Professional Documents
Culture Documents
'
DETERMINATION
OF
GENERATOR INERTIA
' BY
J. L. Gordon, P. Eng.
Presented to.
Eastern Zone Meeting
Hydraulic Power Section
l. INrRODUCTION
This paper deals with some of the considerations necessary in the selec -
generating unit, so that the unit will perform satisfactorily under the
Several analysis of this problem have been made in the past, the most
notable being the NEMA publication No. HT-4-1958, from which the gen-
erator inertia may be selected depending on the _unit size and the length
• which shows in a simple form the experience gained from past installations •
2. COST OF INERTIA
•
costs have to be kept to a bare minimum, and since extra inertia invariably
adds cost to the project, a compromise must be reached wherein the iner-
• -2-
An illustration of the extra costs involved from adding inertia to the gen-
erator may be obtained from a common rule of thumb which states that the
inertia. If a large inertia increase is required, both the size and weight
crease in powerhouse area to accommodate the larger unit, and the in-
while the cost of adding inertia may, at first glance, appear to be low,
the actual cost, once all the factors have been taken into account, may
. 2. ~) I
l-t
N is the rpm
• from the governor,and using the rule that a 1% frequency change will
then the total Kilowatt - seconds in the flywheel effect of the generator
for 2 seconds, the load change would then be 10,000 KW seconds, or 10%
of the generator flywheel inertia. This will then give a frequency drop
60 cycle system.
flywheel effect are simply added together, since the speed of all units
• will rise or fall together with the system frequency. For example,
KVA with an H value of 2.5, the total flywheel effect would be 70,000 KW
seconds. A load drop of 3500 KW for 2 seconds would then produce a speed
rise of 5%.
The above simple formula neglects to take into account two of the major
factors affecting speed change, namely, governor time and inertia in the
For a given generator KVA rating, there would appear to be two means of
since, generally speaking, the higher the speed the lower ls the turbine
cost. Also, a higher unit speed usually reduces the normal inertia
• -4-
required for the KVA output, so that the product of inertia by speed
speeds (about 100 to 400 spin). Fig. 1 shows the value of the standard
Hence, for any one size of unit, the only method of increasing the inertia
• s.
design of t he powerhouse and its crane •
Advances in the design of generators over the years have produced units
factured, say 20 years ago. This has produced a unit which is admira -
bly suited for _insta llation in a large system, but somewhat lacking in
• The factors which must be taken into account when making this study are:
(a)
(b)
Size of the system to which the generator will be connected
• However, suf ficient ine r tia must be installed to keep the speed
the generator.
For small isolateg systems and even large systems with poor
with the inertia s tudy becoming more and more important as the
one cycle being the frequency band width during normal operation.
•
should be possib le to maintain frequency within a band width
since the smaller the desired band width, the greater the
required inertia and hence, the greater will be the cost of the
development.
the greater the water hammer and the greater will be the re-
•
is due to the fact that on a load rejection, water hammer will
Another factor which could limit the rate of gate closure is the
•
effect of negative water hammer in the draft tube. The wicket
of the draft tube water column. This, however, will only apply
• -8-
city, the governor time may be shortened for the same water
rejection.
give 50% water hammer and then determine the required inertia,
• -9-
•
shovels demand a heavy output over a short period of time,
toward s stability.
be encountered in practice.
the chart shown in Fig. 2 on which can be plotted most of the factors
l°/s
• where I° and
-
8 are the Allievi coefficients. and
Lp - length of penstock
• The higher this factor, the greater will be the effect of water hammer •
Normally, a value of0.4 is rarely exceeded since this will give about
• -11 -
In the calculation of water hammer, the length of the draft tube water
passage has been neglected, but the water velocity In the draft tube has
been included when estimating the average water velocity for t he whole
conduit. It has been found that this gives a more accurate resu lt than
inclusion of the draft tube length, justified by the fact that the
2 2
• W R " N
6
I• 6 " I O x t\P ,c Tc
where WR2 a inertia
N = rpm
H a Rated HP of unit
and is the amount of flywheel effect In the generator per horsepower per
governor time Te has been used, since the maximum water hammer is produced
down of the rate of movement of the wicket gates under partial load
changes. Usually, the total governor time is 1.0 to 1.6 seconds greater
The governor opening time has been selected because it ls often slower
than the closing time, a restriction imposed by either the draft tube,
• development s fall into three general areas. On the left hand side fall
units which have a very low inertia per horsepower per second of
governor opening time . These units operate on base load, several having
very long penstocks with slow governor times, others having relief valves
to alleviate the effects of water hammer. They are not used to control
In the center of the chart lie units which are connected to isolated
with the standard minimum inertia when three or more units are supplying
On the right lie the isolated units supplying mining loads, having
generators with extra inertia. These are the units for which a careful
• analysis of the inertia is required . If the load swings are large with
• -13-
units to have generators with 60% to 75% extra inertia over standard.
On this basis two lines may be drawn, separating the base load units,
system units and Iso l ated units. Since the chart has no allowance for
the type of load, it can be expected that some units will not fall Into
their r espective areas. For example, three isolated units are shown
in the area pertaining to system units. The reason for this is that
two of the units will only be subjected to small load changes, and hence,
•
several generators of the same size, and hence, is a borderline case,
indicating that they have more than adequate inertia. Many of these
units with large low head slow speed turbines, with large diameter
generators having a very high (normal) inertia, and others have hy-
• will move the plotted position of a unit towards the zero, crossing the
the lines separating the areas. Thus, an isolated unit with a governor
,
• -14-
seconds, appear in the area reserved for base load units, indicating
that control of the system frequency would not be adequate with the slow
governor time,
7. CONCLUS I ONS
Thus it is apparent that there are many factors which affect the deter-
istics of the development, to the size of the system and the nature of
•
the load. The use of the data on Fig, 2, should, since it is based on
• JLG/jh
• • • ' .
200
150
/
100 I /
/ / / /
/
/
/
90 / / / ., ./
80 / / / / ./ /
70 I / / / / /
I / / / / /
60
50
J / / / / /
40
E>:GPS
WR
ova< STMOA~
I I I / "
/ /
r--.. I
t/ ,./ . •✓ ,
"''
, ~
...,,
,-
---- 0~ ()
i---,oo
,. .
(,i
,
30
..I I I I II / /V
20
....
,.,. /
I; 1/ I;
11
. .,.
>
..
14
"
II
; 10
I I
I
I / /
; 9
8
I I I I / 5 6 T
~ I I I I J APPUCAIILE ONLY TO VERT1CAL HYOIIAUUC TURBINE
7
6
I I I / I ORIVEH SYNa<RONaJS GENERATORS,
5
I I J I ) I
4
I I I I I ,I UNIT START-1.P TIME
r, • Hx2·7 KVA
I /1
11P
/ J I
3
2 3 ..,
GENERATOR INERTIA CONSTANT H = 2·31xWfixN~ IO-IO G')
MVA ---
.
I • I ..
.
.• 0 .I .2 .4 7
·' ' lO II
" I L4 1.5 1• 17 1,
•
A
/.. I e " 0
,t
0
0
0 I
.,
<-
'
UNITS IN THIS RANG( CANNOT Pfl()\tlO[ AltY FA[OIJ!NCY lt<GOL ATIOW Ufft.E U.
Ft TTEO WITH RELl(F YA.I.VE$ ~RATING ON ,orH l.OAO-OF ANO LOAD-ON /
I
I fREO\lfNCY
"
" MT< I N THI$ ••••• • ..., ••
IIIEGUL TIC)N Off UltGf
ri 0 /
0
0
El
rn
..
'
t WAJUt WASTING ) ·1 SYSTEMS ONLY
i-!-I"' I
rn
I
G
>
II
"' "' 0 I I
I
.. .2
A j ~
,. 0
II I ·2
~~
j'~
+
"
..J
Q
' I I I')
I')
/
0
. 1/ I')
"' e
"'
I 1 .... ~ IN T14S RANGE Wl\.L PflOVtOE QO()Q • G'" AT...,...
IN ISOLAT£ 0 OP(ltATf()frl ~ $Y5T(M OPUAT N
a, ,.
A
J
A
I I
0
0
' .2 • • ,.o
.. I. I 1,2
0
0
•
,., ,
LEGEND
.
ISOLATED UNITS
SYSE:M UNITS
"
8AS£ U)AO SYSTEM UNl'l'S
1.6
'·' 1•
0