.6500 90,000.00 508,500.00
Tukang Batu OH 0.2750 130,000.00 35,750.00
Tukang Kayu OH 1.5600 130,000.00 202,800.00
Tukang Besi OH 1.4000 130,000.00 182,000.00
Kepala Tukang OH 0.3230 145,000.00 46,835.00
Mandor OH 0.2830 135,000.00 38,205.00
JUMLAH TENAGA KERJA 1,014,090.00
B BAHAN
Kayu Klas III M3 0.2700 2,300,000.00 621,000.00
Paku Biasa 2"-5" Kg 2.0000 15,000.00 30,000.00
Minyak Bekisting Liter 0.6000 8,700.00 5,220.00
Besi Beton Kg 157.5000 14,000.00 2,205,000.00
Kawat Beton Kg 2.2500 20,000.00 45,000.00
Semen Portlant Kg 336.0000 1,300.00 436,800.00
Pasir Beton M3 0.5400 130,000.00 70,200.00
Kerikil M3 0.8100 450,000.00 364,500.00
JUMLAH HARGA BAHAN 3,777,720.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 4,791,810.00


E Overhead & Profit 10% x D 479,181.00
F Harga Satuan Pekerjaan (D+E) 5,270,991.00

Page 13 of 60
A.4.1.1.31 Membuat 1 M3 balok beton bertulang (200 kg besi + bekisting)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 6.350 90,000.00 571,500.00
Tukang Batu OH 0.275 130,000.00 35,750.00
Tukang Kayu OH 1.650 130,000.00 214,500.00
Tukang Besi OH 1.400 130,000.00 182,000.00
Kepala Tukang OH 0.333 145,000.00 48,285.00
Mandor OH 0.318 135,000.00 42,930.00
JUMLAH TENAGA KERJA 1,094,965.00
B BAHAN
Kayu Klas III M3 0.3200 2,300,000.00 736,000.00
Paku Biasa 2"-5" Kg 3.2000 15,000.00 48,000.00
Minyak Bekisting Liter 1.6000 8,700.00 13,920.00
Besi Beton Kg 210.0000 14,000.00 2,940,000.00
Kawat Beton Kg 3.0000 20,000.00 60,000.00
Semen Portlant Kg 336.0000 1,300.00 436,800.00
Pasir Beton M3 0.5400 130,000.00 70,200.00
Kerikil M3 0.8100 450,000.00 364,500.00
Kayu kelas II balok M3 0.1400 3,500,000.00 490,000.00
Plywood 9 mm Lbr 2.8000 115,000.00 322,000.00
Dolken kayu Btg 16.0000 10,000.00 160,000.00
JUMLAH HARGA BAHAN 5,641,420.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 6,736,385.00


E Overhead & Profit 10% x D 673,638.50
F Harga Satuan Pekerjaan (D+E) 7,410,023.50

A.4.1.1.32 Membuat 1 M3 kolom beton bertulang (150 kg besi + bekisting)


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 5.3000 90,000.00 477,000.00
Tukang Batu OH 0.2750 130,000.00 35,750.00
Tukang Kayu OH 1.3000 130,000.00 169,000.00
Tukang Besi OH 1.0500 130,000.00 136,500.00
Kepala Tukang OH 0.2650 145,000.00 38,425.00
Mandor OH 0.2650 135,000.00 35,775.00
JUMLAH TENAGA KERJA 892,450.00
B BAHAN
Kayu Klas III M3 0.3200 2,300,000.00 736,000.00
Paku Biasa 2"-5" Kg 3.2000 15,000.00 48,000.00
Minyak Bekisting Liter 1.6000 8,700.00 13,920.00
Besi Beton Kg 157.5000 14,000.00 2,205,000.00
Kawat Beton Kg 2.2500 20,000.00 45,000.00
Semen Portlant Kg 336.0000 1,300.00 436,800.00
Pasir Beton M3 0.5400 130,000.00 70,200.00
Kerikil M3 0.8100 450,000.00 364,500.00
Kayu kelas II balok M3 0.1200 3,500,000.00 420,000.00
Plywood 9 mm Lbr 2.8000 115,000.00 322,000.00
Dolken kayu Btg 32.0000 10,000.00 320,000.00
JUMLAH HARGA BAHAN 4,981,420.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 5,873,870.00


E Overhead & Profit 10% x D 587,387.00
F Harga Satuan Pekerjaan (D+E) 6,461,257.00

Page 14 of 60
A.4.1.1.33 Membuat 1 M3 dinding beton bertulang (150 kg besi + bekisting)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 5.3000 90,000.00 477,000.00
Tukang Batu OH 0.2750 130,000.00 35,750.00
Tukang Kayu OH 1.3000 130,000.00 169,000.00
Tukang Besi OH 1.0500 130,000.00 136,500.00
Kepala Tukang OH 0.2620 145,000.00 37,990.00
Mandor OH 0.2650 135,000.00 35,775.00
JUMLAH TENAGA KERJA 892,015.00
B BAHAN
Kayu Klas III M3 0.2400 2,300,000.00 552,000.00
Paku Biasa 2"-5" Kg 3.2000 15,000.00 48,000.00
Minyak Bekisting Liter 1.6000 8,700.00 13,920.00
Besi Beton Kg 157.5000 14,000.00 2,205,000.00
Kawat Beton Kg 2.2500 20,000.00 45,000.00
Semen Portlant Kg 336.0000 1,300.00 436,800.00
Pasir Beton M3 0.5400 130,000.00 70,200.00
Kerikil M3 0.8100 450,000.00 364,500.00
Kayu kelas II balok M3 0.1600 3,500,000.00 560,000.00
Plywood 9 mm Lbr 2.8000 115,000.00 322,000.00
Dolken kayu Btg 24.0000 10,000.00 240,000.00
JUMLAH HARGA BAHAN 4,857,420.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 5,749,435.00


E Overhead & Profit 10% x D 574,943.50
F Harga Satuan Pekerjaan (D+E) 6,324,378.50

A.4.1.1.35 Membuat 1 M' kolom praktis beton bertulang (11 x 11) cm


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1800 90,000.00 16,200.00
Tukang Batu OH 0.0200 130,000.00 2,600.00
Tukang Kayu OH 0.0200 130,000.00 2,600.00
Tukang Besi OH 0.0200 130,000.00 2,600.00
Kepala Tukang OH 0.0060 145,000.00 870.00
Mandor OH 0.0090 135,000.00 1,215.00
JUMLAH TENAGA KERJA 26,085.00
B BAHAN
Kayu Klas III M3 0.0020 2,300,000.00 4,600.00
Paku Biasa 2"-5" Kg 0.0100 15,000.00 150.00
Minyak Bekisting Liter - 8,700.00 0.00
Besi Beton Polos Kg 3.0000 14,000.00 42,000.00
Kawat Beton Kg 0.4500 20,000.00 9,000.00
Semen Portlant Kg 4.0000 1,300.00 5,200.00
Pasir Beton M3 0.0060 130,000.00 780.00
Kerikil M3 0.0090 450,000.00 4,050.00
JUMLAH HARGA BAHAN 65,780.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 91,865.00


E Overhead & Profit 10% x D 9,186.50
F Harga Satuan Pekerjaan (D+E) 101,051.50

Page 15 of 60
A.4.1.1.36 Membuat 1 M' ring balok beton bertulang (10 x 15) cm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.2970 90,000.00 26,730.00
Tukang Batu OH 0.0330 130,000.00 4,290.00
Tukang Kayu OH 0.0330 130,000.00 4,290.00
Tukang Besi OH 0.0330 130,000.00 4,290.00
Kepala Tukang OH 0.0100 145,000.00 1,450.00
Mandor OH 0.0150 135,000.00 2,025.00
JUMLAH TENAGA KERJA 43,075.00
B BAHAN
Kayu Klas III M3 0.0030 2,300,000.00 6,900.00
Paku Biasa 2"-5" Kg 0.0200 15,000.00 300.00
Minyak Bekisting Liter - 8,700.00 0.00
Besi Beton Polos Kg 3.6000 14,000.00 50,400.00
Kawat Beton Kg 0.0500 20,000.00 1,000.00
Semen Portlant Kg 5.5000 1,300.00 7,150.00
Pasir Beton M3 0.0090 130,000.00 1,170.00
Kerikil M3 0.0150 450,000.00 6,750.00
JUMLAH HARGA BAHAN 73,670.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 116,745.00


E Overhead & Profit 10% x D 11,674.50
F Harga Satuan Pekerjaan (D+E) 128,419.50

A.4.2.1. PEKERJAAN BESI DAN ALUMUNIUM

A.4.2.1.21 Pemasangan 1 M2 Rangka Pipa Hollow 4x4 cm, Modul 60x60 cm, Plafond
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.2000 90,000.00 18,000.00
Tukang Besi OH 0.3000 130,000.00 39,000.00
Kepala Tukang OH 0.0300 145,000.00 4,350.00
Mandor OH 0.0100 135,000.00 1,350.00
JUMLAH TENAGA KERJA 62,700.00
B BAHAN
Rangka Metal Hollow 40.40.2mm M2 1.0500 150,000.00 157,500.00
JUMLAH HARGA BAHAN 157,500.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 220,200.00


E Overhead & Profit 10% x D 22,020.00
F Harga Satuan Pekerjaan (D+E) 242,220.00

Page 16 of 60
A.4.4.1. PEKERJAAN PASANGAN DINDING

A.4.4.1.1 Pemasangan 1 M2 Dinding Bata Merah (5x11x22) cm tebal 1 Batu Campuran 1 SP : 2 PP


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.6000 90,000.00 54,000.00
Tukang Batu OH 0.2000 130,000.00 26,000.00
Kepala Tukang OH 0.0200 145,000.00 2,900.00
Mandor OH 0.0300 135,000.00 4,050.00
JUMLAH TENAGA KERJA 86,950.00
B BAHAN
Bata Merah Buah 140.0000 500.00 70,000.00
Semen Portland Kg 43.5000 1,300.00 56,550.00
Pasir Pasang M3 0.0800 130,000.00 10,400.00
JUMLAH HARGA BAHAN 136,950.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 223,900.00


E Overhead & Profit 10% x D 22,390.00
F Harga Satuan Pekerjaan (D+E) 246,290.00

A.4.4.1.2 Pemasangan 1 M2 Dinding bata merah (5x11x22) cm tebal 1 batu Campuran 1 SP : 3 PP


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.6000 90,000.00 54,000.00
Tukang Batu OH 0.2000 130,000.00 26,000.00
Kepala Tukang OH 0.0200 145,000.00 2,900.00
Mandor OH 0.0300 135,000.00 4,050.00
JUMLAH TENAGA KERJA 86,950.00
B BAHAN
Bata Merah Buah 140.0000 500.00 70,000.00
Semen Portland Kg 32.9500 1,300.00 42,835.00
Pasir Pasang M3 0.0910 130,000.00 11,830.00
JUMLAH HARGA BAHAN 124,665.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 211,615.00


E Overhead & Profit 10% x D 21,161.50
F Harga Satuan Pekerjaan (D+E) 232,776.50

A.4.4.1.3 Pemasangan 1 M2 Dinding bata merah (5x11x22) cm tebal 1 batu Campuran 1 SP : 4 PP


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.6000 90,000.00 54,000.00
Tukang Batu OH 0.2000 130,000.00 26,000.00
Kepala Tukang OH 0.0200 145,000.00 2,900.00
Mandor OH 0.0300 135,000.00 4,050.00
JUMLAH TENAGA KERJA 86,950.00
B BAHAN
Bata Merah Buah 140.0000 500.00 70,000.00
Semen Portland Kg 26.5500 1,300.00 34,515.00
Pasir Pasang M3 0.0930 130,000.00 12,090.00
JUMLAH HARGA BAHAN 116,605.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 203,555.00


E Overhead & Profit 10% x D 20,355.50
F Harga Satuan Pekerjaan (D+E) 223,910.50

Page 17 of 60
A.4.4.1.7 Pemasangan 1 M2 Dinding bata merah (5x11x22) cm tebal 1/2 batu Campuran 1 SP : 2 PP
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3000 90,000.00 27,000.00
Tukang Batu OH 0.1000 130,000.00 13,000.00
Kepala Tukang OH 0.0100 145,000.00 1,450.00
Mandor OH 0.0150 135,000.00 2,025.00
JUMLAH TENAGA KERJA 43,475.00
B BAHAN
Bata Merah Buah 70.0000 500.00 35,000.00
Semen Portland Kg 18.9500 1,300.00 24,635.00
Pasir Pasang M3 0.0380 130,000.00 4,940.00
JUMLAH HARGA BAHAN 64,575.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 108,050.00


E Overhead & Profit 10% x D 10,805.00
F Harga Satuan Pekerjaan (D+E) 118,855.00

A.4.4.1.8 Pemasangan 1 M2 Dinding bata merah (5x11x22) cm tebal 1/2 batu Campuran 1 SP : 3 PP
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3000 90,000.00 27,000.00
Tukang Batu OH 0.1000 130,000.00 13,000.00
Kepala Tukang OH 0.0100 145,000.00 1,450.00
Mandor OH 0.0150 135,000.00 2,025.00
JUMLAH TENAGA KERJA 43,475.00
B BAHAN
Bata Merah Buah 70.0000 500.00 35,000.00
Semen Portland Kg 14.3700 1,300.00 18,681.00
Pasir Pasang M3 0.0400 130,000.00 5,200.00
JUMLAH HARGA BAHAN 58,881.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 102,356.00


E Overhead & Profit 10% x D 10,235.60
F Harga Satuan Pekerjaan (D+E) 112,591.60

A.4.4.1.9 Pemasangan 1 M2 Dinding bata merah (5x11x22) cm tebal 1/2 batu Campuran 1 SP : 4 PP
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3000 90,000.00 27,000.00
Tukang Batu OH 0.1000 130,000.00 13,000.00
Kepala Tukang OH 0.0100 145,000.00 1,450.00
Mandor OH 0.0150 135,000.00 2,025.00
JUMLAH TENAGA KERJA 43,475.00
B BAHAN
Bata Merah Buah 70.0000 500.00 35,000.00
Semen Portland Kg 11.5000 1,300.00 14,950.00
Pasir Pasang M3 0.0430 130,000.00 5,590.00
JUMLAH HARGA BAHAN 55,540.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 99,015.00


E Overhead & Profit 10% x D 9,901.50
F Harga Satuan Pekerjaan (D+E) 108,916.50

Page 18 of 60
A.4.4.2 PEKERJAAN PLESTERAN

A.4.4.2.2 Pemasangan 1 M2 Plesteran dinding 1 SP : 2 PP tebal 15 mm


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3000 90,000.00 27,000.00
Tukang Batu OH 0.1500 130,000.00 19,500.00
Kepala Tukang OH 0.0150 145,000.00 2,175.00
Mandor OH 0.0150 135,000.00 2,025.00
JUMLAH TENAGA KERJA 50,700.00
B BAHAN
Semen Portland Kg 10.2240 1,300.00 13,291.20
Pasir Pasang M3 0.0200 130,000.00 2,600.00
JUMLAH HARGA BAHAN 15,891.20
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 66,591.20


E Overhead & Profit 10% x D 6,659.12
F Harga Satuan Pekerjaan (D+E) 73,250.32

A.4.4.2.3 Pemasangan 1 M2 Plesteran dinding 1 SP : 3 PP tebal 15 mm


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3000 90,000.00 27,000.00
Tukang Batu OH 0.1500 130,000.00 19,500.00
Kepala Tukang OH 0.0150 145,000.00 2,175.00
Mandor OH 0.0150 135,000.00 2,025.00
JUMLAH TENAGA KERJA 50,700.00
B BAHAN
Semen Portland Kg 7.7760 1,300.00 10,108.80
Pasir Pasang M3 0.0230 130,000.00 2,990.00
JUMLAH HARGA BAHAN 13,098.80
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 63,798.80


E Overhead & Profit 10% x D 6,379.88
F Harga Satuan Pekerjaan (D+E) 70,178.68

A.4.4.2.4 Pemasangan 1 M2 Plesteran dinding 1 SP : 4 PP tebal 15 mm


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3000 90,000.00 27,000.00
Tukang Batu OH 0.1500 130,000.00 19,500.00
Kepala Tukang OH 0.0150 145,000.00 2,175.00
Mandor OH 0.0150 135,000.00 2,025.00
JUMLAH TENAGA KERJA 50,700.00
B BAHAN
Semen Portland Kg 6.2400 1,300.00 8,112.00
Pasir Pasang M3 0.0240 130,000.00 3,120.00
JUMLAH HARGA BAHAN 11,232.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 61,932.00


E Overhead & Profit 10% x D 6,193.20
F Harga Satuan Pekerjaan (D+E) 68,125.20

Page 19 of 60
A.4.4.2.27 Pemasangan 1 M2 Acian
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.2000 90,000.00 18,000.00
Tukang Batu OH 0.1000 130,000.00 13,000.00
Kepala Tukang OH 0.0100 145,000.00 1,450.00
Mandor OH 0.0100 135,000.00 1,350.00
JUMLAH TENAGA KERJA 33,800.00
B BAHAN
Semen Portland Kg 3.2500 1,300.00 4,225.00
JUMLAH HARGA BAHAN 4,225.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 38,025.00


E Overhead & Profit 10% x D 3,802.50
F Harga Satuan Pekerjaan (D+E) 41,827.50

A.4.4.3 PEKERJAAN PENUTUP LANTAI DAN DINDING

A.4.4.3.9b Pemasangan 1 M2 Ubin granit ukuran 60x60 cm


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.7000 90,000.00 63,000.00
Tukang Batu OH 0.3500 130,000.00 45,500.00
Kepala Tukang OH 0.0350 145,000.00 5,075.00
Mandor OH 0.0350 135,000.00 4,725.00
JUMLAH TENAGA KERJA 118,300.00
B BAHAN
Granit 60x60 cm Bh 3.1000 60,000.00 186,000.00
Semen Portland Kg 9.8000 1,300.00 12,740.00
Pasir Pasang M3 0.0450 130,000.00 5,850.00
Semen Warna Kg 1.3000 17,000.00 22,100.00
JUMLAH HARGA BAHAN 226,690.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 344,990.00


E Overhead & Profit 15% x D 34,499.00
F Harga Satuan Pekerjaan (D+E) 379,489.00

A.4.4.3.9b Pemasangan 1 M2 Ubin Keramik ukuran 50x50 cm


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.7000 90,000.00 63,000.00
Tukang Batu OH 0.3500 130,000.00 45,500.00
Kepala Tukang OH 0.0350 145,000.00 5,075.00
Mandor OH 0.0350 135,000.00 4,725.00
JUMLAH TENAGA KERJA 118,300.00
B BAHAN
Keramik 50x50 Bh 4.0000 60,000.00 240,000.00
Semen Portland Kg 9.8000 1,300.00 12,740.00
Pasir Pasang M3 0.0450 130,000.00 5,850.00
Semen Warna Kg 1.3000 17,000.00 22,100.00
JUMLAH HARGA BAHAN 280,690.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 398,990.00


E Overhead & Profit 10% x D 39,899.00
F Harga Satuan Pekerjaan (D+E) 438,889.00

A.4.4.3.35 Pemasangan 1 M2 Lantai keramik ukuran 30x30 cm


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.7000 90,000.00 63,000.00
Tukang Batu OH 0.3500 130,000.00 45,500.00
Page 20 of 60
Kepala Tukang OH 0.0350 145,000.00 5,075.00
Mandor OH 0.0350 135,000.00 4,725.00
JUMLAH TENAGA KERJA 118,300.00
B BAHAN
Keramik 30x30 Bh 11.8700 3,681.82 43,703.18
Semen Portland Kg 10.0000 1,300.00 13,000.00
Pasir Pasang M3 0.0450 130,000.00 5,850.00
Semen Warna Kg 1.5000 17,000.00 25,500.00
JUMLAH HARGA BAHAN 88,053.18
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 206,353.18


E Overhead & Profit 10% x D 20,635.32
F Harga Satuan Pekerjaan (D+E) 226,988.50

Page 21 of 60
A.4.4.3.36a Pemasangan 1 M2 Lantai keramik ukuran 25x25 cm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.7000 90,000.00 63,000.00
Tukang Batu OH 0.3500 130,000.00 45,500.00
Kepala Tukang OH 0.0350 145,000.00 5,075.00
Mandor OH 0.0350 135,000.00 4,725.00
JUMLAH TENAGA KERJA 118,300.00
B BAHAN
Keramik 25x25 Bh 16.0000 4,250.00 68,000.00
Semen Portland Kg 10.4000 1,300.00 13,520.00
Pasir Pasang M3 0.0450 130,000.00 5,850.00
Semen Warna Kg 1.5000 17,000.00 25,500.00
JUMLAH HARGA BAHAN 112,870.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 231,170.00


E Overhead & Profit 10% x D 23,117.00
F Harga Satuan Pekerjaan (D+E) 254,287.00

A.4.4.3.36b Pemasangan 1 M2 Lantai keramik ukuran 40x40 cm


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.2500 90,000.00 22,500.00
Tukang Batu OH 0.1250 130,000.00 16,250.00
Kepala Tukang OH 0.0130 145,000.00 1,885.00
Mandor OH 0.0130 135,000.00 1,755.00
JUMLAH TENAGA KERJA 42,390.00
B BAHAN
Keramik 40x40 Bh 6.6300 15,000.00 99,450.00
Semen Portland Kg 9.8000 1,300.00 12,740.00
Pasir Pasang M3 0.0450 130,000.00 5,850.00
Semen Warna Kg 0.5000 17,000.00 8,500.00
JUMLAH HARGA BAHAN 126,540.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 168,930.00


E Overhead & Profit 10% x D 16,893.00
F Harga Satuan Pekerjaan (D+E) 185,823.00

A.4.4.3.39.2 Pemasangan 1 M' Plint keramik ukuran 10x40 cm


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0900 90,000.00 8,100.00
Tukang Batu OH 0.0900 130,000.00 11,700.00
Kepala Tukang OH 0.0090 145,000.00 1,305.00
Mandor OH 0.0050 135,000.00 675.00
JUMLAH TENAGA KERJA 21,780.00
B BAHAN
Plint Keramik 10x40 cm Bh 2.6500 2,925.00 7,751.25
Semen Portland Kg 1.1400 1,300.00 1,482.00
Pasir Pasang M3 0.0030 130,000.00 390.00
Semen Warna Kg 0.0250 17,000.00 425.00
JUMLAH HARGA BAHAN 10,048.25
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 31,828.25


E Overhead & Profit 10% x D 3,182.83
F Harga Satuan Pekerjaan (D+E) 35,011.08

Page 22 of 60
A.4.4.3.39.2b Pemasangan 1 M' Plint granit ukuran 10x60 cm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0900 90,000.00 8,100.00
Tukang Batu OH 0.0900 130,000.00 11,700.00
Kepala Tukang OH 0.0090 145,000.00 1,305.00
Mandor OH 0.0050 135,000.00 675.00
JUMLAH TENAGA KERJA 21,780.00
B BAHAN
Plint Granit 10x60 cm Bh 1.7500 10,000.00 17,500.00
Semen Portland Kg 1.1400 1,300.00 1,482.00
Pasir Pasang M3 0.0030 130,000.00 390.00
Semen Warna Kg 0.0250 17,000.00 425.00
JUMLAH HARGA BAHAN 19,797.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 41,577.00


E Overhead & Profit 10% x D 4,157.70
F Harga Satuan Pekerjaan (D+E) 45,734.70

A.4.4.3.54a Pemasangan 1 M2 Dinding keramik ukuran 25x40 cm


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.9000 90,000.00 81,000.00
Tukang Batu OH 0.4500 130,000.00 58,500.00
Kepala Tukang OH 0.0450 145,000.00 6,525.00
Mandor OH 0.0450 135,000.00 6,075.00
JUMLAH TENAGA KERJA 152,100.00
B BAHAN
Keramik 25x40 cm Bh 10.0000 6,500.00 65,000.00
Semen Portland Kg 9.3000 1,300.00 12,090.00
Pasir Pasang M3 0.0180 130,000.00 2,340.00
Semen Warna Kg 1.9400 17,000.00 32,980.00
JUMLAH HARGA BAHAN 112,410.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 264,510.00


E Overhead & Profit 10% x D 26,451.00
F Harga Satuan Pekerjaan (D+E) 290,961.00

A.4.4.3.54b Pemasangan 1 M2 Dinding granit ukuran 30x60 cm


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.9000 90,000.00 81,000.00
Tukang Batu OH 0.4500 130,000.00 58,500.00
Kepala Tukang OH 0.0450 145,000.00 6,525.00
Mandor OH 0.0450 135,000.00 6,075.00
JUMLAH TENAGA KERJA 152,100.00
B BAHAN
Granit 30x60 Bh 5.5500 60,000.00 333,000.00
Semen Portland Kg 9.3000 1,300.00 12,090.00
Pasir Pasang M3 0.0180 130,000.00 2,340.00
Semen Warna Kg 1.9400 17,000.00 32,980.00
JUMLAH HARGA BAHAN 380,410.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 532,510.00


E Overhead & Profit 10% x D 53,251.00
F Harga Satuan Pekerjaan (D+E) 585,761.00

Page 23 of 60
A.4.4.3.61 Pemasangan 1 M2 Floor hardener
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1200 90,000.00 10,800.00
Tukang Batu OH 0.1200 130,000.00 15,600.00
Kepala Tukang OH 0.0120 145,000.00 1,740.00
Mandor OH 0.0060 135,000.00 810.00
JUMLAH TENAGA KERJA 28,950.00
B BAHAN
Floor Hardener Kg 5.0000 45,000.00 225,000.00
JUMLAH HARGA BAHAN 225,000.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 253,950.00


E Overhead & Profit 10% x D 25,395.00
F Harga Satuan Pekerjaan (D+E) 279,345.00

A.4.4.3.7 Pemasangan 1 M2 lantai kayu/Parquet


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.8000 90,000.00 72,000.00
Tukang Batu OH 0.4000 130,000.00 52,000.00
Kepala Tukang OH 0.0400 145,000.00 5,800.00
Mandor OH 0.0400 135,000.00 5,400.00
JUMLAH TENAGA KERJA 135,200.00
B BAHAN
Bahan Parquet M2 1.0500 514,000.00 539,700.00
Lem Kg 0.6000 20,000.00 12,000.00
JUMLAH HARGA BAHAN 551,700.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 686,900.00


E Overhead & Profit 10% x D 68,690.00
F Harga Satuan Pekerjaan (D+E) 755,590.00

A.4.4.3.7 Pemasangan 1 M2 lantai Vynil


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1500 90,000.00 13,500.00
Tukang Batu OH 0.1500 130,000.00 19,500.00
Kepala Tukang OH 0.0150 145,000.00 2,175.00
Mandor OH 0.0080 135,000.00 1,080.00
JUMLAH TENAGA KERJA 36,255.00
B BAHAN
Bahan Parquet Bh 11.8700 28,000.00 332,360.00
Lem Kg 0.3500 65,000.00 22,750.00
JUMLAH HARGA BAHAN 355,110.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 391,365.00


E Overhead & Profit 10% x D 39,136.50
F Harga Satuan Pekerjaan (D+E) 430,501.50

A.4.4.3.7 Pemasangan 1 M2 Wallpaper


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3500 90,000.00 31,500.00
Tukang Batu OH 0.1750 130,000.00 22,750.00
Kepala Tukang OH 0.0170 145,000.00 2,465.00
Mandor OH 0.0020 135,000.00 270.00
JUMLAH TENAGA KERJA 56,985.00
B BAHAN
Wallpaper m 2.2000 40,000.00 88,000.00
Lem Wallpaper Kg 0.2500 75,000.00 18,750.00

Page 24 of 60
JUMLAH HARGA BAHAN 106,750.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 163,735.00


E Overhead & Profit 10% x D 16,373.50
F Harga Satuan Pekerjaan (D+E) 180,108.50

A.4.5.1 PEKERJAAN LANGIT-LANGIT (PLAFOND)

A.4.5.1.7 Pemasangan 1 M2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1000 90,000.00 9,000.00
Tukang Kayu OH 0.0500 130,000.00 6,500.00
Kepala Tukang OH 0.0050 145,000.00 725.00
Mandor OH 0.0050 135,000.00 675.00
JUMLAH TENAGA KERJA 16,900.00
B BAHAN
Gypsum Board Lbr 0.3640 75,000.00 27,300.00
Paku Skrup Kg 0.1100 55,000.00 6,050.00
JUMLAH HARGA BAHAN 33,350.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 50,250.00


E Overhead & Profit 10% x D 5,025.00
F Harga Satuan Pekerjaan (D+E) 55,275.00

Page 25 of 60
A.4.5.1.7b Pemasangan 1 M2 langit-langit GRC board ukuran (120x240) mm, tebal 4 mm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1000 90,000.00 9,000.00
Tukang Kayu OH 0.0500 130,000.00 6,500.00
Kepala Tukang OH 0.0050 145,000.00 725.00
Mandor OH 0.0050 135,000.00 675.00
JUMLAH TENAGA KERJA 16,900.00
B BAHAN
GRC Board 4 mm Lbr 0.3640 77,000.00 28,028.00
Paku Skrup Kg 0.1100 55,000.00 6,050.00
JUMLAH HARGA BAHAN 34,078.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 50,978.00


E Overhead & Profit 10% x D 5,097.80
F Harga Satuan Pekerjaan (D+E) 56,075.80

A.4.5.1.B Pemasangan 1 M' List langit-langit gypsum profil


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0600 90,000.00 5,400.00
Tukang Kayu OH 0.0600 130,000.00 7,800.00
Kepala Tukang OH 0.0060 145,000.00 870.00
Mandor OH 0.0030 135,000.00 405.00
JUMLAH TENAGA KERJA 14,475.00
B BAHAN
List Gypsum L. 10 Cm M' 1.0500 17,000.00 17,850.00
Tepung Gypsum Kg 0.1500 5,600.00 840.00
JUMLAH HARGA BAHAN 18,690.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 33,165.00


E Overhead & Profit 10% x D 3,316.50
F Harga Satuan Pekerjaan (D+E) 36,481.50

A.4.6.1 PEKERJAAN KAYU

A.4.6.1.2 Pembuatan dan pemasangan 1 M3 kusen pintu dan kusen jendela kayu klas I
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 7.0000 90,000.00 630,000.00
Tukang Kayu OH 21.0000 130,000.00 2,730,000.00
Kepala Tukang OH 2.1000 145,000.00 304,500.00
Mandor OH 0.3500 135,000.00 47,250.00
JUMLAH TENAGA KERJA 3,711,750.00
B BAHAN
Balok Kayu M3 1.1000 5,000,000.00 5,500,000.00
Paku 10 cm Kg 1.2500 15,000.00 18,750.00
Lem Kayu Kg 1.0000 20,000.00 20,000.00
JUMLAH HARGA BAHAN 5,538,750.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 9,250,500.00


E Overhead & Profit 10% x D 925,050.00
F Harga Satuan Pekerjaan (D+E) 10,175,550.00

Page 26 of 60
A.4.6.1.5 Pembuatan dan pemasangan 1 M2 daun pintu panel kayu klas I
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.8000 90,000.00 72,000.00
Tukang Kayu OH 2.4000 130,000.00 312,000.00
Kepala Tukang OH 0.2400 145,000.00 34,800.00
Mandor OH 0.0400 135,000.00 5,400.00
JUMLAH TENAGA KERJA 424,200.00
B BAHAN
Papan Kayu kelas II M3 0.0240 5,000,000.00 120,000.00
Lem Kayu Kg 0.3000 20,000.00 6,000.00
JUMLAH HARGA BAHAN 126,000.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 550,200.00


E Overhead & Profit 10% x D 55,020.00
F Harga Satuan Pekerjaan (D+E) 605,220.00

A.4.6.2 PEKERJAAN KUNCI DAN KACA

A.4.6.2.2 pemasangan 1 buah kunci tanam biasa


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH - 90,000.00 0.00
Tukang Kayu OH 0.5000 130,000.00 65,000.00
Kepala Tukang OH 0.0500 145,000.00 7,250.00
Mandor OH - 135,000.00 0.00
JUMLAH TENAGA KERJA 72,250.00
B BAHAN
Kunci Tanam Biasa Bh 1.0000 175,000.00 175,000.00
JUMLAH HARGA BAHAN 175,000.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 247,250.00


E Overhead & Profit 10% x D 24,725.00
F Harga Satuan Pekerjaan (D+E) 271,975.00

A.4.6.2.5 pemasangan 1 buah Engsel pintu


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH - 90,000.00 0.00
Tukang Kayu OH 0.1250 130,000.00 16,250.00
Kepala Tukang OH 0.0130 145,000.00 1,885.00
Mandor OH - 135,000.00 0.00
JUMLAH TENAGA KERJA 18,135.00
B BAHAN
Engsel Pintu Bh 1.0000 35,500.00 35,500.00
JUMLAH HARGA BAHAN 35,500.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 53,635.00


E Overhead & Profit 10% x D 5,363.50
F Harga Satuan Pekerjaan (D+E) 58,998.50

Page 27 of 60
A.4.6.2.5b pemasangan 1 buah Grendel pintu
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH - 90,000.00 0.00
Tukang Kayu OH 0.2500 130,000.00 32,500.00
Kepala Tukang OH 0.0250 145,000.00 3,625.00
Mandor OH - 135,000.00 0.00
JUMLAH TENAGA KERJA 36,125.00
B BAHAN
Grendel Pintu Bh 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 25,000.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 61,125.00


E Overhead & Profit 10% x D 6,112.50
F Harga Satuan Pekerjaan (D+E) 67,237.50

A.4.6.2.12b pemasangan 1 buah Pegangan Pintu


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0150 90,000.00 1,350.00
Tukang Kayu OH 0.1500 130,000.00 19,500.00
Kepala Tukang OH 0.0150 145,000.00 2,175.00
Mandor OH 0.0008 135,000.00 108.00
JUMLAH TENAGA KERJA 23,133.00
B BAHAN
Handel Pintu Aluminium Bh 1.0000 45,000.00 45,000.00
JUMLAH HARGA BAHAN 45,000.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 68,133.00


E Overhead & Profit 10% x D 6,813.30
F Harga Satuan Pekerjaan (D+E) 74,946.30

A.4.6.2.18 Pemasangan 1 M2 kaca Polos tebal 5 mm


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1600 90,000.00 14,400.00
Tukang Kayu OH 0.1600 130,000.00 20,800.00
Kepala Tukang OH 0.0160 145,000.00 2,320.00
Mandor OH 0.0080 135,000.00 1,080.00
JUMLAH TENAGA KERJA 38,600.00
B BAHAN
Kaca tbl 5 mm M2 1.1000 95,000.00 104,500.00
Sealant Kg 0.0700 25,800.00 1,806.00

JUMLAH HARGA BAHAN 106,306.00


C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 144,906.00


E Overhead & Profit 10% x D 14,490.60
F Harga Satuan Pekerjaan (D+E) 159,396.60

Page 28 of 60
A.4.6.2.19 Pemasangan 1 M2 kaca tebal 12 mm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0250 90,000.00 2,250.00
Tukang Kayu OH 0.2500 130,000.00 32,500.00
Kepala Tukang OH 0.0250 145,000.00 3,625.00
Mandor OH 0.0013 135,000.00 175.50
JUMLAH TENAGA KERJA 38,550.50
B BAHAN
Kaca polos 12 mm M2 1.1000 550,000.00 605,000.00
Sealant Kg 0.0700 25,800.00 1,806.00

JUMLAH HARGA BAHAN 606,806.00


C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 645,356.50


E Overhead & Profit 10% x D 64,535.65
F Harga Satuan Pekerjaan (D+E) 709,892.15

A.4.7.1 PEKERJAAN PENGECATAN

A.4.7.1.4 Pengecatan 1 M2 bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0700 90,000.00 6,300.00
Tukang Cat OH 0.0900 130,000.00 11,700.00
Kepala Tukang OH 0.0600 145,000.00 8,700.00
Mandor OH 0.0250 135,000.00 3,375.00
JUMLAH TENAGA KERJA 30,075.00
B BAHAN
Cat Menie Kg 0.2000 25,000.00 5,000.00
Plamuur Kg 0.1500 45,000.00 6,750.00
Cat Dasar Kg 0.1700 62,000.00 10,540.00
Cat Penutup Kg 0.2600 62,000.00 16,120.00
Kuas Bh 0.0100 25,000.00 250.00
Pengencer Kg 0.0300 13,300.00 399.00
Amplas Lbr 0.2000 6,000.00 1,200.00
JUMLAH HARGA BAHAN 40,259.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 70,334.00


E Overhead & Profit 10% x D 7,033.40
F Harga Satuan Pekerjaan (D+E) 77,367.40

Page 29 of 60
A.4.7.1.10 Pengecatan 1 M2 Tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0200 90,000.00 1,800.00
Tukang Cat OH 0.0630 130,000.00 8,190.00
Kepala Tukang OH 0.0060 145,000.00 870.00
Mandor OH 0.0030 135,000.00 405.00
JUMLAH TENAGA KERJA 11,265.00
B BAHAN
Plamuur Kg 0.1000 20,000.00 2,000.00
Cat Dasar Kg 0.1000 25,000.00 2,500.00
Cat Penutup Kg 0.2600 25,000.00 6,500.00
Amplas Lbr 0.5000 0.00
JUMLAH HARGA BAHAN 11,000.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 22,265.00


E Overhead & Profit 10% x D 2,226.50
F Harga Satuan Pekerjaan (D+E) 24,491.50

A.4.7.1.16. Pengecatan 1 m2 permukaan baja dengan menie besi


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0200 90,000.00 1,800.00
Tukang Cat OH 0.2000 130,000.00 26,000.00
Kepala Tukang OH 0.0200 145,000.00 2,900.00
Mandor OH 0.0025 135,000.00 337.50
JUMLAH TENAGA KERJA 31,037.50
B BAHAN
Menie besi Kg 0.1000 25,000.00 2,500.00
Kuas Bh 0.0100 25,000.00 250.00
JUMLAH HARGA BAHAN 2,750.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 33,787.50


E Overhead & Profit 10% x D 3,378.75
F Harga Satuan Pekerjaan (D+E) 37,166.25

A.4.7.1.16. Pengecatan 1 m2 permukaan lantai kayu/parquet


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0300 90,000.00 2,700.00
Tukang Cat OH 0.2000 130,000.00 26,000.00
Kepala Tukang OH 0.0200 145,000.00 2,900.00
Mandor OH 0.0025 135,000.00 337.50
JUMLAH TENAGA KERJA 31,937.50
B BAHAN
Ultran Parquet Lack UPL-77E set 0.2000 273,000.00 54,600.00
Kuas Bh 0.0100 25,000.00 250.00
JUMLAH HARGA BAHAN 54,850.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 86,787.50


E Overhead & Profit 10% x D 8,678.75
F Harga Satuan Pekerjaan (D+E) 95,466.25

Page 30 of 60
A.5.1.1 PEKERJAAN SANITASI DALAM GEDUNG

A.5.1.1.1 Pemasangan 1 buah closet duduk/monoblock


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 3.3000 90,000.00 297,000.00
Tukang Batu OH 1.1000 130,000.00 143,000.00
Kepala Tukang OH 0.1100 145,000.00 15,950.00
Mandor OH 0.0160 135,000.00 2,160.00
JUMLAH TENAGA KERJA 458,110.00
B BAHAN
Kloset Duduk Unit 1.0000 2,500,000.00 2,500,000.00
JUMLAH HARGA BAHAN 2,500,000.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 2,958,110.00


E Overhead & Profit 10% x D 295,811.00
F Harga Satuan Pekerjaan (D+E) 3,253,921.00

A.5.1.1.4 Pemasangan 1 buah urinoir


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.0000 90,000.00 90,000.00
Tukang Batu OH 1.0000 130,000.00 130,000.00
Kepala Tukang OH 0.1000 145,000.00 14,500.00
Mandor OH 0.0500 135,000.00 6,750.00
JUMLAH TENAGA KERJA 241,250.00
B BAHAN
Urinoir Unit 1.0000 750,000.00 750,000.00
Semen Portlant Kg 6.0000 1,300.00 1,300.00
Pasir Pasang M3 0.0100 130,000.00 130,000.00
JUMLAH HARGA BAHAN 881,300.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 1,122,550.00


E Overhead & Profit 10% x D 112,255.00
F Harga Satuan Pekerjaan (D+E) 1,234,805.00

A.5.1.1.5 Pemasangan 1 buah wastafel Dinding


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.2000 90,000.00 108,000.00
Tukang Batu OH 1.4500 130,000.00 188,500.00
Kepala Tukang OH 0.1500 145,000.00 21,750.00
Mandor OH 0.0600 135,000.00 8,100.00
JUMLAH TENAGA KERJA 326,350.00
B BAHAN
Wastafel Unit 1.2000 823,800.00 988,560.00
Semen Portlant Kg 6.0000 1,300.00 1,300.00
Pasir Pasang M3 0.0100 130,000.00 130,000.00
JUMLAH HARGA BAHAN 1,119,860.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 1,446,210.00


E Overhead & Profit 10% x D 144,621.00
F Harga Satuan Pekerjaan (D+E) 1,590,831.00

Page 31 of 60
A.5.1.1.5 Pemasangan 1 buah wastafel Meja
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.2000 90,000.00 108,000.00
Tukang Batu OH 1.4500 130,000.00 188,500.00
Kepala Tukang OH 0.1500 145,000.00 21,750.00
Mandor OH 0.0600 135,000.00 8,100.00
JUMLAH TENAGA KERJA 326,350.00
B BAHAN
Wastafel Unit 1.2000 1,500,000.00 1,800,000.00
Semen Portlant Kg 6.0000 1,300.00 1,300.00
Pasir Pasang M3 0.0100 130,000.00 130,000.00
JUMLAH HARGA BAHAN 1,931,300.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 2,257,650.00


E Overhead & Profit 10% x D 225,765.00
F Harga Satuan Pekerjaan (D+E) 2,483,415.00

A.5.1.1.14 Pemasangan 1 buah floor drain


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0100 90,000.00 900.00
Tukang Batu OH 0.1000 130,000.00 13,000.00
Kepala Tukang OH 0.0100 145,000.00 1,450.00
Mandor OH 0.0050 135,000.00 675.00
JUMLAH TENAGA KERJA 16,025.00
B BAHAN
Floor Drain Unit 1.0000 100,000.00 100,000.00
JUMLAH HARGA BAHAN 100,000.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 116,025.00


E Overhead & Profit 10% x D 11,602.50
F Harga Satuan Pekerjaan (D+E) 127,627.50

Pemasangan 1 buah Closed Duduk


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH - 90,000.00 0.00
Tukang Batu OH 1.1000 130,000.00 143,000.00
Kepala Tukang OH 0.1100 145,000.00 15,950.00
Mandor OH 0.0160 135,000.00 2,160.00
JUMLAH TENAGA KERJA 161,110.00
B BAHAN
Kloset jongkok porselen Bh 1.0000 2,500,000.00 2,500,000.00
Semen zak 0.1200 65,000.00 7,800.00
Pasir pasang M3 - 130,000.00 0.00
JUMLAH HARGA BAHAN 2,507,800.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 2,668,910.00


E Overhead & Profit 10% x D 266,891.00
F Harga Satuan Pekerjaan (D+E) 2,935,801.00

Page 32 of 60
Pemasangan 1 buah Kran Air 1/2''
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0100 90,000.00 900.00
Tukang Batu OH 0.1000 130,000.00 13,000.00
Kepala Tukang OH 0.0100 145,000.00 1,450.00
Mandor OH 0.0050 135,000.00 675.00
JUMLAH TENAGA KERJA 16,025.00
B BAHAN
kran air Bh 1.0000 21,000.00 21,000.00
seal tape Bh 0.0250 4,400.00 110.00
JUMLAH HARGA BAHAN 21,110.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 37,135.00


E Overhead & Profit 10% x D 3,713.50
F Harga Satuan Pekerjaan (D+E) 40,848.50

MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 3/4''


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0360 90,000.00 3,240.00
Tukang Batu OH 0.0600 130,000.00 7,800.00
Kepala Tukang OH 0.0060 145,000.00 870.00
Mandor OH 0.0020 135,000.00 270.00
JUMLAH TENAGA KERJA 12,180.00
B BAHAN
Pipa pvc m' 1.2000 5,600.00 6,720.00
Perlengkapan Ls 0.3500 5,600.00 1,960.00
JUMLAH HARGA BAHAN 8,680.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 20,860.00


E Overhead & Profit 10% x D 2,086.00
F Harga Satuan Pekerjaan (D+E) 22,946.00

MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 3''


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0810 90,000.00 7,290.00
Tukang Batu OH 0.1350 130,000.00 17,550.00
Kepala Tukang OH 0.0135 145,000.00 1,957.50
Mandor OH 0.0040 135,000.00 540.00
JUMLAH TENAGA KERJA 27,337.50
B BAHAN
Pipa pvc m' 1.2000 38,750.00 46,500.00
Perlengkapan Ls 0.3500 38,750.00 13,562.50
JUMLAH HARGA BAHAN 60,062.50
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 87,400.00


E Overhead & Profit 10% x D 8,740.00
F Harga Satuan Pekerjaan (D+E) 96,140.00

Page 33 of 60
MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 4''
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0810 90,000.00 7,290.00
Tukang Batu OH 0.1350 130,000.00 17,550.00
Kepala Tukang OH 0.0135 145,000.00 1,957.50
Mandor OH 0.0040 135,000.00 540.00
JUMLAH TENAGA KERJA 27,337.50
B BAHAN
Pipa pvc m' 1.2000 52,500.00 63,000.00
Perlengkapan Ls 0.3500 52,500.00 18,375.00
JUMLAH HARGA BAHAN 81,375.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 108,712.50


E Overhead & Profit 10% x D 10,871.25
F Harga Satuan Pekerjaan (D+E) 119,583.75

Page 34 of 60
PERHITUNGAN VOLUME

NO URAIAN PEKERJAAN LEBAR TINGGI PJG LUAS jml VOL SAT JMLH SAT
(M) (M) m m2 TOTAL
A PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 935.75 935.75 M2
2 Pengukuran & pasang bouwplank 140.00 M'
3 Pagar pengaman proyek 156.00 M'
4 Pembuatan papan nama proyek/banner 1 1.00 Bh
5 Mobilisasi & Demobilisasi 1 1.00 Ls
6 Dokumentasi dan pelaporan 1 1.00 Ls

B PEKERJAAN STRUKTUR LANTAI 1

I PEKERJAAN PONDASI
1 Pondasi bore pile Ø 40 cm Beton Bertulang
- Pengeboran 2,197.00 M'
P1 13.00 128 1,664.00 M'
P2 13.00 30 390.00 M'
P3 13.00 11 143.00 M'
2,197.00 M'
- Pembesian Bor Pile
Besi Beton D16 27,752.00 Kg
P1 13.00 1024 13,312.00 M'
P2 13.00 240 3,120.00 M'
P3 13.00 88 1,144.00 M'
( 1.579 kg/m') 17,576.00 M'
0.00 Kg
Besi Beton Ø8 0.95 14647 13,914.33 M' 5,492.58 Kg
( 0.395 Kg/m') 5,492.58 Kg
- Pengecoran Beton K-250 (Site Mix) 276.19 M3
P1 13.00 0.13 128 209.19 M3
P2 13.00 0.13 30 49.03 M3
P3 13.00 0.13 11 17.98 M3
276.19 M3

2 Pile Cap P1 (2,00x2,00x0,60)


- Galian tanah 2.00 1.65 2.00 32 211.20 M3 211.20 M3
- Urugan pasir 2.00 0.05 2.00 32 6.40 M3 6.40 M3
- Lantai kerja beton K-100 2.00 0.10 2.00 32 12.80 M3 12.80 M3
- Beton K-300 (Readymix) 2.00 0.60 2.00 32 76.80 M3 76.80 M3
- Besi Beton D22 2.50 320 800.00 M' 4,734.36 Kg
2.46 320 785.92 M'
1,585.92 M'
Berat Besi ( 2.985 kg/m') 4,734.36 Kg
- Besi Beton D19 2.54 320 812.16 M' 3,589.63 Kg
2.50 320 800.00 M'
1,612.16 M'
Berat Besi ( 2.227 kg/m') 3,589.63 Kg
- Besi Beton D13 7.27 32 232.70 M' 242.56 Kg
Berat Besi ( 1.042 kg/m') 242.56 Kg
- Bekisting 0.60 8.00 32 153.60 M2 153.60 M2

3 Pile Cap P2 (2,00x1,20x0,60)


- Galian tanah 1.20 1.65 2.00 15 59.40 M3 59.40 M3
- Urugan pasir 1.20 0.05 2.00 15 1.80 M3 1.80 M3
- Lantai kerja beton K-100 1.20 0.10 2.00 15 3.60 M3 3.60 M3
- Beton K-300 (Readymix) 1.20 0.60 2.00 15 21.60 M3 21.60 M3
- Besi Beton D22 2.50 90 225.00 M' 1,432.92 Kg
1.70 150 255.00 M'
480.00 M'
Berat Besi ( 2.985 kg/m') 1,432.92 Kg
- Besi Beton D19 2.54 90 228.42 M' 1,076.38 Kg
1.70 150 255.00 M'
483.42 M'
Berat Besi ( 2.227 kg/m') 1,076.38 Kg
- Besi Beton D13 5.70 15 85.47 M' 89.09 Kg
Berat Besi ( 1.042 kg/m') 89.09 Kg
- Bekisting 0.60 6.40 15 57.60 M2 57.60 M2

4 Pile Cap P3 (1,20x1,20x0,50)


- Galian tanah 1.20 1.65 1.20 11 26.14 M3 26.14 M3
- Urugan pasir 1.20 0.05 1.20 11 0.79 M3 0.79 M3
- Lantai kerja beton K-100 1.20 0.10 1.20 11 1.58 M3 1.58 M3
- Beton K-300 (Readymix) 1.20 0.50 1.20 11 7.92 M3 7.92 M3
- Besi Beton D19 2.95 66 194.70 M' 861.45 Kg
2.91 66 192.19 M'
386.89 M'
Berat Besi ( 2.227 kg/m') 861.45 Kg
- Bekisting 0.50 4.80 11 26.40 M2 26.40 M2

5 Pile Cap P4 (1,00x1,00x0,30)


- Galian tanah 1.00 1.10 1.00 12 13.20 M3 13.20 M3
- Urugan pasir 1.00 0.05 1.00 12 0.60 M3 0.60 M3
- Lantai kerja beton K-100 1.00 0.05 1.00 12 0.60 M3 0.60 M3
- Beton K-300 (Readymix) 1.00 0.30 1.00 12 3.60 M3 3.60 M3
- Besi Beton D16 2.30 72 165.60 M' 519.32 Kg
2.27 72 163.30 M'
328.90 M'
Berat Besi ( 1.579 kg/m') 519.32 Kg
- Bekisting 0.30 4.00 12 14.40 M2 14.40 M2

II PEKERJAAN PONDASI PAS. BATU KALI 1:3 (Dudukan Sloof)


1 Galian tanah 0.50 0.70 503.85 1 176.35 M3 176.35 M3
2 Lantai kerja beton K-100 0.50 0.05 503.85 1 12.60 M3 12.60 M3
3 Pas. Batu Belah 1:3 0.40 0.50 503.85 1 100.77 M3 100.77 M3
4 Urugan Tanah Kembali 58.78 M3 58.78 M3

III PEKERJAAN KOLOM PEDESTAL BETON BERTULANG


1 Kolom Pedestal K1 (60x60 cm)
- Beton K-300 (Readymix) 0.60 1.40 0.60 47 23.69 M3 23.69 M3
- Besi Beton D19 1.90 940 1,786.00 M' 3,976.70 Kg
Berat Besi ( 2.227 kg/m') 3,976.70 Kg
- Besi Beton Ø10 4.91 439 2,153.85 M' 1,328.47 Kg
Berat Besi ( 0.617 kg/m') 1,328.47 Kg
- Bekisting 1.40 2.40 47 157.92 M2 157.92 M2

2 Kolom Pedestal K2 (40x40 cm)


- Beton K-300 (Readymix) 0.40 1.50 0.40 11 2.64 M3 2.64 M3
- Besi Beton D19 1.90 132 250.80 M' 558.43 Kg
Berat Besi ( 2.227 kg/m') 558.43 Kg
- Besi Beton Ø10 3.20 110 352.00 M' 217.11 Kg
Berat Besi ( 0.617 kg/m') 217.11 Kg
- Bekisting 1.50 1.60 11 26.40 M2 26.40 M2

3 Kolom Pedestal K3 (30x30 cm)


- Beton K-300 (Readymix) 0.30 1.20 0.30 12 1.30 M3 1.30 M3
- Besi Beton D16 1.50 96 144.00 M' 227.37 Kg
Berat Besi ( 1.579 kg/m') 227.37 Kg
- Besi Beton Ø8 1.02 72 73.44 M' 28.99 Kg
Berat Besi ( 0.395 kg/m') 28.99 Kg
- Bekisting 1.20 1.20 12 17.28 M2 17.28 M2

IV PEKERJAAN SLOOF (Elv. -0.50)


1 Sloof Beton Bertulang SL1 (20x40 cm) 173.60
- Beton K-300 (Readymix) 0.20 0.40 173.60 1 13.89 M3 13.89 M3
- Besi Beton D16 173.60 8 1,388.80 M' 2,192.88 Kg
Berat Besi ( 1.579 kg/m') 2,192.88 Kg
- Besi Beton Ø8 1.06 1157 1,226.77 M' 484.26 Kg
Berat Besi ( 0.395 kg/m') 484.26 Kg
- Bekisting 0.40 173.60 2 138.88 M2 138.88 M2

2 Sloof Beton Bertulang SL2 (20x30 cm) 216.10


- Beton K-300 (Readymix) 0.20 0.30 216.10 1 12.97 M3 12.97 M3
- Besi Beton D16 216.10 6 1,296.60 M' 2,047.29 Kg
Berat Besi ( 1.579 kg/m') 2,047.29 Kg
- Besi Beton Ø8 0.86 1441 1,238.97 M' 489.08 Kg
Berat Besi ( 0.395 kg/m') 489.08 Kg
- Bekisting 0.30 216.10 2 129.66 M2 129.66 M2

3 Sloof Beton Bertulang SL3 (15x25 cm) 114.15


- Beton K-300 (Readymix) 0.15 0.25 114.15 1 4.28 M3 4.28 M3
- Besi Beton D13 114.15 6 684.90 M' 713.92 Kg
Berat Besi ( 1.042 kg/m') 713.92 Kg
- Besi Beton Ø8 0.70 571 399.53 M' 157.71 Kg
Berat Besi ( 0.395 kg/m') 157.71 Kg
- Bekisting 0.25 114.15 2 57.08 M2 57.08 M2

V PEKERJAAN KOLOM BETON BERTULANG


1 Kolom Beton Bertulang K1 (60x60 cm)
- Beton K-300 (Readymix) 0.60 4.00 0.60 47 67.68 M3 67.68 M3
- Besi Beton D19 4.00 940 3,760.00 M' 8,372.00 Kg
Berat Besi ( 2.227 kg/m') 8,372.00 Kg
- Besi Beton Ø10 4.91 1253 6,153.87 M' 3,795.62 Kg
Berat Besi ( 0.617 kg/m') 3,795.62 Kg
- Bekisting 4.00 2.40 47 451.20 M2 451.20 M2
2 Kolom Beton Bertulang K2 (40x40 cm)
- Beton K-300 (Readymix) 0.40 4.00 0.40 11 7.04 M3 7.04 M3
- Besi Beton D19 4.00 132 528.00 M' 1,175.64 Kg
Berat Besi ( 2.227 kg/m') 1,175.64 Kg
- Besi Beton Ø10 3.20 293 938.67 M' 578.96 Kg
Berat Besi ( 0.617 kg/m') 578.96 Kg
- Bekisting 4.00 1.60 11 70.40 M2 70.40 M2

3 Kolom Beton Bertulang K3 (30x30 cm)


- Beton K-300 (Readymix) 0.30 4.00 0.30 4 1.44 M3 1.44 M3
- Besi Beton D16 4.00 32 128.00 M' 202.11 Kg
Berat Besi ( 1.579 kg/m') 202.11 Kg
- Besi Beton Ø8 1.02 80 81.60 M' 32.21 Kg
Berat Besi ( 0.395 kg/m') 32.21 Kg
- Bekisting 4.00 1.20 4 19.20 M2 19.20 M2

VI PEKERJAAN PIT LIFT


1 Pit Lift 1 & 2
- Galian tanah 3.70 2.00 5.20 1 38.48 M3 38.48 M3
- Urugan pasir 3.70 0.05 5.20 1 0.96 M3 0.96 M3
- Lantai kerja beton K-100 3.70 0.05 5.20 1 0.96 M3 0.96 M3
- Beton K-300 (Readymix) 12.33 M3
Lantai 3.70 0.30 5.20 1 5.77 M3
Dinding 0.20 1.60 20.50 1 6.56 M3
12.33 M3

- Besi Beton D16 1,265.07 Kg


Lantai 3.70 35 128.27 M'
5.20 25 128.27 M'
Dinding 1.90 74 140.60 M'
3.70 38 140.60 M'
1.90 69 131.73 M'
5.20 25 131.73 M'
801.20 M'
Berat Besi ( 1.579 kg/m') 1,265.07 Kg
- Bekisting 1.90 41.00 77.90 M2 77.90 M2

VII PEKERJAAN TANGGA BETON BERTULANG


1 Pondasi Tangga Beton Bertulang
- Beton K-300 (Readymix) 1.50 0.51 1 0.77 M3 0.77 M3
- Besi Beton D13 61.50 Kg
1.70 10 17.00 M'
3.00 4 12.00 M'
3.00 10 30.00 M'
59.00 M'
Berat Besi ( 1.042 kg/m') 61.50 Kg
- Bekisting 0.25 4.60 1.15 M2 5.53 M2
1.25 3.50 4.38 M2
5.53 M2
2 Balok Bordes Beton Bertulang Uk. 20x40 cm
- Beton K-300 (Readymix) 0.20 0.40 4.90 1 0.39 M3 0.39 M3
- Besi Beton D16 4.90 9 44.10 M' 69.63 Kg
Berat Besi ( 1.579 kg/m') 69.63 Kg
- Besi Beton Ø8 1.06 33 34.63 M' 13.67 Kg
Berat Besi ( 0.395 kg/m') 13.67 Kg
- Bekisting 0.85 4.90 4.17 M2 4.17 M2
3 Plat Tangga & Bordes Beton Bertulang tbl. 15 cm
- Beton K-300 (Readymix) 1.50 0.15 9.61 2.16 M3 2.16 M3
- Besi Beton D13
Memanjang 9.61 10 96.10 M' 350.60 Kg
Melintang 1.50 48 72.08 M'
168.18 M'
Jumlah 2 Lapis 336.35 M'
Berat Besi ( 1.042 kg/m') 350.60 Kg

- Bekisting 1.50 9.61 14.42 M2 14.42 M2

4 Anak Tangga Bertulang uk. 18 x 30 cm


- Beton K-300 (Readymix) 1.50 0.03 20 0.81 M3 0.81 M3
- Besi Beton D13
Memanjang 1.50 20 30.00 M' 140.72 Kg
Melintang 0.70 150 105.00 M'
135.00 M'
Berat Besi ( 1.042 kg/m') 140.72 Kg

- Bekisting 0.20 1.50 20 6.00 M2 6.00 M2

VIII PEKERJAAN RAMP BETON BERTULANG


1 Pondasi Ramp Beton Bertulang
- Galian tanah 1.00 1.10 2.25 1 2.48 M3 2.48 M3
- Urugan pasir 1.00 0.05 2.25 1 0.11 M3 0.11 M3
- Lantai kerja beton K-100 1.00 0.05 2.25 1 0.11 M3 0.11 M3
- Beton K-300 (Readymix) 2.25 0.60 1 1.35 M3 1.35 M3
- Besi Beton D16 175.27 Kg
2.20 15 33.00 M'
4.50 6 27.00 M'
3.40 15 51.00 M'
111.00 M'
Berat Besi ( 1.579 kg/m') 175.27 Kg
- Besi Beton Ø10 4.18 5 20.90 M' 12.89 Kg
Berat Besi ( 0.617 kg/m') 12.89 Kg
- Bekisting 0.30 6.50 1.95 M2 7.35 M2
1.20 4.50 5.40 M2
7.35 M2
2 Balok Bordes Beton Bertulang B2 Uk. 25x50 cm
- Beton K-300 (Readymix) 0.25 0.50 4.50 1 0.56 M3 0.56 M3
- Besi Beton D16 4.50 10 45.00 M' 71.05 Kg
Berat Besi ( 1.579 kg/m') 71.05 Kg
- Besi Beton D13 4.50 2 9.00 M' 9.38 Kg
Berat Besi ( 1.042 kg/m') 9.38 Kg
- Besi Beton Ø10 1.28 30 38.40 M' 23.68 Kg
Berat Besi ( 0.617 kg/m') 23.68 Kg
- Bekisting 0.25 4.50 2.25 M2 2.25 M2
3 Balok Ramp Beton Bertulang B2 Uk. 25x50 cm
- Beton K-300 (Readymix) 0.25 0.50 7.00 1 0.88 M3 0.88 M3
- Besi Beton D16 7.00 10 70.00 M' 110.53 Kg
Berat Besi ( 1.579 kg/m') 110.53 Kg
- Besi Beton D13 7.00 2 14.00 M' 14.59 Kg
Berat Besi ( 1.042 kg/m') 14.59 Kg
- Besi Beton Ø10 1.28 47 59.73 M' 36.84 Kg
Berat Besi ( 0.617 kg/m') 36.84 Kg
- Bekisting 0.25 7.00 3.50 M2 3.50 M2
4 Plat Ramp Beton Bertulang tbl. 25 cm
- Beton K-300 (Readymix) 2.25 0.25 34.80 19.58 M3 19.58 M3
- Besi Beton D16 34.80 23 783.00 M' 1,236.33 Kg
Berat Besi ( 1.579 kg/m') 1,236.33 Kg
- Besi Beton D13 2.25 174 391.50 M' 408.09 Kg
Berat Besi ( 1.042 kg/m') 408.09 Kg

- Bekisting 2.25 34.80 78.30 M2 78.30 M2

C PEKERJAAN STRUKTUR LANTAI 2

I PEKERJAAN BALOK BETON BERTULANG Elv. + 4.00


1 Balok Beton Bertulang B1 (30x60 cm)
- Beton K-300 (Readymix) 0.30 0.60 134.40 1 24.19 M3 24.19 M3
- Besi Beton D19 134.40 12 1,612.80 M' 3,591.05 Kg
Berat Besi ( 2.227 kg/m') 3,591.05 Kg
- Besi Beton D16 134.40 2 268.80 M' 424.43 Kg
Berat Besi ( 1.579 kg/m') 424.43 Kg
- Besi Beton Ø10 1.58 896 1,415.68 M' 873.17 Kg
Berat Besi ( 0.617 kg/m') 873.17 Kg
- Bekisting 0.30 0.45 134.40 161.28 M2 161.28 M2

2 Balok Beton Bertulang B2 (25x50 cm)


- Beton K-300 (Readymix) 0.25 0.50 43.20 1 5.40 M3 5.40 M3
- Besi Beton D16 43.20 10 432.00 M' 682.12 Kg
Berat Besi ( 1.579 kg/m') 682.12 Kg
- Besi Beton D13 43.20 2 86.40 M' 90.06 Kg
Berat Besi ( 1.042 kg/m') 90.06 Kg
- Besi Beton Ø10 1.28 288 368.64 M' 227.37 Kg
Berat Besi ( 0.617 kg/m') 227.37 Kg
- Bekisting 0.25 0.35 43.20 41.04 M2 41.04 M2

3 Balok Beton Bertulang B3 (20x40 cm)


- Beton K-300 (Readymix) 0.20 0.40 187.40 1 14.99 M3 14.99 M3
- Besi Beton D16 187.40 9 1,686.60 M' 2,663.09 Kg
Berat Besi ( 1.579 kg/m') 2,663.09 Kg
- Besi Beton Ø8 1.06 1249 1,324.29 M' 522.76 Kg
Berat Besi ( 0.395 kg/m') 522.76 Kg
- Bekisting 0.20 0.25 187.40 131.18 M2 131.18 M2

4 Balok Beton Bertulang B4 (20x30 cm)


- Beton K-300 (Readymix) 0.20 0.30 100.70 1 6.04 M3 6.04 M3
- Besi Beton D16 100.70 7 704.90 M' 1,113.02 Kg
Berat Besi ( 1.579 kg/m') 1,113.02 Kg
- Besi Beton Ø8 0.86 671 577.35 M' 227.90 Kg
Berat Besi ( 0.395 kg/m') 227.90 Kg
- Bekisting 0.20 0.15 100.70 50.35 M2 50.35 M2

5 Balok Beton Bertulang B5 (15x35cm)


- Beton K-300 (Readymix) 0.15 0.35 21.00 1 1.10 M3 1.10 M3
- Besi Beton D16 21.00 6 126.00 M' 198.95 Kg
Berat Besi ( 1.579 kg/m') 198.95 Kg
- Besi Beton D13 21.00 2 42.00 M' 43.78 Kg
Berat Besi ( 1.042 kg/m') 43.78 Kg
- Besi Beton Ø8 0.82 140 114.80 M' 45.32 Kg
Berat Besi ( 0.395 kg/m') 45.32 Kg
- Bekisting 0.15 0.20 21.00 11.55 M2 11.55 M2

6 Balok Beton Bertulang B6 (15x30 cm)


- Beton K-300 (Readymix) 0.15 0.30 41.80 1 1.88 M3 1.88 M3
- Besi Beton D16 41.80 6 250.80 M' 396.01 Kg
Berat Besi ( 1.579 kg/m') 396.01 Kg
- Besi Beton Ø8 0.72 279 200.64 M' 79.20 Kg
Berat Besi ( 0.395 kg/m') 79.20 Kg
- Bekisting 0.15 0.15 41.80 18.81 M2 18.81 M2

7 Balok Separator Lift B4 (20x30 cm)


- Beton K-300 (Readymix) 0.20 0.30 9.30 1 0.56 M3 0.56 M3
- Besi Beton D16 9.30 7 65.10 M' 102.79 Kg
Berat Besi ( 1.579 kg/m') 102.79 Kg
- Besi Beton Ø8 0.86 62 53.32 M' 21.05 Kg
Berat Besi ( 0.395 kg/m') 21.05 Kg
- Bekisting 0.20 0.15 9.30 4.65 M2 4.65 M2

II PEKERJAAN PLAT LANTAI BETON BERTULANG Elv. + 4.00


- Beton K-300 (Readymix) 0.13 742.81 92.85 M3 92.85 M3
- Wiremesh M8 4,452.21 Kg
M8 ( 61.790 kg/lbr)
Ukuran Per Lembar 2.10 5.40 11.34 M2
Jumlah Lembar yg dibutuhkan 65.50 Lbr
Overlap Sambungan 6.55 Lbr
72.05 Lbr
Berat Wiremesh 4,452.21 Kg

- Pelat Bondek / Floor Deck 742.81 M2 742.81 M2

III PEKERJAAN KOLOM BETON BERTULANG


1 Kolom Beton Bertulang K1 (60x60 cm)
- Beton K-300 (Readymix) 0.60 4.00 0.60 47 67.68 M3 67.68 M3
- Besi Beton D19 4.00 940 3,760.00 M' 8,372.00 Kg
Berat Besi ( 2.227 kg/m') 8,372.00 Kg
- Besi Beton Ø10 4.91 1253 6,153.87 M' 3,795.62 Kg
Berat Besi ( 0.617 kg/m') 3,795.62 Kg
- Bekisting 4.00 2.40 47 451.20 M2 451.20 M2
2 Kolom Beton Bertulang K2 (40x40 cm)
- Beton K-300 (Readymix) 0.40 4.00 0.40 11 7.04 M3 7.04 M3
- Besi Beton D19 4.00 132 528.00 M' 1,175.64 Kg
Berat Besi ( 2.227 kg/m') 1,175.64 Kg
- Besi Beton Ø10 3.20 293 938.67 M' 578.96 Kg
Berat Besi ( 0.617 kg/m') 578.96 Kg
- Bekisting 4.00 1.60 11 70.40 M2 70.40 M2

IV PEKERJAAN TANGGA BETON BERTULANG


1 Balok Bordes Beton Bertulang Uk. 20x40 cm
- Beton K-300 (Readymix) 0.20 0.40 4.90 1 0.39 M3 0.39 M3
- Besi Beton D16 4.90 9 44.10 M' 69.63 Kg
Berat Besi ( 1.579 kg/m') 69.63 Kg
- Besi Beton Ø8 1.06 33 34.63 M' 13.67 Kg
Berat Besi ( 0.395 kg/m') 13.67 Kg
- Bekisting 0.85 4.90 4.17 M2 4.17 M2
2 Plat Tangga & Bordes Beton Bertulang tbl. 15 cm
- Beton K-300 (Readymix) 1.50 0.15 9.61 2.16 M3 2.16 M3
- Besi Beton D13
Memanjang 9.61 10 96.10 M' 350.60 Kg
Melintang 1.50 48 72.08 M'
168.18 M'
Jumlah 2 Lapis 336.35 M'
Berat Besi ( 1.042 kg/m') 350.60 Kg

- Bekisting 1.50 9.61 14.42 M2 14.42 M2

3 Anak Tangga Bertulang uk. 18 x 30 cm


- Beton K-300 (Readymix) 1.50 0.03 20 0.81 M3 0.81 M3
- Besi Beton D13
Memanjang 1.50 20 30.00 M' 140.72 Kg
Melintang 0.70 150 105.00 M'
135.00 M'
Berat Besi ( 1.042 kg/m') 140.72 Kg

- Bekisting 0.20 1.50 20 6.00 M2 6.00 M2

V PEKERJAAN RAMP BETON BERTULANG


1 Balok Bordes Beton Bertulang B2 Uk. 25x50 cm
- Beton K-300 (Readymix) 0.25 0.50 4.50 1 0.56 M3 0.56 M3
- Besi Beton D16 4.50 10 45.00 M' 71.05 Kg
Berat Besi ( 1.579 kg/m') 71.05 Kg
- Besi Beton D13 4.50 2 9.00 M' 9.38 Kg
Berat Besi ( 1.042 kg/m') 9.38 Kg
- Besi Beton Ø10 1.28 30 38.40 M' 23.68 Kg
Berat Besi ( 0.617 kg/m') 23.68 Kg
- Bekisting 0.25 4.50 2.25 M2 2.25 M2
2 Balok Ramp Beton Bertulang B2 Uk. 25x50 cm
- Beton K-300 (Readymix) 0.25 0.50 7.00 1 0.88 M3 0.88 M3
- Besi Beton D16 7.00 10 70.00 M' 110.53 Kg
Berat Besi ( 1.579 kg/m') 110.53 Kg
- Besi Beton D13 7.00 2 14.00 M' 14.59 Kg
Berat Besi ( 1.042 kg/m') 14.59 Kg
- Besi Beton Ø10 1.28 47 59.73 M' 36.84 Kg
Berat Besi ( 0.617 kg/m') 36.84 Kg
- Bekisting 0.25 7.00 3.50 M2 3.50 M2
3 Plat Ramp Beton Bertulang tbl. 25 cm
- Beton K-300 (Readymix) 2.25 0.25 31.32 17.62 M3 17.62 M3
- Besi Beton D16 31.32 23 704.70 M' 1,112.70 Kg
Berat Besi ( 1.579 kg/m') 1,112.70 Kg
- Besi Beton D13 2.25 157 352.35 M' 367.28 Kg
Berat Besi ( 1.042 kg/m') 367.28 Kg

- Bekisting 2.25 31.32 70.47 M2 70.47 M2

D PEKERJAAN STRUKTUR LANTAI 3

I PEKERJAAN BALOK BETON BERTULANG Elv. + 8.00


1 Balok Beton Bertulang B1 (30x60 cm)
- Beton K-300 (Readymix) 0.30 0.60 134.40 1 24.19 M3 24.19 M3
- Besi Beton D19 134.40 12 1,612.80 M' 3,591.05 Kg
Berat Besi ( 2.227 kg/m') 3,591.05 Kg
- Besi Beton D16 134.40 2 268.80 M' 424.43 Kg
Berat Besi ( 1.579 kg/m') 424.43 Kg
- Besi Beton Ø10 1.58 896 1,415.68 M' 873.17 Kg
Berat Besi ( 0.617 kg/m') 873.17 Kg
- Bekisting 0.30 0.45 134.40 161.28 M2 161.28 M2

2 Balok Beton Bertulang B2 (25x50 cm)


- Beton K-300 (Readymix) 0.25 0.50 43.20 1 5.40 M3 5.40 M3
- Besi Beton D16 43.20 10 432.00 M' 682.12 Kg
Berat Besi ( 1.579 kg/m') 682.12 Kg
- Besi Beton D13 43.20 2 86.40 M' 90.06 Kg
Berat Besi ( 1.042 kg/m') 90.06 Kg
- Besi Beton Ø10 1.28 288 368.64 M' 227.37 Kg
Berat Besi ( 0.617 kg/m') 227.37 Kg
- Bekisting 0.25 0.35 43.20 41.04 M2 41.04 M2

3 Balok Beton Bertulang B3 (20x40 cm)


- Beton K-300 (Readymix) 0.20 0.40 180.00 1 14.40 M3 14.40 M3
- Besi Beton D16 180.00 9 1,620.00 M' 2,557.93 Kg
Berat Besi ( 1.579 kg/m') 2,557.93 Kg
- Besi Beton Ø8 1.06 1200 1,272.00 M' 502.11 Kg
Berat Besi ( 0.395 kg/m') 502.11 Kg
- Bekisting 0.20 0.25 180.00 126.00 M2 126.00 M2

4 Balok Beton Bertulang B4 (20x30 cm)


- Beton K-300 (Readymix) 0.20 0.30 87.50 1 5.25 M3 5.25 M3
- Besi Beton D16 87.50 7 612.50 M' 967.12 Kg
Berat Besi ( 1.579 kg/m') 967.12 Kg
- Besi Beton Ø8 0.86 583 501.67 M' 198.03 Kg
Berat Besi ( 0.395 kg/m') 198.03 Kg
- Bekisting 0.20 0.15 87.50 43.75 M2 43.75 M2

5 Balok Beton Bertulang B5 (15x35cm)


- Beton K-300 (Readymix) 0.15 0.35 21.00 1 1.10 M3 1.10 M3
- Besi Beton D16 21.00 6 126.00 M' 198.95 Kg
Berat Besi ( 1.579 kg/m') 198.95 Kg
- Besi Beton D13 21.00 2 42.00 M' 43.78 Kg
Berat Besi ( 1.042 kg/m') 43.78 Kg
- Besi Beton Ø8 0.82 140 114.80 M' 45.32 Kg
Berat Besi ( 0.395 kg/m') 45.32 Kg
- Bekisting 0.15 0.20 21.00 11.55 M2 11.55 M2

6 Balok Beton Bertulang B6 (15x30 cm)


- Beton K-300 (Readymix) 0.15 0.30 33.30 1 1.50 M3 1.50 M3
- Besi Beton D16 33.30 6 199.80 M' 315.48 Kg
Berat Besi ( 1.579 kg/m') 315.48 Kg
- Besi Beton Ø8 0.72 222 159.84 M' 63.10 Kg
Berat Besi ( 0.395 kg/m') 63.10 Kg
- Bekisting 0.15 0.15 33.30 14.99 M2 14.99 M2

7 Balok Separator Lift B4 (20x30 cm)


- Beton K-300 (Readymix) 0.20 0.30 9.30 1 0.56 M3 0.56 M3
- Besi Beton D16 9.30 7 65.10 M' 102.79 Kg
Berat Besi ( 1.579 kg/m') 102.79 Kg
- Besi Beton Ø8 0.86 62 53.32 M' 21.05 Kg
Berat Besi ( 0.395 kg/m') 21.05 Kg
- Bekisting 0.20 0.15 9.30 4.65 M2 4.65 M2

II PEKERJAAN PLAT LANTAI BETON BERTULANG Elv. + 8.00


- Beton K-300 (Readymix) 0.13 697.36 87.17 M3 87.17 M3
- Wiremesh M8 4,179.79 Kg
M8 ( 61.790 kg/lbr)
Ukuran Per Lembar 2.10 5.40 11.34 M2
Jumlah Lembar yg dibutuhkan 61.50 Lbr
Overlap Sambungan 6.15 Lbr
67.65 Lbr
Berat Wiremesh 4,179.79 Kg

- Pelat Bondek / Floor Deck 697.36 M2 697.36 M2

III PEKERJAAN KOLOM BETON BERTULANG


1 Kolom Beton Bertulang K1 (60x60 cm)
- Beton K-300 (Readymix) 0.60 4.00 0.60 47 67.68 M3 67.68 M3
- Besi Beton D19 4.00 940 3,760.00 M' 8,372.00 Kg
Berat Besi ( 2.227 kg/m') 8,372.00 Kg
- Besi Beton Ø10 4.91 1253 6,153.87 M' 3,795.62 Kg
Berat Besi ( 0.617 kg/m') 3,795.62 Kg
- Bekisting 4.00 2.40 47 451.20 M2 451.20 M2

2 Kolom Beton Bertulang K2 (40x40 cm)


- Beton K-300 (Readymix) 0.40 4.00 0.40 11 7.04 M3 7.04 M3
- Besi Beton D19 4.00 132 528.00 M' 1,175.64 Kg
Berat Besi ( 2.227 kg/m') 1,175.64 Kg
- Besi Beton Ø10 3.20 293 938.67 M' 578.96 Kg
Berat Besi ( 0.617 kg/m') 578.96 Kg
- Bekisting 4.00 1.60 11 70.40 M2 70.40 M2

IV PEKERJAAN TANGGA BETON BERTULANG


1 Balok Bordes Beton Bertulang Uk. 20x40 cm
- Beton K-300 (Readymix) 0.20 0.40 4.90 1 0.39 M3 0.39 M3
- Besi Beton D16 4.90 9 44.10 M' 69.63 Kg
Berat Besi ( 1.579 kg/m') 69.63 Kg
- Besi Beton Ø8 1.06 33 34.63 M' 13.67 Kg
Berat Besi ( 0.395 kg/m') 13.67 Kg
- Bekisting 0.85 4.90 4.17 M2 4.17 M2
2 Plat Tangga & Bordes Beton Bertulang tbl. 15 cm
- Beton K-300 (Readymix) 1.50 0.15 9.61 2.16 M3 2.16 M3
- Besi Beton D13
Memanjang 9.61 10 96.10 M' 350.60 Kg
Melintang 1.50 48 72.08 M'
168.18 M'
Jumlah 2 Lapis 336.35 M'
Berat Besi ( 1.042 kg/m') 350.60 Kg

- Bekisting 1.50 9.61 14.42 M2 14.42 M2

3 Anak Tangga Bertulang uk. 18 x 30 cm


- Beton K-300 (Readymix) 1.50 0.03 20 0.81 M3 0.81 M3
- Besi Beton D13
Memanjang 1.50 20 30.00 M' 140.72 Kg
Melintang 0.70 150 105.00 M'
135.00 M'
Berat Besi ( 1.042 kg/m') 140.72 Kg

- Bekisting 0.20 1.50 20 6.00 M2 6.00 M2

V PEKERJAAN RAMP BETON BERTULANG


1 Balok Bordes Beton Bertulang B2 Uk. 25x50 cm
- Beton K-300 (Readymix) 0.25 0.50 4.50 1 0.56 M3 0.56 M3
- Besi Beton D16 4.50 10 45.00 M' 71.05 Kg
Berat Besi ( 1.579 kg/m') 71.05 Kg
- Besi Beton D13 4.50 2 9.00 M' 9.38 Kg
Berat Besi ( 1.042 kg/m') 9.38 Kg
- Besi Beton Ø10 1.28 30 38.40 M' 23.68 Kg
Berat Besi ( 0.617 kg/m') 23.68 Kg
- Bekisting 0.25 4.50 2.25 M2 2.25 M2
2 Balok Ramp Beton Bertulang B2 Uk. 25x50 cm
- Beton K-300 (Readymix) 0.25 0.50 7.00 1 0.88 M3 0.88 M3
- Besi Beton D16 7.00 10 70.00 M' 110.53 Kg
Berat Besi ( 1.579 kg/m') 110.53 Kg
- Besi Beton D13 7.00 2 14.00 M' 14.59 Kg
Berat Besi ( 1.042 kg/m') 14.59 Kg
- Besi Beton Ø10 1.28 47 59.73 M' 36.84 Kg
Berat Besi ( 0.617 kg/m') 36.84 Kg
- Bekisting 0.25 7.00 3.50 M2 3.50 M2
3 Plat Ramp Beton Bertulang tbl. 25 cm
- Beton K-300 (Readymix) 2.25 0.25 34.80 19.58 M3 19.58 M3
- Besi Beton D16 34.80 23 783.00 M' 1,236.33 Kg
Berat Besi ( 1.579 kg/m') 1,236.33 Kg
- Besi Beton D13 2.25 174 391.50 M' 408.09 Kg
Berat Besi ( 1.042 kg/m') 408.09 Kg

- Bekisting 2.25 34.80 78.30 M2 78.30 M2

E PEKERJAAN STRUKTUR LANTAI 4

I PEKERJAAN BALOK BETON BERTULANG Elv. + 12.00


1 Balok Beton Bertulang B1 (30x60 cm)
- Beton K-300 (Readymix) 0.30 0.60 134.40 1 24.19 M3 24.19 M3
- Besi Beton D19 134.40 12 1,612.80 M' 3,591.05 Kg
Berat Besi ( 2.227 kg/m') 3,591.05 Kg
- Besi Beton D16 134.40 2 268.80 M' 424.43 Kg
Berat Besi ( 1.579 kg/m') 424.43 Kg
- Besi Beton Ø10 1.58 896 1,415.68 M' 873.17 Kg
Berat Besi ( 0.617 kg/m') 873.17 Kg
- Bekisting 0.30 0.45 134.40 161.28 M2 161.28 M2

2 Balok Beton Bertulang B2 (25x50 cm)


- Beton K-300 (Readymix) 0.25 0.50 43.20 1 5.40 M3 5.40 M3
- Besi Beton D16 43.20 10 432.00 M' 682.12 Kg
Berat Besi ( 1.579 kg/m') 682.12 Kg
- Besi Beton D13 43.20 2 86.40 M' 90.06 Kg
Berat Besi ( 1.042 kg/m') 90.06 Kg
- Besi Beton Ø10 1.28 288 368.64 M' 227.37 Kg
Berat Besi ( 0.617 kg/m') 227.37 Kg
- Bekisting 0.25 0.35 43.20 41.04 M2 41.04 M2

3 Balok Beton Bertulang B3 (20x40 cm)


- Beton K-300 (Readymix) 0.20 0.40 180.00 1 14.40 M3 14.40 M3
- Besi Beton D16 180.00 9 1,620.00 M' 2,557.93 Kg
Berat Besi ( 1.579 kg/m') 2,557.93 Kg
- Besi Beton Ø8 1.06 1200 1,272.00 M' 502.11 Kg
Berat Besi ( 0.395 kg/m') 502.11 Kg
- Bekisting 0.20 0.25 180.00 126.00 M2 126.00 M2

4 Balok Beton Bertulang B4 (20x30 cm)


- Beton K-300 (Readymix) 0.20 0.30 87.50 1 5.25 M3 5.25 M3
- Besi Beton D16 87.50 7 612.50 M' 967.12 Kg
Berat Besi ( 1.579 kg/m') 967.12 Kg
- Besi Beton Ø8 0.86 583 501.67 M' 198.03 Kg
Berat Besi ( 0.395 kg/m') 198.03 Kg
- Bekisting 0.20 0.15 87.50 43.75 M2 43.75 M2

5 Balok Beton Bertulang B5 (15x35cm)


- Beton K-300 (Readymix) 0.15 0.35 21.00 1 1.10 M3 1.10 M3
- Besi Beton D16 21.00 6 126.00 M' 198.95 Kg
Berat Besi ( 1.579 kg/m') 198.95 Kg
- Besi Beton D13 21.00 2 42.00 M' 43.78 Kg
Berat Besi ( 1.042 kg/m') 43.78 Kg
- Besi Beton Ø8 0.82 140 114.80 M' 45.32 Kg
Berat Besi ( 0.395 kg/m') 45.32 Kg
- Bekisting 0.15 0.20 21.00 11.55 M2 11.55 M2

6 Balok Beton Bertulang B6 (15x30 cm)


- Beton K-300 (Readymix) 0.15 0.30 33.30 1 1.50 M3 1.50 M3
- Besi Beton D16 33.30 6 199.80 M' 315.48 Kg
Berat Besi ( 1.579 kg/m') 315.48 Kg
- Besi Beton Ø8 0.72 222 159.84 M' 63.10 Kg
Berat Besi ( 0.395 kg/m') 63.10 Kg
- Bekisting 0.15 0.15 33.30 14.99 M2 14.99 M2

7 Balok Separator Lift B4 (20x30 cm)


- Beton K-300 (Readymix) 0.20 0.30 9.30 1 0.56 M3 0.56 M3
- Besi Beton D16 9.30 7 65.10 M' 102.79 Kg
Berat Besi ( 1.579 kg/m') 102.79 Kg
- Besi Beton Ø8 0.86 62 53.32 M' 21.05 Kg
Berat Besi ( 0.395 kg/m') 21.05 Kg
- Bekisting 0.20 0.15 9.30 4.65 M2 4.65 M2

II PEKERJAAN PLAT LANTAI BETON BERTULANG Elv. + 12.00


- Beton K-300 (Readymix) 0.13 690.77 86.35 M3 86.35 M3
- Wiremesh M8 4,140.30 Kg
M8 ( 61.790 kg/lbr)
Ukuran Per Lembar 2.10 5.40 11.34 M2
Jumlah Lembar yg dibutuhkan 60.91 Lbr
Overlap Sambungan 6.09 Lbr
67.01 Lbr
Berat Wiremesh 4,140.30 Kg

- Pelat Bondek / Floor Deck 690.77 M2 690.77 M2

III PEKERJAAN KOLOM BETON BERTULANG


1 Kolom Beton Bertulang K1 (60x60 cm)
- Beton K-300 (Readymix) 0.60 4.00 0.60 47 67.68 M3 67.68 M3
- Besi Beton D19 4.00 940 3,760.00 M' 8,372.00 Kg
Berat Besi ( 2.227 kg/m') 8,372.00 Kg
- Besi Beton Ø10 4.91 1253 6,153.87 M' 3,795.62 Kg
Berat Besi ( 0.617 kg/m') 3,795.62 Kg
- Bekisting 4.00 2.40 47 451.20 M2 451.20 M2

2 Kolom Beton Bertulang K2 (40x40 cm)


- Beton K-300 (Readymix) 0.40 4.00 0.40 11 7.04 M3 7.04 M3
- Besi Beton D19 4.00 132 528.00 M' 1,175.64 Kg
Berat Besi ( 2.227 kg/m') 1,175.64 Kg
- Besi Beton Ø10 3.20 293 938.67 M' 578.96 Kg
Berat Besi ( 0.617 kg/m') 578.96 Kg
- Bekisting 4.00 1.60 11 70.40 M2 70.40 M2
IV PEKERJAAN TANGGA BETON BERTULANG
1 Balok Bordes Beton Bertulang Uk. 20x40 cm
- Beton K-300 (Readymix) 0.20 0.40 4.90 1 0.39 M3 0.39 M3
- Besi Beton D16 4.90 9 44.10 M' 69.63 Kg
Berat Besi ( 1.579 kg/m') 69.63 Kg
- Besi Beton Ø8 1.06 33 34.63 M' 13.67 Kg
Berat Besi ( 0.395 kg/m') 13.67 Kg
- Bekisting 0.85 4.90 4.17 M2 4.17 M2
2 Plat Tangga & Bordes Beton Bertulang tbl. 15 cm
- Beton K-300 (Readymix) 1.50 0.15 9.61 2.16 M3 2.16 M3
- Besi Beton D13
Memanjang 9.61 10 96.10 M' 350.60 Kg
Melintang 1.50 48 72.08 M'
168.18 M'
Jumlah 2 Lapis 336.35 M'
Berat Besi ( 1.042 kg/m') 350.60 Kg

- Bekisting 1.50 9.61 14.42 M2 14.42 M2

3 Anak Tangga Bertulang uk. 18 x 30 cm


- Beton K-300 (Readymix) 1.50 0.03 20 0.81 M3 0.81 M3
- Besi Beton D13
Memanjang 1.50 20 30.00 M' 140.72 Kg
Melintang 0.70 150 105.00 M'
135.00 M'
Berat Besi ( 1.042 kg/m') 140.72 Kg

- Bekisting 0.20 1.50 20 6.00 M2 6.00 M2

V PEKERJAAN RAMP BETON BERTULANG


1 Balok Bordes Beton Bertulang B2 Uk. 25x50 cm
- Beton K-300 (Readymix) 0.25 0.50 4.50 1 0.56 M3 0.56 M3
- Besi Beton D16 4.50 10 45.00 M' 71.05 Kg
Berat Besi ( 1.579 kg/m') 71.05 Kg
- Besi Beton D13 4.50 2 9.00 M' 9.38 Kg
Berat Besi ( 1.042 kg/m') 9.38 Kg
- Besi Beton Ø10 1.28 30 38.40 M' 23.68 Kg
Berat Besi ( 0.617 kg/m') 23.68 Kg
- Bekisting 0.25 4.50 2.25 M2 2.25 M2
2 Balok Ramp Beton Bertulang B2 Uk. 25x50 cm
- Beton K-300 (Readymix) 0.25 0.50 7.00 1 0.88 M3 0.88 M3
- Besi Beton D16 7.00 10 70.00 M' 110.53 Kg
Berat Besi ( 1.579 kg/m') 110.53 Kg
- Besi Beton D13 7.00 2 14.00 M' 14.59 Kg
Berat Besi ( 1.042 kg/m') 14.59 Kg
- Besi Beton Ø10 1.28 47 59.73 M' 36.84 Kg
Berat Besi ( 0.617 kg/m') 36.84 Kg
- Bekisting 0.25 7.00 3.50 M2 3.50 M2
3 Plat Ramp Beton Bertulang tbl. 25 cm
- Beton K-300 (Readymix) 2.25 0.25 34.80 19.58 M3 19.58 M3
- Besi Beton D16 34.80 23 783.00 M' 1,236.33 Kg
Berat Besi ( 1.579 kg/m') 1,236.33 Kg
- Besi Beton D13 2.25 174 391.50 M' 408.09 Kg
Berat Besi ( 1.042 kg/m') 408.09 Kg

- Bekisting 2.25 34.80 78.30 M2 78.30 M2

F PEKERJAAN STRUKTUR LANTAI ATAP

I PEKERJAAN BALOK BETON BERTULANG Elv. + 16.50


1 Balok Beton Bertulang B1 (30x60 cm)
- Beton K-300 (Readymix) 0.30 0.60 134.40 1 24.19 M3 24.19 M3
- Besi Beton D19 134.40 12 1,612.80 M' 3,591.05 Kg
Berat Besi ( 2.227 kg/m') 3,591.05 Kg
- Besi Beton D16 134.40 2 268.80 M' 424.43 Kg
Berat Besi ( 1.579 kg/m') 424.43 Kg
- Besi Beton Ø10 1.58 896 1,415.68 M' 873.17 Kg
Berat Besi ( 0.617 kg/m') 873.17 Kg
- Bekisting 0.30 0.45 134.40 161.28 M2 161.28 M2

2 Balok Beton Bertulang B2 (25x50 cm)


- Beton K-300 (Readymix) 0.25 0.50 39.20 1 4.90 M3 4.90 M3
- Besi Beton D16 39.20 10 392.00 M' 618.96 Kg
Berat Besi ( 1.579 kg/m') 618.96 Kg
- Besi Beton D13 39.20 2 78.40 M' 81.72 Kg
Berat Besi ( 1.042 kg/m') 81.72 Kg
- Besi Beton Ø10 1.28 261 334.51 M' 206.32 Kg
Berat Besi ( 0.617 kg/m') 206.32 Kg
- Bekisting 0.25 0.35 39.20 37.24 M2 37.24 M2

3 Balok Beton Bertulang B3 (20x40 cm)


- Beton K-300 (Readymix) 0.20 0.40 200.30 1 16.02 M3 16.02 M3
- Besi Beton D16 200.30 9 1,802.70 M' 2,846.41 Kg
Berat Besi ( 1.579 kg/m') 2,846.41 Kg
- Besi Beton Ø8 1.06 1335 1,415.45 M' 558.74 Kg
Berat Besi ( 0.395 kg/m') 558.74 Kg
- Bekisting 0.20 0.25 200.30 140.21 M2 140.21 M2

4 Balok Beton Bertulang B4 (20x30 cm)


- Beton K-300 (Readymix) 0.20 0.30 87.50 1 5.25 M3 5.25 M3
- Besi Beton D16 87.50 7 612.50 M' 967.12 Kg
Berat Besi ( 1.579 kg/m') 967.12 Kg
- Besi Beton Ø8 0.86 583 501.67 M' 198.03 Kg
Berat Besi ( 0.395 kg/m') 198.03 Kg
- Bekisting 0.20 0.15 87.50 43.75 M2 43.75 M2

5 Balok Beton Bertulang B5 (15x35cm)


- Beton K-300 (Readymix) 0.15 0.35 21.00 1 1.10 M3 1.10 M3
- Besi Beton D16 21.00 6 126.00 M' 198.95 Kg
Berat Besi ( 1.579 kg/m') 198.95 Kg
- Besi Beton D13 21.00 2 42.00 M' 43.78 Kg
Berat Besi ( 1.042 kg/m') 43.78 Kg
- Besi Beton Ø8 0.82 140 114.80 M' 45.32 Kg
Berat Besi ( 0.395 kg/m') 45.32 Kg
- Bekisting 0.15 0.20 21.00 11.55 M2 11.55 M2

6 Balok Beton Bertulang B6 (15x30 cm)


- Beton K-300 (Readymix) 0.15 0.30 33.30 1 1.50 M3 1.50 M3
- Besi Beton D16 33.30 6 199.80 M' 315.48 Kg
Berat Besi ( 1.579 kg/m') 315.48 Kg
- Besi Beton Ø8 0.72 222 159.84 M' 63.10 Kg
Berat Besi ( 0.395 kg/m') 63.10 Kg
- Bekisting 0.15 0.15 33.30 14.99 M2 14.99 M2

7 Balok Separator Lift B4 (20x30 cm)


- Beton K-300 (Readymix) 0.20 0.30 9.30 1 0.56 M3 0.56 M3
- Besi Beton D16 9.30 7 65.10 M' 102.79 Kg
Berat Besi ( 1.579 kg/m') 102.79 Kg
- Besi Beton Ø8 0.86 62 53.32 M' 21.05 Kg
Berat Besi ( 0.395 kg/m') 21.05 Kg
- Bekisting 0.20 0.15 9.30 4.65 M2 4.65 M2

II PEKERJAAN PLAT LANTAI BETON BERTULANG Elv. + 16.50


- Beton K-300 (Readymix) 0.13 760.55 95.07 M3 95.07 M3
- Wiremesh M8 4,558.54 Kg
M8 ( 61.790 kg/lbr)
Ukuran Per Lembar 2.10 5.40 11.34 M2
Jumlah Lembar yg dibutuhkan 67.07 Lbr
Overlap Sambungan 6.71 Lbr
73.77 Lbr
Berat Wiremesh 4,558.54 Kg

- Pelat Bondek / Floor Deck 760.55 M2 760.55 M2

IV PEKERJAAN TOILET TRIBUN DAN RUANG KAJUR

1 Pasangan Dinding 1/2 Bata ad. 1 : 4 24.34 M2


2.50 1.60 2 8.00
2.50 1.35 3 10.13
2.50 1.47 1 3.68
0.80 1.35 2 2.16
1.00 4.68 1 4.68
28.64

pengurangan pintu 2.05 0.70 3 4.31

Plesteran Dinding ad. 1 : 4 24.34 2 48.67 M2

Kolom Praktis uk. 11/11 cm 2.50 4 10.00 M'


Ring Balok uk. 10/15 cm 1.60 2 3.20 8.72 M'
1.35 3 4.05
1.47 1 1.47
8.72

Urugan Tanah Peninggi Lantai 0.80 0.40 1.20 3 1.15 M3

Lantai kerja Beton K.100 Tebal 5 cm 1.35 0.05 1.60 2 0.22 0.32 M3
1.35 0.05 1.47 1 0.10
0.32

Pas. Keramik Lantai uk. 25x25 1.35 1.60 2 4.32 6.30 M2


1.35 1.47 1 1.98
6.30

Pas. Keramik Dinding uk. 25x40 4.60 1.60 2 14.72 30.42 M2


4.32 1.60 2 13.82
4.68 0.40 1 1.87
30.42

Pas. Rangka Plafond Besi Hollow 1.35 1.60 2 4.32 8.29 M2


1.35 1.47 2 3.97
8.29

Pas. Plafond Gypsum 9 mm 8.29 8.29 M2


Pas. Kloset Duduk 3 3.00 Bh
Pas. Kloset Jongkok 1 1.00 Bh
Pas. Floordrain Besi 4 4.00 Bh
Pas. Pipa Air Kotor 4" 72 72.00 M'
Pas. Pipa Air Kotor 3" 56 56.00 M'
Pas. Pipa Air Bersih 3/4" 96 96.00 M'
Pas. Kran Air 5 5.00 Bh
Pembuatan Septictank 1 1.00 Bh
Pas. Kusen Pintu & Ventilasi Kayu Bulian 0.23 M3
0.06 0.12 4.80 5 0.17
0.06 0.12 2.00 4 0.06
0.23

Pas. Pintu Panel Kayu Kelas I 0.60 2.00 5 6.00 M2


Pas. Engsel Pintu 15 15.00 Bh
Pas. Kunci Pintu 5 5.00 Set
Pas. Grendel Pintu 5 5.00 Bh
Pas. Kaca Mati 5 mm 0.45 0.60 8 2.16 M2
Instalasi Listrik 4 4.00 Titik
Pas. Lampu LED Petak 6 Watt 4 4.00 Bh
Saklar Ganda 2 2.00 Bh
Pengecatan Dinding & Plafond 48.67 48.67 M2
Pengecatan Pintu 12.00 12.00 M2
II PEKERJAAN KOLOM DAN BALOK BETON BERTULANG
1 Sloof Beton Bertulang SL2 (20x30 cm) 54.00
- Beton K-250 0.20 0.30 54.00 1 3.24 M3 3.24 M3
- Besi Beton Ø 16 54.00 6 324.00 M' 511.59 Kg
Berat Besi ( 1.579 kg/m') 511.59 Kg
- Besi Beton Ø8 0.86 360 309.60 M' 122.21 Kg
Berat Besi ( 0.395 kg/m') 122.21 Kg
- Bekisting 0.30 54.00 2 32.40 M2 32.40 M2

2 Kolom Beton Bertulang K1 (40x40 cm)


- Beton K-250 0.40 4.50 0.40 1 0.72 M3 0.72 M3
- Besi Beton Ø 16 4.50 12 54.00 M' 85.26 Kg
Berat Besi ( 1.579 kg/m') 85.26 Kg
- Besi Beton Ø8 1.54 23 34.65 M' 13.68 Kg
Berat Besi ( 0.395 kg/m') 13.68 Kg
- Bekisting 4.50 1.60 1 7.20 M2 7.20 M2

3 Balok Beton Bertulang B1 (20x40 cm)


- Beton K-250 0.20 0.40 54.00 1 4.32 M3 4.32 M3
- Besi Beton D16 54.00 9 486.00 M' 767.38 Kg
Berat Besi ( 1.579 kg/m') 767.38 Kg
- Besi Beton Ø8 1.06 360 381.60 M' 150.63 Kg
Berat Besi ( 0.395 kg/m') 150.63 Kg
- Bekisting 0.20 0.25 54.00 37.80 M2 37.80 M2

4 Balok Beton Bertulang B2 (15x35cm)


- Beton K-250 0.15 0.35 20.00 1 1.05 M3 1.05 M3
- Besi Beton D16 20.00 5 100.00 M' 157.90 Kg
Berat Besi ( 1.579 kg/m') 157.90 Kg
- Besi Beton D13 20.00 2 40.00 M' 41.69 Kg
Berat Besi ( 1.042 kg/m') 41.69 Kg
- Besi Beton Ø8 0.82 133 109.33 M' 43.16 Kg
Berat Besi ( 0.395 kg/m') 43.16 Kg
- Bekisting 0.15 0.20 20.00 11.00 M2 11.00 M2

III Plat Lantai Beton Bertulang Elv. + 3,50


- Beton K-250 0.12 80.00 9.60 M3 9.60 M3
- Wiremesh M8 479.50 Kg
M8 ( 61.790 kg/lbr)
Ukuran Per Lembar 2.10 5.40 11.34 M2
Jumlah Lembar yg dibutuhkan 7.05 Lbr
Overlap Sambungan 0.71 Lbr
7.76 Lbr
Berat Wiremesh 479.50 Kg

- Bekisting 80.00 M2 80.00 M2

IV Tangga Beton Bertulang


1 Pondasi Tangga Beton Bertulang
- Beton K-250 1.50 0.51 1 0.77 M3 0.77 M3
- Besi Beton D13 61.50 Kg
1.70 10 17.00 M'
3.00 4 12.00 M'
3.00 10 30.00 M'
59.00 M'
Berat Besi ( 1.042 kg/m') 61.50 Kg
- Bekisting 0.25 4.60 1.15 M2 5.53 M2
1.25 3.50 4.38 M2
5.53 M2
2 Balok Bordes Beton Bertulang Uk. 20x40 cm
- Beton K-250 0.20 0.40 4.90 1 0.39 M3 0.39 M3
- Besi Beton D16 4.90 9 44.10 M' 69.63 Kg
Berat Besi ( 1.579 kg/m') 69.63 Kg
- Besi Beton Ø8 1.06 33 34.63 M' 13.67 Kg
Berat Besi ( 0.395 kg/m') 13.67 Kg
- Bekisting 0.85 4.90 4.17 M2 4.17 M2
3 Plat Tangga & Bordes Beton Bertulang tbl. 15 cm
- Beton K-250 1.50 0.15 9.61 2.16 M3 2.16 M3
- Besi Beton D13
Memanjang 9.61 10 96.10 M' 350.60 Kg
Melintang 1.50 48 72.08 M'
168.18 M'
Jumlah 2 Lapis 336.35 M'
Berat Besi ( 1.042 kg/m') 350.60 Kg

- Bekisting 1.50 9.61 14.42 M2 14.42 M2

4 Anak Tangga Bertulang uk. 18 x 30 cm


- Beton K-250 1.50 0.03 20 0.81 M3 0.81 M3
- Besi Beton D13
Memanjang 1.50 20 30.00 M' 140.72 Kg
Melintang 0.70 150 105.00 M'
135.00 M'
Berat Besi ( 1.042 kg/m') 140.72 Kg

- Bekisting 0.20 1.50 20 6.00 M2 6.00 M2

PEKERJAAN PENUTUP LANTAI

Acian lantai Existing 912.61 M2


1 Pas. Lantai Parquet kayu Jati grade A 912.61 M2
27.90 29.90 834.21 M2
9.80 8.00 1 78.40 M2
912.61

2 Pas. Keramik Uk.40x40 (area tribun) 631.76 M2


10.60 29.80 2 631.76 M2
631.76 M2
2 Pas. Keramik Uk.40x40 Lantai Ruangan Bawah 187.33 M2
4.90 5.90 28.91
7.40 5.90 43.66
12.40 5.90 73.16
5.81 3.82 22.19
3.30 5.88 19.40
187.33

2 Pas. Keramik Uk.50x50 Motif Kayu 1.00 29.90 2 59.80 M2 59.80 M2

PEKERJAAN FINISHING
Acian lantai Existing Dibawah Parquet 912.61 M2
Pengecatan Lantai kayu/parquet 912.61 M2

Pengecatan Dinding 72.00 M2


1.20 30.00 1 36.00 M2
1.20 30.00 1 36.00 M2
72.00 M2
Pengecatan Lantai kayu/parquet

E PEKERJAAN KONSTRUKSI IPAL (PEKERJAAN SIPIL)

1 Galian tanah untuk anaerobic equalization 2.00 1.50 3.00 9.00 M3 9.00 M3
2 Galian tanah pondasi 0.50 0.75 15.00 5.63 M3 5.63 M3
3 Lantai kerja beton K-100 tbl. 5 cm 0.50 0.05 15.00 0.38 M3 0.38 M3
4 Pas. Batu Belah 1:3 0.40 0.50 15.00 3.00 M3 3.00 M3
5 Urugan Sirtu tbl. 15 cm 2.00 0.15 5.50 1.65 M3 1.65 M3
6 Lantai kerja dudukan biofilter beton K-100 tbl. 5 cm 2.00 0.05 5.50 0.55 M3
0.55 M3
7 Besi Beton D13 152.88 Kg
5.50 13 73.33 M'
2.00 37 73.33 M'
146.67 M'
Berat Besi ( 1.042 kg/m') 152.88 Kg
8 Cor Beton K-200 tbl. 15 cm 2.00 0.15 5.50 1.65 M3 1.65 M3
9 Bekisting 0.15 15.00 2.25 M2 2.25 M2
10 Pondasi Rabat Pas. Bata 1:3 13.26 M2
0.30 17.40 5.22 M2
0.30 26.80 8.04 M2
13.26 M2
11 Urugan Pasir bawah lantai Tbl 5 cm 0.05 31.64 1.58 M3 1.58 M3
12 Cor Lantai Beton cor K-175 Tbl. 5cm 0.05 31.64 1.58 M3 1.58 M3
13 Acian Lantai 31.64 31.64 M2 31.64 M2
14 Bak Indikator Pas. Bata 1:3 0.50 6.00 3.00 M2 3.00 M2
15 Plasteran Bak Indikator 1 : 3 tbl. 1,5 Cm 3.00 2 6.00 M2 6.00 M2
16 Acian Bak Indikator 6.00 M2
17 Pagar BRC T. 90 cm 26.80 M'
18 Tiang Pagar Pipa Galvanis Ø 2" 1.30 14 18.20 M' 18.20 M'
19 Pondasi Tiang Pagar Cor Beton K-175 uk. 20x20x40 cm 0.20 0.40 0.20 13 0.21 M3 0.21 M3
20 Awning Penutup Konstruksi IPAL 3.30 6.80 22.44 M2 22.44 M2

F PEKERJAAN SUMPIT (2 UNIT)

1 Galian tanah 2.40 1.80 2.40 2 20.74 M3 20.74 M3


2 Urugan pasir 2.40 0.05 2.40 2 0.58 M3 0.58 M3
3 Lantai kerja beton K-100 2.40 0.05 2.40 2 0.58 M3 0.58 M3
4 Beton K-200 9.30 M3
Lantai 2.00 0.20 2.00 2 1.60 M3
Dinding 0.20 1.85 9.60 2 7.10 M3
Penutup 2.00 0.15 2.00 1 0.60 M3
9.30 M3

5 Besi Beton D13 1,012.35 Kg


Dinding 8.80 37 325.60 M'
1.85 176 325.60 M'
Lantai 2.00 40 80.00 M'
2.00 40 80.00 M'
Penutup 2.00 40 80.00 M'
2.00 40 80.00 M'
971.20 M'
Berat Besi ( 1.042 kg/m') 1,012.35 Kg

6 Bekisting Dinding Dinding 1.90 9.60 2 36.48 M2 60.48 M2


1.50 8.00 2 24.00 M2
60.48 M2
7 Bekisting Plat Penutup Plat Penutup 2.00 2.00 2 8.00 M2 8.00 M2
8 Plat Besi Penutup Man Hole 0.72 M2
DAFTAR HARGA SATUAN UPAH, BAHAN DAN PERALATAN
KABUPATEN : MUARO JAMBI
TAHUN ANGGARAN : 2020

Harga Satuan
No. Uraian Satuan
(Rp.)
1 2 3 4

I HARGA TENAGA KERJA

1 Pekerja Org/hr 90,000.00


2 Tukang Org/hr 130,000.00
3 Kepala tukang Org/hr 145,000.00
4 Mandor Org/hr 135,000.00
5 Operator Org/hr 130,000.00
6 Pembantu Operator Org/hr 90,000.00

II HARGA BAHAN

BAHAN PASANGAN DAN URUGAN


1 Pasir beton M3 130,000.00
2 Pasir beton Kg 92.86
3 Pasir pasang M3 130,000.00
4 Pasir urug M3 130,000.00
5 Kerikil M3 450,000.00
6 Tanah urug biasa M3 80,000.00
7 Semen PC ( 50 Kg ) Zak 65,000.00
8 Semen PC ( 50 Kg ) Kg 1,300.00
9 Semen warna Kg 17,000.00
10 Batu kali/batu belah/batu gunung M3 350,000.00
11 Split (Gradasi bervariasi) M3 450,000.00
12 Split (Gradasi bervariasi) Kg 250.00
Sirtu M3 352,000.00
13 Air Ltr 121.00

BAHAN LANTAI
2 Keramik 25 x 25 cm Bh 4,250.00
3 Keramik 30 x 30 cm Bh 3,681.82
4 Keramik 25 x 40 cm Bh 6,500.00
5 Keramik 40 x 40 cm Bh 11,700.00
5 Keramik Kasar 40 x 40 cm Bh 15,000.00
6 Plint Keramik 10 x 40 cm Bh 2,925.00
7 Keramik 50 x 50 cm Bh 60,000.00
8 Granit 60 x 60 cm Bh 60,000.00
9 Plint Granit 10 x 60 cm Bh 10,000.00
9 Lantai kayu/Parquet M2 514,000.00
9 Lantai Vynil Bh 28,000.00
9 Wallpaper M1 40,000.00

BAHAN DINDING
1 Batu bata Bh 500.00

BAHAN PENUTUP LANGIT-LANGIT


3 GRC 4 mm Lbr 77,000.00
4 Gypsum board 9 mm Lbr 75,000.00
5 Tepung gypsum Kg 5,600.00
6 List profil gypsum M1 17,000.00
Harga Satuan
No. Uraian Satuan
(Rp.)
1 2 3 4

BAHAN PENUTUP ATAP


3 Seng gelombang BJLS 20, 6' Kodi 973,500.00
4 Seng gelombang BJLS 20, 6' Lbr 49,500.00

BAHAN KAYU
1 Kayu balok klas I M3 5,000,000.00
2 Kayu balok klas II M3 3,500,000.00
3 Kayu balok klas III M3 2,300,000.00
4 Kayu papan klas I M3 5,000,000.00
5 Kayu papan klas II M3 5,000,000.00
6 Kayu papan klas III M3 5,000,000.00
2 Plywood 9 mm Lbr 115,000.00
7 Dolken kayu Ø 8-10/400 Cm Btg 10,000.00

BAHAN BESI / BAJA


1 Besi beton kg 14,000.00
3 Kawat ikat beton kg 20,000.00
4 Besi Hollo 40.40.2 Btg 155,500.00
5 Besi Hollo 40.40.2 M' 25,916.67
6 Pipa Hollow 4x4 cm Rangka Plafond M2 150,000.00
7 Baja profil kg 21,900.00
9 Kawat Las Listrik kg 26,000.00
10 Paku biasa Kg 15,000.00
11 Paku triplek Kg 22,000.00
12 Paku sekrup Kg 55,000.00
13 Paku sekrup fixer bh 3,200.00
14 Paku seng Kg 44,000.00
15 Paku genteng Kg 33,000.00
6 Besi Jaring Kawat Baja (Wiremesh) M8 Lbr 748,000.00
7 Besi Jaring Kawat Baja (Wiremesh) M8 Kg 12,105.52

BAHAN AULMUNIUM
1 Profil Kusen Alumunium 4" M' 137,500.00
2 Profil Kusen Alumunium 3" M' 70,000.00
3 Bingkai Pintu Alumunium Putih M' 93,500.00
4 Bingkai Alumunium 3" M' 65,000.00
5 Sealant Tube 25,800.00
6 Engsel pintu Kaca (top/bottom hinge) Bh 55,000.00
7 Engsel pintu Kaca (Stainless) Bh 35,000.00
8 Handel Pintu Stainless Set 350,000.00
9 Handel Pintu Aluminium Set 45,000.00
10 Handel Pintu Biasa Set 75,000.00
11 Kunci Slot Tanam Bh 55,000.00
12 Pintu Aluminium Lengkap + Accessories Unit 1,750,000.00
13 Kunci pintu 2 slaag biasa Bh 120,800.00
14 Kunci tanam biasa Bh 175,000.00
15 Engsel pintu Bh 35,500.00
16 Engsel Jendela Bh 13,800.00
17 Grendel pintu Bh 25,000.00
18 Grendel Jendela Bh 7,400.00
19 Hak Angin Bh 31,000.00
20 Handel Jendela Bh 15,000.00
Harga Satuan
No. Uraian Satuan
(Rp.)
1 2 3 4

BAHAN SANITARI
1 Closet Duduk (setara America Standart Lengkap) Bh 2,500,000.00
2 Kloset Jongkok Bh 300,000.00
3 Wastapel type LW 526J lengkap dgn kran Unit 823,800.00
4 Wastapel type LW 200J lengkap dgn kran Unit 1,500,000.00
5 Isolatif Bh 4,400.00
6 Urinoir Bh 750,000.00
7 Kran Air, uk. 1/2 & 3/4 Bh 21,000.00
8 Shower Stainless std. Hotel Bh 5,500,000.00
9 Floor drain Bh 100,000.00
10 Bak cuci piring stinless Bh 220,000.00

BAHAN SALURAN AIR


1 Pipa PVC dia. 3/4" AW (4 m') Btg 22,400.00
2 Pipa PVC dia. 2" AW (4 m') Btg 81,000.00
3 Pipa PVC dia. 3" AW (4 m') Btg 155,000.00
4 Pipa PVC dia. 4" AW (4 m') Btg 210,000.00

BAHAN FINISHING
1 Cat tembok Setara Dulux Kg 25,000.00
2 Cat kayu Kg 62,000.00
3 Cat dasar tembok Kg 82,500.00
4 Cat dasar kayu Kg 36,000.00
5 Minyak cat Ltr 13,300.00
6 Minyak bekisting Ltr 8,700.00
7 Meni Kg 25,000.00
8 Plamir tembok Kg 20,000.00
9 Amplas Lbr 6,000.00
10 Lem kayu Kg 20,000.00
10 Lem Kuning Kg 65,000.00
10 Lem Wallpaper Kg 75,000.00
11 Kuas Bh 25,000.00
12 Waterprofing Cement Base M2 45,000.00
12 Ultran Parquet Lack UPL-77E set 273,000.00

BAHAN KACA
1 Kaca Polos 5 mm M2 95,000.00
2 Kaca Panasap tbl. 8 mm M2 325,000.00
3 Kaca Polos tbl. 12 mm M2 550,000.00
4 Kaca Tempered tbl. 12 mm M2 1,850,000.00
5 Sticker Sandblast M2 375,000.00
6 Vertical Blind M2 225,000.00
Kaca cermin Uk. 210 x 70 Cm Unit 1,200,000.00
Kaca cermin Uk. 50 x 100 Cm Unit 520,000.00

BAHAN LAIN
1 BBM Premium Ltr 7,095.00
2 BBM Solar (Non Subsidi) Ltr 10,780.00
3 Minyak Pelumas Ltr 31,600.00
4 Rangka ACP Besi Hollow 36x36x1,8 mm M2 344,250.00
5 Dinding ACP PVDF M2 803,250.00
6 Ornamen Teralis Besi Hollow 16x36x1,8 mm Finish Cat M2 907,500.00
7 Curtain Wall Kaca Oneway 5 mm Rangka Aluminium M2 1,980,000.00
8 Aluminium Louvers Coating White M2 990,000.00
Harga Satuan
No. Uraian Satuan
(Rp.)
1 2 3 4
9 Huruf Timbul Akrilik + Lampu LED & Rangka T. 100 cm Bh 3,630,000.00
10 Waterproofing Membrane Bakar Atap Dak M2 242,000.00
11 Gapura Pintu Lift Finish Marmer Unit 16,644,000.00
12 Awning Balkon Depan M2 850,000.00
13 Pagar BRC uk. 150cmx6mm M' 195,000.00
14 Pagar BRC uk. 90 cmx6mm M' 125,000.00

BAHAN PERALATAN SEWA


1 Stamper Hari 200,000.00
2 Molen Hari 250,000.00
3 Peralatan Bor M' 75,000.00

You might also like