POINT TO POINT INTERNET – PROJECT PROPOSAL FOR BRGY.

SAN JOSE GERONA

I. RATIONALE

The said brgy. has no internet provider of any kind (PLDT, Converge, etc.). What residents
usually use are prepaid mobile data wherein this mode is costly and is usually prone to poor
internet connection than the previously mentioned.

Point-to-point system also known as P2P is the most convenient and cost-effective way to
provide internet access. Point-to-point protocol over Ethernet allows users to avoid special
support from usual internet service providers while enjoying minimal equipment requirement.
Private individuals are currently the ones providing this kind of internet service. Users merely
require a router, at least two devices and an Ethernet cable. This internet provider can also
accommodate several devices at ones. P2P is a safe and a secure provider which will be
appreciated by the people of San Jose since this will be the first internet service provider in the
said area.

Point-to-point networks provide a variety of benefits which include the following:

1. Speed – P2P networks can transport large volumes of information instantly over a secure
network.
2. Security – Due to limited user accessibility, information shared over P2P remains secure.
3. Accessibility – dedicated private lines remain connected at all times.

The initial target clientele of this project is 30 or more households in barangay San jose Gerona
where a monthly payment for the service will be collected.

Below is a proposed Megabits Per Second (MBPS) plan per client:

DATA PLAN (per MBPS) MONTHLY BILL


5 mbps P 800.00
10 mbps P 1,000.00
15 mbps P 1,300.00
*installation fee of each client is P 2,500.00 – P 3,000.00, depending on the type of antenna and
Pipe to be used

II. ESTIMATED COST OF PROJECT

40FT TOWER

ITEM QUANTITY ESTIMATED COST


GI PIPE EAGLE SIZE 2” 2 pieces PHP 3400.00
GI WIRE SIZE 8” 1 roll PHP 2,400.00
TURNBUCKLE SIZE 16mm” 32 pieces PHP 4480.00
HIGH CARBON TORNILYO 5/8 8 pieces PHP 520.00
STEEL BAR 10mm 4 pieces PHP 572.00
STEEL BAR 12mm 4 pieces PHP 640.00
WELDING ROD 2.5 kilos PHP 300.00
CUTTING DICS 6 pieces PHP 210.00
Fabrication of tower and Welder PHP 2,000.00
welding cost
Construction of tower Helper/aakyat ng tower PHP 1000/10 feet

Grand Total P 18,522.00

BACKHAUL AND 1 ACCESS POINT ANTENNA

ITEM QUANTITY ESTIMATED COST


PowerBeam 5AC Gen2 2 PHP 17,000
LAP GPS 2 UP TO 20 to 25 PHP 13,000
SUBSCRIBERS
Lightning Arrester 1 PHP 8,000
UBNT Tough Cable CAT5e 1 PHP 9,500.00

Grand Total P 47,500.00

POINT TO POINT CLIENT’S ANTENNA

ITEM QUANTITY ESTIMATED COST


LiteBeam AC GEN2 10 PHP 40,000.00
Router TP-link 10 PHP 9,500.00
CAT6 Outdoor UTP 1 PHP 3,000.00
Pipe ¾ S-20 10 PHP 4,000.00
GI Wire s16 10kilos PHP 850.00
Electric tape 3 PHP 150.00
RJ45 100 PHP 425.00
Grand Total P 57,925.00

INSTALATION TEAM

ITEM QUANTITY ESTIMATED COST


Installer’s fee 3 persons P 200.00/client
Gas and food allowance of Per day N/A
installer’s team

III. PROJECTED INCOME

ESTIMATED NUMBER MBPS PLAN PER COST GROSS INCOME PER


OF CLIENTS CLIENT MONTH
0 5 MBPS P 800.00
8 10 MBPS P 1,000.00 P 8,000.00
7 15 MBPS P 1,300.00 P 9,100.00
Grand Total P 17,100.00
*This is based on estimation of 15 clients. Income may increase as clients increases.

IV. PROJECTED MONTHLY EXPENSES


ITEM QUANTITY ESTIMATED COST
Internet 1 N/A
Electric/place cost 1 P 2,000.00
Grand Total P 2,000.00

V. ESTIMATED RETURN OF EXPENSES

NUMBER OF CLIENTS EXPECTED MONTHLY EXPECTED MONTHLY EXPECTED NET


EXPENSES INCOME INCOME PER
MONTH
15 clients P 2,000.00 P 17,100.00 P 15,100.00
***Target ROI is 1 year. Note – Based on 15 clients in barangay. San Jose Gerona