Professional Documents
Culture Documents
-and-
WITNESSETH that:
ARTICLE I
SCOPE OF MATERIALS AND WORKS
I.1. The SECOND PARTY agrees to supply to the FIRST PARTY the materials
and provide the labor installation thereof in strict accordance with the
specifications below:
I.2. The SECOND PARTY agrees to supply to the FIRST PARTY the
incidental service of installation of the mentioned materials and other
services necessary for its completion;
I.3. The PARTIES agree that the consideration involved in this contract is
inclusive of any contingent price increase of materials unless the
PARTIES subsequently agree in writing to amend the contract price to
accommodate price hikes;
I.4. The PARTIES have agreed that the quantities may vary based on
measurements of actual, completed, and approved by the procuring
agency for billing purposes. Any works not authorized by the procuring
agency shall not be billable nor payable to the SECOND PARTY;
I.5. The SECOND PARTY shall use its basic tools, equipment, materials, and
RAQUEL MACARAT
manpower, all for the cost of the SECOND PARTY. In case the SECOND
R&M Metal
PARTY does Corporation
Archer not have all of the required tools, equipment, or materials,
he may lease from the FIRST PARTY at the rates agreed upon by the
PARTIES.
I.6. The scope covers the responsibility of the SECOND PARTY to shoulder
the expenses of basic first aid and health facilities and to maintain security
and order in the project site, in compliance with DPWH, DENR, DOH,
LGU, or government regulations while the barracks for the workers shall
be provided by the FIRST PARTY;
ARTICLE II
DURATION
II.1. The duration of this Contract is Sixty (60) Working Days from its
execution, subject to extension if there is an additional volume of work,
those granted by the FIRST PARTY, and/or if the site where the items of
work are not yet complete or is prevented by force majeure.
ARTICLE III
CONSIDERATION
IV.A.1 Payment will be made based on the progress of work done by the
SECOND PARTY who shall submit an accomplishment report and
progress billing to the FIRST PARTY. The report and billing shall be
subject to inspection and/or verification by the FIRST PARTY’s Project
Engineer and Inspectorate Team, for approval.
IV.A.2 The PARTIES agree that payment shall only be made once the FIRST
PARTY is satisfied that the progress and accomplishment billing are true
and correct.
B. MOBILIZATION FUND
IV.B.1. The FIRST PARTY shall allow the SECOND PARTY to avail of a THIRTY
Percent (30%) mobilization fund to be paid only when the materials have
been mobilized to the project site specified in the contract. The remaining
balance of the whole contract amount shall be collected through
accomplishment billings.
IV.B.2. If the down payment has not been repaid before taking over or before
termination of the contract, the whole of the balance shall immediately
RAQUEL
become dueMACARAT
and payable by the SECOND PARTY to the FIRST PARTY.
R&M Metal Archer Corporation
C. DEDUCTIBLE FROM ALL BILLING AND PAYMENT
IV.C.1. All payments of billing shall be subject to the mandatory TWO PERCENT
(2%) Withholding Tax;
IV.C.2. The FIRST PARTY shall deduct TEN PERCENT (10%) on the gross billed
amount as retention to guarantee all warranty undertakings of the
SECOND PARTY. The retention fund shall be released only upon
completion and acceptance by the procuring agency;
IV.C.3. The FIRST PARTY shall deduct TWENTY-FIVE (25%) PERCENT on the
gross billed amount, as recoupment to the mobilization fund paid in
advance to the SECOND PARTY. This shall be enforced in every
progress billing by the SECOND PARTY until the 15% mobilization fund is
fully paid.
ARTICLE V
DELIVERY
V.1. The materials shall be delivered to the Project Site in Bukidnon Sports
Complex, Laguitas, Bukidnon within the duration of the contract by the
SECOND PARTY.
Page 3 of 9
21K00278
Supply and Delivery of Materials
R&M Metal Archer Corporation
V.2. The cost of the delivery is deemed to be included in the contract price.
V.3. In the event of a breach of this Article, the FIRST PARTY reserves the
right to:
Engr. RODUARD MICHAEL C. BUSTILLO
a. Terminate this Contract without liability by giving an immediate
RFB Construction Corporation
notice and charge the SECOND PARTY with any loss incurred as
a result of the SECOND PARTY’s failure to make the delivery
within the time specified; or
b. Charge a penalty of 0.25% of the total contract price for every day
of delay or breach of the delivery schedule by the SECOND
PARTY; or
c. Give notice to the SECOND PARTY within five (5) days in case of
a mistake in the delivery and charge the variance of the prices to
the SECOND PARTY. The demobilization of the materials shall be
at the expense of the SECOND PARTY.
ARTICLE VI
INSPECTION AND ACCEPTANCE
A. GENERAL PROVISION
VI.A.1. The SECOND PARTY agrees that the FIRST PARTY’s payment under
this Contract shall not be deemed as an acceptance of any materials
delivered hereunder.
VI.A.2. The SECOND PARTY agrees that any acceptance by the FIRST PARTY
RAQUEL
does notMACARAT
release the SECOND PARTY from any warranty or other
obligations
R&M Metal Archer under this Contract.
Corporation
VI.A.3. Title to the materials and works shall pass to the FIRST PARTY when
they are delivered, inspected, and accepted by the FIRST PARTY. The
risk of loss, injury, or destruction of the materials shall be borne by the
SECOND PARTY until the title passes to the FIRST PARTY.
B. MATERIALS
VI.B.1. Acceptance of the delivered items shall be deemed to occur on the date
when, in the reasonable opinion of the FIRST PARTY, the delivered items
conform to the stipulated specification. The FIRST PARTY shall have
thirty (30) calendar days after proper receipt of the materials to inspect
them and either accept or reject them as non-conforming with this
Contract.
VI.B.2. The SECOND PARTY agrees that the final acceptance occurs when
FIRST PARTY executes and returns to the SECOND PARTY the signed
delivery receipt and/or acknowledgment receipt within thirty (30) calendar
days but only after the necessary inspection was conducted.
VI.B.3. All materials not found upon delivery shall be notified to the SECOND
PARTY within seven (7) days. No substitutions shall be made without
Page 4 of 9
21K00278
Supply and Delivery of Materials
R&M Metal Archer Corporation
prior authorization by the FIRST PARTY through its authorized technical
representatives.
VI.C.2 The parties agree that FIRST PARTY shall conduct a periodic inspection
at least twice a month to inspect the quality and program of works, for
billing, reconstruction, replacement, and other purposes.
ARTICLE VII
WARRANTY AGAINST NON-PERFORMANCE
VII.1 Non-performance arises when the SECOND PARTY fails to perform the
required works under this Contract;
VII.2 The SECOND PARTY shall be required to put up warranty security in the
form of SURETY BOND CALLABLE ON-DEMAND issued by any surety
or insurance or bonding company accredited by the Insurance
Commission and duly accepted by the FIRST PARTY. The amount of the
surety bond callable on-demand shall be equivalent to One Hundred
Percent (100%) of the Contract Price.
RAQUEL MACARAT
R&M Metal Archer Corporation
ARTICLE VIII
WARRANTY FOR WORKS AND MATERIALS
VIII.1. The SECOND PARTY shall guarantee that the work done will be by the
specification of the Project as required by the FIRST PARTY.
VIII.2. The warranty for the quality of equipment of the SECOND PARTY shall
extend to the period of TWELVE (12) months from the final acceptance
of the procuring agency. On top of the equipment warranty, the SECOND
PARTY shall extend a period of TWELVE (12) months for preventive
maintenance from the final acceptance of the procuring agency.
VIII.4. If any defects are found, the PARTIES obligate themselves to perform the
following:
Page 5 of 9
21K00278
Supply and Delivery of Materials
R&M Metal Archer Corporation
b. The SECOND PARTY shall repair or replace any of the alleged
defective work at its cost including all labor and materials;
ARTICLE IX
RESPONSIBILITIES TO MANPOWER
IX.1. The SECOND PARTY shall maintain at all times a sufficient number of
laborers and skilled workers, sufficient to meet the program of works that
the Procuring Agency has imposed in the contract.
IX.2. The SECOND PARTY shall, at all times during the terms of this Contract,
keep on the job site a competent superintendent to prosecute the work in
accordance with the drawings, specifications, and other instructions. The
superintendent shall act as an agent of the SECOND PARTY in its
absence and all formal instructions given to him shall be binding as if
given directly to the FIRST PARTY.
IX.5. The SECOND PARTY shall also be solely and exclusively responsible for
any death, injury, or damage caused to or by the personnel or agents of
the SECOND PARTY to any third person should the cause of such death,
damage, or injury be due to the fault or negligence of the SECOND
PARTY’s personnel or agents.
IX.6. The SECOND PARTY shall also be liable for any loss or damage to any
materials caused by mishandling of its employees or laborers, or for the
reason of lack of skill, care, and experience, the materials have to be
removed and replaced for reason that the work is substandard or the
quality failed to pass the design and quality.
ARTICLE X
LIQUIDATED DAMAGES
X.1. The SECOND PARTY shall pay the FIRST PARTY Liquidated Damages
equivalent to One Percent (1%) of the cost of the unfinished portion of the
Page 6 of 9
21K00278
Supply and Delivery of Materials
R&M Metal Archer Corporation
project for each day of delay in the completion of the project, but not to
exceed Ten (10%) percent of the contract price. The start of delay shall
be reckoned from the end of the duration of this contract. The Liquidated
Damages shall be automatically be deducted from the collectibles, should
there MICHAEL
Engr. RODUARD be any, of C.
theBUSTILLO
SECOND PARTY from the FIRST PARTY. In the
event the collectibles of the SECOND PARTY are insufficient to pay the
RFB Construction Corporation
liquidated damages, the SECOND PARTY shall be obligated to pay the
same through cash or the issuance of a check.
X.2. In the event the cumulative amount of Liquidated Damages due to the
SECOND PARTY reaches Fifteen Percent (15%) of the Contract Price,
the FIRST PARTY is automatically entitled to TERMINATE the Contract,
without prejudice to other courses of action and remedies the SECOND
PARTY may avail.
ARTICLE XI
TERMINATION OF CONTRACT
XI.1 The presence of any of the grounds enumerated hereunder shall entitle
the FIRST PARTY to terminate the contract:
XI.2 The FIRST PARTY may only exercise its right to terminate the contract
after giving a notarial notice of the existence of any of the grounds for
Termination to the SECOND PARTY without the need for judicial
recourse. In the said notice, the FIRST PARTY shall, in all instances, give
the SECOND PARTY sufficient opportunity to remove, remedy, or rectify,
if possible, said ground before effecting the Termination of the contract.
XI.3 Should the SECOND PARTY still fail to comply with its undertaking even
after receipt of the notice of the intended termination, the FIRST PARTY
may take over the works and/or secure the services of a third party to
undertake its obligations. The cost of completing the works shall be
shouldered by the SECOND PARTY.
ARTICLE XII
COMPLIANCE WITH LAWS
XII.1 Whenever applicable and/or binding upon the parties, the SECOND
PARTY, in the performance of its obligations, shall comply with all laws,
ordinances, decrees, rules, and regulations of both the national and local
governments.
ARTICLE XIII
SEPARABILITY CLAUSE AND ARBITRATION
Page 7 of 9
21K00278
Supply and Delivery of Materials
R&M Metal Archer Corporation
XIII.1 In case any one or more of the provisions contained in this Agreement will
be declared invalid, illegal, or unenforceable, the validity, legality, or
enforceability of the remaining provisions contained `herein, insofar as still
Engr. RODUARDconsistent with theC.declared
MICHAEL purposes of the parties, shall not in any way
BUSTILLO
be affected or impaired thereby.
RFB Construction Corporation
XIII.2 Any dispute or controversy of any kind whatsoever between the FIRST
PARTY and the SECOND PARTY which may arise out of or in connection
with this Agreement shall be referred to the proper courts in Butuan City,
Region XIII to the exclusion of other courts.
ARTICLE XIV
NON-WAIVER
XIV.1 The inaction or silence by any of the parties herein concerning non-
compliance by the other of their respective obligations shall not be
construed or interpreted as a waiver or consent by the aggrieved party of
said non-compliance.
XIV.2 The parties hereto further agree to execute and/or submit such other
documents and papers as may be deemed necessary to
realize/accomplish the purposes of this Agreement or necessary for its
approval.
RAQUEL
RodnetMACARAT
Builders Inc. R&M Metal Archer Corporation
R&M Metal Archer Corporation
First Party Second Party
By: By:
______________________________ _______________________________
RODUARD MICHAEL C. BUSTILLO RAQUEL MACARAT
____________________________ ___________________________
Page 8 of 9
21K00278
Supply and Delivery of Materials
R&M Metal Archer Corporation
Engr. RODUARD MICHAEL C.A BUSTILLO
CKNOWLEDGMENT
RFB Construction Corporation
REPUBLIC OF THE PHILIPPINES )
In the City of BUTUAN . . . . . . . . . . . ) S.S.
BEFORE ME, a Notary Public for and in the city of Butuan, this ___th day
of ___________ 2022, personally appeared:
Raquel Macarat
This instrument, consisting of nine (9) pages including this page wherein
this acknowledgment has been signed by the parties and their instrumental
witness on each and every page thereof.
WITNESS MY HAND AND SEAL on the page and at the place first above
RAQUEL MACARAT
written.
R&M Metal Archer Corporation
NOTARY PUBLIC
Page No. _______;
Doc. No. _______;
Book No. _______;
Series of 2022
Page 9 of 9
21K00278
Supply and Delivery of Materials
R&M Metal Archer Corporation