CALENDARIO VALORIZADO

MEJORAMIENTO DE LOS SERVICIOS DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN EL AA HH JULIO LA ROSA DEL SECTOR DEL PAMPA DEL CARMEN DEL DISTRITO DE CHANCHAMAYO - PROVINCIA DE
PROYECTO: CHANCHAMAYO - DEPARTAMENTO DE JUNIN CUI 2412331
SUBPRESUPUESTO: PAVIMENTACION JULIO LA ROSA
CLIENTE: GOBIERNO REGIONAL DE JUNIN
UBICACION: LA MERCED,
FECHA BASE: 13-03-2023
MONEDA: SOLES

Item Partida Unidad Metrado PU Parcial 01-05-2023 01-06-2023 01-07-2023


1 OBRAS PRELIMINARES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD 55,834.51 55,109.71 724.80 0.00
1.1 OBRAS PROVISIONALES 7,834.82 7,834.82 0.00 0.00
1.1.1 OFICINA, ALMACÉN Y CASETA DE GUARDIANÍA MES 3.00 1,400.00 4,200.00 4,200.00 0.00 0.00
1.1.2 SERVICIOS HIGIÉNICOS PORTÁTILES MES 3.00 520.00 1,560.00 1,560.00 0.00 0.00
1.1.3 CARTEL DE OBRA 4.80 x 3.60 m UND 1.00 2,074.82 2,074.82 2,074.82 0.00 0.00
1.2 TRABAJOS PRELIMINARES 29,488.39 29,488.39 0.00 0.00
1.2.1 REUBICACIÓN DE POSTES DE CONCRETO GLB 10.00 1,400.00 14,000.00 14,000.00 0.00 0.00
1.2.2 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 1.00 4,000.00 4,000.00 4,000.00 0.00 0.00
1.2.3 MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL GLB 1.00 2,015.00 2,015.00 2,015.00 0.00 0.00
1.2.4 PLAN DE MONITOREO ARQUEOLOGICO GLB 1.00 6,000.00 6,000.00 6,000.00 0.00 0.00
1.2.5 NIVELACIÓN DE BUZONES EXISTENTES F'C = 210 KG/CM2 UND 4.00 203.25 813.00 813.00 0.00 0.00
1.2.6 DEMOLICION DE VEREDAS EXISTENTES M2 156.77 16.97 2,660.39 2,660.39 0.00 0.00
1.3 SEGURIDAD Y SALUD 18,511.30 17,786.50 724.80 0.00
1.3.1 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEG GLB 1.00 4,100.00 4,100.00 4,100.00 0.00 0.00
1.3.2 EQUIPO DE PROTECCION INDIVIDUAL UND 30.00 241.60 7,248.00 6,523.20 724.80 0.00
1.3.3 EQUIPOS DE PROTECCION COLECTIVA GLB 1.00 1,308.50 1,308.50 1,308.50 0.00 0.00
1.3.4 SEÑALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 1,031.20 1,031.20 1,031.20 0.00 0.00
1.3.5 CAPACITACITACION DE SEGURIDAD Y SALUD GLB 1.00 2,500.00 2,500.00 2,500.00 0.00 0.00
1.3.6 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SA GLB 1.00 2,323.60 2,323.60 2,323.60 0.00 0.00
2 PAVIMENTOS 497,890.12 154,335.12 343,555.00 0.00
2.1 PAVIMENTO RIGIDO 497,890.12 154,335.12 343,555.00 0.00
2.1.1 TRABAJOS PRELIMINARES 10,573.81 10,573.81 0.00 0.00
2.1.1.1 LIMPIEZA DE TERRENO MANUAL Y DESBROCE M2 3,119.12 0.53 1,653.13 1,653.13 0.00 0.00
2.1.1.2 TRAZO Y REPLANTEO PRELIMINAR M2 3,119.12 1.09 3,399.84 3,399.84 0.00 0.00
2.1.1.3 TRAZO Y REPLANTEO DURANTE EJECUCIÓN M2 3,119.12 1.77 5,520.84 5,520.84 0.00 0.00
2.1.2 MOVIMIENTO DE TIERRAS 143,761.31 143,761.31 0.00 0.00
2.1.2.1 CORTE CON MAQUINARIA EN TERRENO NATURAL M3 1,808.44 7.00 12,659.08 12,659.08 0.00 0.00
2.1.2.2 RELLENO CON MATERIAL PROPIO M3 58.05 36.61 2,125.21 2,125.21 0.00 0.00
2.1.2.3 ELIMINACION DE MATERIAL EXCEDENTE D>1KM <5 KM M3 2,187.99 9.11 19,932.59 19,932.59 0.00 0.00
2.1.2.4 PERFILADO Y COMPACTACION DE SUB-RASANTE EN ZONAS-CORTE M2 3,119.12 3.10 9,669.27 9,669.27 0.00 0.00
2.1.2.5 BASE GRANULAR E=0.20 m FACTOR COMPACTACION = 1.20 M2 3,119.12 31.86 99,375.16 99,375.16 0.00 0.00
2.1.3 LOSA DE CONCRETO 314,040.16 0.00 314,040.16 0.00
2.1.3.1 CONCRETO PREMEZCLADO F´C=210 KG/CM2 - PAVIMENTOS M3 623.82 430.78 268,729.18 0.00 268,729.18 0.00
2.1.3.2 ENCOFRADO Y DESENCOFRADO PARA PAVIMENTOS M2 587.81 64.19 37,731.52 0.00 37,731.52 0.00
2.1.3.3 CURADO DE CONCRETO M2 3,119.12 2.43 7,579.46 0.00 7,579.46 0.00
2.1.4 JUNTAS 29,514.84 0.00 29,514.84 0.00
2.1.4.1 JUNTAS DE DILATACION CON ASFALTO M 572.41 12.13 6,943.33 0.00 6,943.33 0.00
2.1.4.2 JUNTA DE CONTRACCIÓN e=1/2" M 1,094.00 5.62 6,148.28 0.00 6,148.28 0.00
2.1.4.3 DOWLLES ACERO LISO fy=4200 KG/CM2, GRADO 60 KG 1,934.42 8.49 16,423.23 0.00 16,423.23 0.00
3 VEREDAS, RAMPAS Y MARTILLOS 160,187.82 0.00 142,556.11 17,631.71
3.1 VEREDAS 128,955.68 0.00 125,375.90 3,579.78
3.1.1 TRABAJOS PRELIMINARES 2,890.88 0.00 2,890.88 0.00
3.1.1.1 TRAZO Y REPLANTEO DURANTE EL PROCESO M2 1,357.22 2.13 2,890.88 0.00 2,890.88 0.00
3.1.2 MOVIMIENTO DE TIERRAS 27,349.83 0.00 27,349.83 0.00
3.1.2.1 CORTE MANUAL EN MATERIAL SUELTO A NIVEL DE SUB RASANTE M3 203.58 45.00 9,161.10 0.00 9,161.10 0.00
3.1.2.2 ACARREO INTERNO DE MATERIAL M3 203.58 19.69 4,008.49 0.00 4,008.49 0.00
3.1.2.3 AFIRMADO PARA VEREDAS-BASE, COMPACTADO C/EQUIPO M3 135.72 87.40 11,861.93 0.00 11,861.93 0.00
3.1.2.4 ELIMINACION DE MATERIAL EXCEDENTE D>1KM <5 KM M3 254.48 9.11 2,318.31 0.00 2,318.31 0.00
3.1.3 VEREDAS DE CONCRETO 98,714.97 0.00 95,135.19 3,579.78
3.1.3.1 CONCRETO F'C=175KG/CM2 EN VEREDAS, INC. BRUÑADO A CADA 0.90m M3 203.58 421.37 85,782.50 0.00 85,782.50 0.00
3.1.3.2 ENCOFRADO Y DESENCOFRADO NORMAL EN VEREDAS M2 91.94 62.79 5,772.91 0.00 5,772.91 0.00
3.1.3.3 CURADO DE CONCRETO M2 1,357.22 2.43 3,298.04 0.00 1,649.02 1,649.02
3.1.3.4 RELLENO DE JUNTAS M 612.94 6.30 3,861.52 0.00 1,930.76 1,930.76
3.2 RAMPAS PEATONALES 5,810.87 0.00 5,810.87 0.00
3.2.1 CONCRETO F'C=175KG/CM2 EN RAMPAS PEATONALES, INC. BRUÑADO A M3 9.35 421.37 3,939.81 0.00 3,939.81 0.00
3.2.2 ENCOFRADO Y DESENCOFRADO NORMAL EN RAMPAS PEATONALES M2 29.36 58.57 1,719.62 0.00 1,719.62 0.00
3.2.3 CURADO DE CONCRETO M2 62.32 2.43 151.44 0.00 151.44 0.00
3.3 NIVELACIÓN DE CAJAS DOMICILIARIAS 10,982.00 0.00 10,982.00 0.00
3.3.1 NIVELACIÓN DE CAJAS DE AGUA Y DESAGÜE UND 85.00 129.20 10,982.00 0.00 10,982.00 0.00
3.4 MARTILLOS 14,439.27 0.00 387.34 14,051.93
3.4.1 TRABAJOS PRELIMINARES 387.34 0.00 387.34 0.00
3.4.1.1 TRAZO Y REPLANTEO DURANTE EL PROCESO M2 181.85 2.13 387.34 0.00 387.34 0.00
3.4.2 MOVIMIENTO DE TIERRAS 1,140.98 0.00 0.00 1,140.98
3.4.2.1 CORTE MANUAL EN MATERIAL SUELTO A NIVEL DE SUB RASANTE M3 27.28 30.90 842.95 0.00 0.00 842.95
3.4.2.2 ELIMINACION DE MATERIAL EXCEDENTE D>1 KM < 5 KM M3 34.10 8.74 298.03 0.00 0.00 298.03
3.4.3 MARTILLO DE CONCRETO 12,910.95 0.00 0.00 12,910.95
3.4.3.1 CONCRETO F'C=175KG/CM2 EN MARTILLO M3 25.02 421.37 10,542.68 0.00 0.00 10,542.68
3.4.3.2 ENCOFRADO Y DESENCOFRADO NORMAL EN MARTILLO M2 32.89 58.57 1,926.37 0.00 0.00 1,926.37
3.4.3.3 CURADO DE CONCRETO M2 181.85 2.43 441.90 0.00 0.00 441.90
4 ÁREAS VERDES 2,689.29 0.00 0.00 2,689.29
4.1 SEMBRÍO DE GRASS 966.04 0.00 0.00 966.04
4.1.1 SEMBRIO DE GRASS TIPO AMERICANO, INC. TIERRA DE CHACRA M2 57.40 16.83 966.04 0.00 0.00 966.04
4.2 SEMBRÍO DE PLANTAS Y ÁRBOLES 1,723.25 0.00 0.00 1,723.25
4.2.1 SEMBRÍO DE PLANTAS ORNAMENTALES DE LA ZONA UND 25.00 68.93 1,723.25 0.00 0.00 1,723.25
5 SARDINELES 101,899.32 6,327.40 95,571.92 0.00
5.1 TRABAJOS PRELIMINARES 415.69 415.69 0.00 0.00
5.1.1 TRAZO Y REPLANTEO DURANTE EL PROCESO M2 195.16 2.13 415.69 415.69 0.00 0.00
5.2 MOVIMIENTO DE TIERRAS 5,911.71 5,911.71 0.00 0.00
5.2.1 CORTE MANUAL EN MATERIAL SUELTO A NIVEL DE SUB RASANTE M3 107.34 44.15 4,739.06 4,739.06 0.00 0.00
5.2.2 ELIMINACION DE MATERIAL EXCEDENTE D>1 KM < 5 KM M3 134.17 8.74 1,172.65 1,172.65 0.00 0.00
5.3 SARDINELES DE CONCRETO 95,571.92 0.00 95,571.92 0.00
5.3.1 CONCRETO F'C=175KG/CM2 EN SARDINELES M3 107.34 421.37 45,229.86 0.00 45,229.86 0.00
5.3.2 ENCOFRADO Y DESENCOFRADO NORMAL EN SARDINELES M2 829.77 58.57 48,599.63 0.00 48,599.63 0.00
5.3.3 CURADO DE CONCRETO M2 195.16 2.43 474.24 0.00 474.24 0.00
5.3.4 RELLENO DE JUNTAS M 201.30 6.30 1,268.19 0.00 1,268.19 0.00
6 DRENAJE DE AGUAS PLUVIALES 348,419.24 0.00 0.00 348,419.24
6.1 CUNETAS 348,419.24 0.00 0.00 348,419.24
6.1.1 TRABAJOS PRELIMINARES 858.48 0.00 0.00 858.48
6.1.1.1 TRAZO Y REPLANTEO DURANTE EL PROCESO M2 403.04 2.13 858.48 0.00 0.00 858.48
6.1.2 MOVIMIENTO DE TIERRAS 7,254.90 0.00 0.00 7,254.90
6.1.2.1 EXCAVACION MANUAL PARA CUNETA M3 161.22 45.00 7,254.90 0.00 0.00 7,254.90
6.1.3 CONCRETO SIMPLE 340,305.86 0.00 0.00 340,305.86
6.1.3.1 CONCRETO F'C=175KG/CM2 EN CUNETAS M3 765.78 421.37 322,676.72 0.00 0.00 322,676.72
6.1.3.2 ENCOFRADO Y DESENCOFRADO NORMAL EN CUNETAS M2 269.04 58.57 15,757.67 0.00 0.00 15,757.67
6.1.3.3 CURADO DE CONCRETO M2 403.04 2.43 979.39 0.00 0.00 979.39
6.1.3.4 RELLENO DE JUNTAS M 141.60 6.30 892.08 0.00 0.00 892.08
7 ALCANTARILLA TIPO MARCO 26,535.28 12,898.51 13,636.77 0.00
7.1 TRABAJOS PRELIMINARES 84.99 84.99 0.00 0.00
7.1.1 TRAZO Y REPLANTEO DURANTE EL PROCESO M2 39.90 2.13 84.99 84.99 0.00 0.00
7.2 MOVIMIENTO DE TIERRAS 26,450.29 12,813.52 13,636.77 0.00
7.2.1 EXCAVACION MANUAL PARA ALCANTARILLA TIPO MARCO M3 4.81 45.00 216.45 216.45 0.00 0.00
7.2.2 CONCRETO SIMPLE 1,399.29 1,399.29 0.00 0.00
7.2.2.1 SOLADO DE E=0.075M M2 39.90 35.07 1,399.29 1,399.29 0.00 0.00
7.2.3 CONCRETO ARMADO 24,834.55 11,197.78 13,636.77 0.00
7.2.3.1 CONCRETO PREMEZCLADO F´C=210 KG/CM2 - ALCANTARILA TIPO MARC M3 13.94 430.78 6,005.07 0.00 6,005.07 0.00
7.2.3.2 ENCOFRADO Y DESENCOFRADO NORMAL EN ALCANTARILLA M2 64.98 58.57 3,805.88 3,805.88 0.00 0.00
7.2.3.3 ACERO CORRUGADO fy=4200 KG/CM2, GRADO 60 KG 2,177.29 6.79 14,783.80 7,391.90 7,391.90 0.00
7.2.3.4 CURADO DE CONCRETO M2 64.98 2.43 157.90 0.00 157.90 0.00
7.2.3.5 RELLENO DE JUNTAS M 13.00 6.30 81.90 0.00 81.90 0.00
8 SEÑALIZACIÓN Y SEGURIDAD VIAL 10,549.76 0.00 3,330.12 7,219.64
8.1 SEÑALIZACIÓN HORIZONTAL 7,219.64 0.00 0.00 7,219.64
8.1.1 MARCAS EN EL PAVIMENTO M2 138.90 14.31 1,987.66 0.00 0.00 1,987.66
8.1.2 LINEAS CONTINUAS Y DISCONTINUAS M 155.83 3.08 479.96 0.00 0.00 479.96
8.1.3 PINTURA DE SARDINEL M2 663.69 7.16 4,752.02 0.00 0.00 4,752.02
8.2 SEÑALIZACIÓN VERTICAL 3,330.12 0.00 3,330.12 0.00
8.2.1 SEÑALIZACION INFORMATIVA UND 6.00 555.02 3,330.12 0.00 3,330.12 0.00
9 PROTECCIÓN AMBIENTAL 16,681.00 6,550.00 0.00 10,131.00
9.1 MITIGACIÓN AMBIENTAL 4,300.00 4,300.00 0.00 0.00
9.1.1 PLAN DE MITIGACIÓN AMBIENTAL DURANTE OBRA GLB 1.00 2,500.00 2,500.00 2,500.00 0.00 0.00
9.1.2 PLAN DE MANEJO DE RESIDUOS SÓLIDOS GLB 1.00 1,800.00 1,800.00 1,800.00 0.00 0.00
9.2 MONITOREO AMBIENTAL DURANTE LA OBRA 2,250.00 2,250.00 0.00 0.00
9.2.1 MONITOREO AIRE RUIDO GLB 1.00 2,250.00 2,250.00 2,250.00 0.00 0.00
9.3 PROGRAMA DE ABANDONO DE OBRA 10,131.00 0.00 0.00 10,131.00
9.3.1 LIMPIEZA FINAL DE OBRA M2 5,335.52 0.39 2,080.85 0.00 0.00 2,080.85
9.3.2 TACHOS ECOLÓGICOS UND 15.00 480.01 7,200.15 0.00 0.00 7,200.15
9.3.3 PLACA RECORDATORIO DE OBRA UND 1.00 850.00 850.00 0.00 0.00 850.00
COSTO DIRECTO 1,220,686.34 235,220.74 599,374.72 386,090.88
GASTOS GENERALES 116,242.43 22,399.39 57,076.72 36,766.32
PRESUPUESTO DE OBRA 1,336,928.77 257,620.13 656,451.44 422,857.20
SUPERVISIÓN 53,475.00 10,304.39 26,257.00 16,913.61
GESTION DE PROYECTO 57,934.50 11,163.72 28,446.68 18,324.10
PRESUPUESTO DE OBRA + SUPERVISION 1,448,338.27 279,088.24 711,155.12 458,094.91
EXPEDIENTE TÉCNICO 28,500.00 5,491.82 13,993.91 9,014.26
LIQUIDACION 10,000.00 1,926.95 4,910.15 3,162.90
PRESUPUESTO TOTAL 1,486,838.27 286,507.01 730,059.18 470,272.07
19.270% 49.101% 31.629%