Objective and Process of Post-qualification. Under any of the above instances, the
- Post-qualification is the stage where the contract shall be re-advertised and re-bid.
bidder with the Lowest Calculated Bid, in
the case of Goods and Infrastructure The BAC shall observe the same process and
Projects, or the Highest Rated Bid, in the set the new periods according to the same
case of Consulting Services, undergoes rules followed during the first bidding. After
verification and validation whether he has the second failed bidding, however, the BAC
passed all the requirements and conditions may resort to negotiated procurement as
as specified in the Bidding Documents. provided for in Section 53 of this Act.
If the bidder with the Lowest Calculated Bid Single Calculate/Rated and Responsive Bid
or Highest Rated Bid passes all the criteria Submission. - A single calculated/rated and
for post-qualification, his Bid shall be responsive bid shall be considered for award
considered the "Lowest Calculated if it falls under of the following
Responsive Bid," in the case of Goods and circumstances:
Infrastructure or the "Highest Rated
Responsive Bid," in the case of Consulting a. If after advertisement, only one
Services. However, if a bidder fails to meet prospective bidder submits a Letter of
any of the requirements or conditions, he Intent and/or applies for eligibility check,
shall be "post-disqualified" and the BAC and meets the eligibility requirements or
shall conduct the post-qualification on the criteria, after which it submits a bide, which
bidder with the second Lowest Calculate Bid is found to be responsive to the bidding
or Highest Rated Bid. If the bidder with the requirements;
second Lowest Calculated Bid or Highest b. If after the advertisement, more than one
Rated Bid is post-disqualified, the same prospective bidder applies for eligibility
procedure shall be repeated until the check, but only one bidder meets the
Lowest Calculated Responsive Bid or Highest eligibility requirements or criteria, after
Rated Responsive Bid is finally determined. which in submits a bid which is found to be
responsive to the bidding requirements; or
In all cases, the contract shall be awarded c. If after the eligibility check, more than
only to the bidder with the Lowest one bidder meets the eligibility
Calculated Responsive Bid or Highest Rated requirements, but only one bidder submits
Responsive Bid. a bid, and its bid is found to be responsive
to the bidding requirements.
Failure of Bidding. - there shall be a failure
of bidding if: In all instances, the Procuring Entity shall
a. No bids are received; ensure that the ABC reflects the most
advantageous prevailing price for the
government. Period of Action on Procurement Activities.
AWARD, IMPLEMENTATION AND - The procurement process from the
TERMINATION OF THE CONTRACT opening of bids up to the award of contract
shall not exceed three (3) months, or a
Notice and Executive of Award. - Within a sho0rter period to be determined by the
period not exceeding fifteen (15) calendar procuring entity concerned. Without
days from the determination and prejudice to the provisions of the preceding
declaration by the BAC of the Lowest section, the different procurement activities
Calculated Responsive Bid or Highest Rated shall be completed within reasonable
Responsive Bid, and the recommendation of periods to be specified in the IRR.
the award, the Head of the Procuring Entity
or his duly authorized representative shall If no action on the contract is taken by the
approve or disapprove the said head of the procuring entity or by his duly
recommendation. In case of approval, the authorized representative, or by the
Head of the Procuring Entity or his duly concerned board, in the case of
authorized representative shall immediately government-owned and/or -controlled
issue the Notice of Award to the bidder with corporations, within the periods specified in
the Lowest Calculated Responsive Bid or the preceding paragraph, the contract
Highest Rated Responsive Bid. concerned shall be deemed approved.
Within ten (10) calendar days from receipt Performing Security. - Prior to the signing of
of the Notice of Award, the Winning bidder the contract, the winning bidder shall, as a
shall formally enter into contract with the measure of guarantee for the faithful
Procuring Entity. When further approval of performance of an compliance with his
higher authority is required, the approving obligations under the contract prepared in
authority for the contracts shall be given a accordance with the Bidding Documents, be
maximum of twenty (20) calendar days to required to post a performance security in
approve or disapprove it. such form and amount as specified in the
Bidding Documents.
In the case of government-owned and/or -
controlled corporations, the concerned Failure to Enter into Contract and Post
board shall take action on the said Performance Security. - If, for justifiable
recommendation within thirty (30) calendar causes, the bidder with the Lowest
days from receipt thereof. Calculated Responsive Bid or Highest Rated
Responsive Bid fails, refuses or is otherwise
The Procuring Entity shall issue the Notice unable to enter into contract with the
to Proceed to the winning bidder not later Procuring Entity, or if the bidder fails to post
than seven (7) calendar days from the date the required performance security within
of approval of the contract by the the period stipulated in the Bidding
appropriate authority. All notices called for Documents, the BAC shall disqualify the said
by the terms of the contract shall be bidder and shall undertake post-
effective only at the time of receipt thereof qualification for the next-ranked Lowest
by the contractor. Calculated Bid or Highest Rated Bid. This
procedure shall be repeated until an award DISCLOSURE OF RELATIONS.
is made. However, if no award is possible,
the contract shall be subjected to a new In addition to the proposed contents of the
bidding. Invitation to Bid, all bidding documents shall
be accompanied by a sworn affidavit of the
In the case of a failure to post the required bidder that he or she or any officer of their
performance security, the bid security shall corporation in not related to the Head of
be forfeited without prejudice to the the Procuring Entity by consanguinity or
imposition of sanctions prescribed under affinity up to the third civil degree.
Article XXIII.
Failure to comply with the aforementioned
Reservation Clause. - The Head of the provision shall be a ground for the
Agency reserves the right to reject any and automatic disqualification of the bid.
all Bids, declare a failure of bidding, or not
award the contract in the following ALTERNATIVE METHODS OF
situations: PROCUREMENT