Professional Documents
Culture Documents
Details
Description Test
Date / time: 15.03.2019
Location Tondela (Portugal) ; Soria (Spain)
Attachments
Follow-up Meeting
Date / time:
Location
Responsable
After process MRP we should have to analyse MRP results and exceptions messages ( see MD06
document)
Launching MRP
1) Automatic
MRP process can be carry out as automatic process (JOB) scheduled as certain date or period.
- We could carry out whole plant parts
- We can create variants of the process in order to select by grouping ( BOM levels, MRP
controller...)
2) Manual
Manual execution transations , explained bellow: MD01, MD02, MD03
- All parts plant or grouping parts (exit fields)
- Single item single level BOM
- Single item multilevel BOM explosion
2. MRP TRANSTIONS
Direct: /nMD01
Full : Logistics / Materials Management / Material Requirements Planning
(MRP) / MRP / Planning / Total Planning/ online.
This transacction is part of the taskchain process ( first MRP or MPS) and the second one
( Purchase process)
Parameters control
Optional parameters :
Select materials by MRP controler or MRP group ( material master data) in order to the MRP
process the materials which below
- Put User exit key: MRP
- Put user parameters : code of MRP controler in the master data
The system will be carry out MRP for those materials which cointain this MRP in the master data
MRP1 view.
Direct: /nMD02
Full : Logistics / Materials Management / Material Requirements Planning
(MRP) / MRP / Total Planning / Multilevel single item
Only the MRP affects to this material and the rest of partnumbers in their BOM explosion
levels
Direct: /nMD03
Full : Logistics / Materials Management / Material Requirements Planning
(MRP) / MRP / Total Planning / Single level single item
3. MASTER DATA
The most important lote size are the Periodics : PB/TB/WB/W1/W2 where the system groups several
requirements within a time interval ( daily / weekly / Monthly)
TB
Daily lote size
Requirements Date from PP order/Sales order = Delivery date for Purchasing
PB
Period lot size = posting period
PK
Period lot size base in planning calender
MB
Monthly lote size
The system groups several requirements within Month. Lot Delivery date for Purchasing at the
begining of the the month
W2
W1
Weekly lote size
Delivery date for Purchasing at the begining of the week
WB
Weekly lote size
Requirements Date from PP order/ Sales order = Delivery date for Purchasing
H1
Replen to max stck after covering reqs
Replenish to maximum stock level
2W
2 Weeks lote size
Delivery date for Purchasing at the begining of the first week
DY Consumption-Based Planning
Dynamic lot size creation in the Lot size field and the Lot size independent costs and storage costs
indicator. Starting from the shortage date, successive requirements are grouped together to form lots
until additional storage costs become greater than lot size independent costs
Result:
When a planned order it’s changed manually the system automatically assumed it as a firm and later
the MRP process will never change it.
Note: Production orders always are fix under the point of view of the MRP process.
click modify
After planned order modification (date/ qauntity ) you will see the option activated
We can get a firm schedule (*) lines through the trade-off zone during the labour days you put in
there. But you can not avoid to get new Schedule lines in this period. To solve this one: binding field.
In the "Firm Zone" field, enter the number of calendar days (calculated from the SA release creation
date) after which the firm zone ends and the offset zone begins.
In this example vendor schedule lines are fixed during 20 labour days from the beginning.