PERT 1) The data relating to a small project cor isting of 11 activities is given below: Activity, Optimistic Time (a) | Most Likely Time Pessimistic Time (m) (b) 1-2 A 1 2 3 1-3 B 1 2 3 1-4 c 1 2 3 2-5 D 4 9 20 3-5 E 2 5 14) 3-8 F 3 6 1s 4-7 G 1 2 9. 4-8 H 2 3 10 5-8 1 1 2 9 7-8 J _ 4 7 8-9 K 4 4 4 'dentify critical activities & determine the critical path|& compute the expected time of completion of the project. > Determine the completion of the projéct in 20 weeks 2. Aproject has the following activities as given in the below table : Activity Predecessor To Tm Tp A a 7 16 B si 5 15 cl A 6 W 30. D A 2 3 8 E c 5 a 7 F D 3 6 15 G B 3 9 27 HW EF 1 4 = i 7 G 4 19 28 Draw the P.E.R.T. network. Identify the Critical Path, Determine the Mean Project Completion Times, Find the probability that the project is completed in 36 weeks. lf the project Manager wishes to be 99% days should be provided for the project? 3. Consider the project, details of which are in the below table: Sure that the project is completed, how many Predecessor ‘Most Likely Pessimistic 5 8 1 8 5 g 4 2/-|-]-]=|=]o]>]Jolaje>, IB LKL i. Drawa network with AOA convention. ‘Compute the expected project completion time. How many days should be provided for 80% project completion’ probability? Find the probability that the project is completed in47 days) vl you wish to be 95% sure that the\project is completed, how many days should be Provided for the project work? vi. _What is the outcome ifthe Activity |is removed from the above Project. A team of chemists is planning to, undertake an applied research project to test a formula for a Tew material. The project.can be separated into 12 distinct activities. The relationship amongst the activities and the time estimates in weeks are as given below: Activity Predecessor S]gle[xle cD E cD GH F LK [c/o] a]o]o)olala|slolely Draw @ network and identify the expected completion time of the project. What 1s the ability of completing the project in 25 weeks? What is the probability of completing the project in less than or equal to 23 weeks? What is the probability of completing the project in pr more than or equal to 26 weeks? What is the time estimate for project completion at 95% confidence level? The Taco Iron & Steel Company is expanding its operations in Maharashtra to include a new drive-in weigh station. The weigh station will be a heated / air-conditioned building with a large floor and small office. The large room will have the scales, a 1.5 foot counter, and several display cases for its equipment, Before erection of the building, the project manager evaluated the project using PERT / CPM analysis. The activities with their corresponding times were recorded in the table below: (MAY 2018 Q 5 ~ 10 Marks) Most Precede Activity | Description Optimistic | Pessimistic | Likely | Task A_| Lay Foundation 6 30 iz None | 8 _| Dighole for scale 4 28 20 | G.None C_| insert scale bases 2 cole 2H 8 D__| Erect frame 4 16 10] AC E__| Complete bldg 10 34 22 D F__| insert scales 66, 66 66 E G__| insert display cases 6 5h 18 E H__| Put inoffice equip. 2 Se, 8 6 1__| Finishing touches 8 O56 38 EH a) Determine critical path anid project duration. b) Determine free floats for all activities. €) Determine the project duration 8 that project completion probability will be 85%. 6. A project consisting of Z,activities has the following relevant information: (All durations are in weeks) (Nov2018 Q 1a -10 Marks) S Most Retivity, | Optimistic | Likely Pessimistic a2 1 1 7 13 1 4 7 X ce) 2 2 8 % [25 1 a 1 35, 2 5 4 46 2 5 8 56 3 6 35 i. Draw the network and find Critical Path & Critical Time of the project. Compute the floats. i. What is the probability that the project will be extended to 20 weeks? Following table lists the various details of project activities. (Nov 2019 ~ Qi (a) ~ Marks 10) qv. Activity Predecessor Duration in weeks te tm ie A Nil 13 2 25 8 Nil 19 20 27 c Nil 7 5 a : A = 14 | 35 é 2 7 8 27 c 7 3 4 Pas s ce 5 r 12 a 7 5 eb 14 23 ; £6 5 8 7 ; be 2. 16 Poa “ ge Draw the network and find the critical path and critical time of the project. Compute total float for all activities. ° Find the probability that the project will be completed in 60 weeks. Zvalue . pasos ‘Area under normalcurve 0 0.1985 2650 -MS-2519-11 eraTistical TAGES (0.4875 of 103 Areas under the Standard Normal probability Distelbutlon between the Mean and Positive Values of t 0.04 0.05 0.08 0,09 gore | 00319 -0,035° orzo 0.0160, 0.0187. Coss 0.5%s| 0.0636 9.0674 o7l4. 00753. Goeao 0.0907 0.1028 O.1}oaON1 AT oni, 0.133! Sada 0.1480 OW1S17 iss, otset 0.1620 O.18tS 0.1700. Sid0s oz01e 0.2054 0.2387 * 0.2704 p.2005 0137264 0.3508, 9.3720 0.3925 0.4099" 0.425 0.4387 oases 04st 0.4671 04738 0.4793 « 0.4838 0.4075, 0.4904 0.4027 * 0.4945 0.4059" 0.4989 * 0.4077 « 0.4904 0.4985 eoeeegsoeeen oe |G eeoecs 29 s eo $8.\2 38 [8 cae 288 |e 288 |o geo 288 (8 oe 288 |

You might also like