KEY TASK LIST WITH COST

TASK WORK PLACE RESOURCE DUR COST


DESIGN AND MATERIAL
TASK 1 DESIGNER AND MATERIAL - 1D RM 600.0
ORDER
MATERIAL
TASK 2 SAND FOR CASTING PAG 2D RM 800.0

TASK 3 ALUMINUM FOR CASTING TH 4D RM 500.0

TASK 3 BEARING BJH 2D RM 300.0

MANUFACTURE WORKERS
TASK 4 WATER PUMP HOUSING IN- - 2D RM 160.0
CHARGE
TASK 5 WATER PUMP TURBINE IN- - 2D RM 160.0
CHARGE
TASK 6 WATER PUMP SHAFT IN- - 3D RM 240.0
CHARGE
TASK 7 FINISHING PROCESS IN- - 2D RM 80.0
CHARGE
TASK 8 ASSEMBLY PROCESS IN- - 3D RM 240.0
CHARGE
QUALITY CONTROL WORKERS
TASK 9 PERSON INCHARGE - 2D RM 160.0

MACHINE MAINTAINANCE
TASK ALL MACHINE - 18D RM
10 2,000.0
INDIRECT COST
TASK ELECTRIC TNB 18D RM1,300.0
11
TASK WATER SATU 18D RM 300.0
12
TASK DAILY USE WIFI/TELCO 18D RM 100.00
13
TASK DELIVERY AND DAILY USE TRANSPORT 18D RM 400.0
14