You are on page 1of 11

GOVERNMENT PROCUREMENT REFORM performed strictly according to

ACT (R.A. 9184) specifications.

GOVERNING PRINCIPLES ON SCOPE AND APPLICATION.- 


GOVERNMENT PROCUREMENT.
RA 9184 shall apply to the Procurement of
All procurement of the national Infrastructure Projects, Goods and
government, its departments, bureaus, Consulting Services, regardless of source of
offices and agencies, including state funds, whether local of foreign, by all
universities and colleges, government - branches and instrumentalities of
owned and/or-controlled corporations, government, its departments, offices and
government financial institutions and local agencies, including government-owned
government units, shall, in all cases, be and/or-controlled corporations and local
governed by these principles: government units, subject to the provisions
of Commonwealth Act No. 138.
(a) Transparency in the procurement
process and in the implementation of Any treaty or international or executive
procurement contracts. agreement affecting the subject matter of
(b) Competitiveness by extending equal this Act to which the Philippine government
opportunity to enable private contracting is signatory shall be observed.
parties who are eligible and qualified to
participate in public bidding. DEFINITION OF TERMS.- 
(c) Streamlined procurement process that
will uniformly apply to all government (a) Approved Budget for the Contract (ABC)
procurement. The procurement process - refers to the budget for the contract duly
shall simple and made adaptable to approved by the Head of the Procuring
advances in modern technology in order to Entity, as provided for in the General
ensure an effective and efficient method. Appropriations Act and/or continuing
(d) System of accountability where both the appropriations, in the National Government
public officials directly or indirectly involved Agencies; the Corporate Budget for the
in the procurement process as well as in the contract approved by the governing Boards,
implementation of procurement contracts pursuant to E.O.No.518, series of 1979, in
and the private parties that deal with the case of Government Financial
government are, when warranted by Institutions and State Universities and
circumstances, investigated and held liable Colleges; and the Budget for the contract
for their actions relative thereto. approved by the respective Sanggunian, in
(e) Public monitoring of the procurement the case of Local Government Units.
process and the implementation of awarded
contracts with the end in view of (b) BAC - refers to the Bids and Awards
guaranteeing that these contracts are Committee established in accordance with
awarded pursuant to the provisions of this Article V of this Act.
Act and its implementing rules and
regulations, and that all these contracts are (c) Bidding Documents - refer to documents
issued by the Procuring Entity as the basis
for Bids, furnishing all information businesses or in the pursuit of any
necessary for a prospective bidder to government undertaking, project or activity,
prepare a bid for the Goods, Infrastructure whether in the nature of equipment,
Projects, and Consulting Services to be furniture, stationery, materials for
provided. construction, or personal property of any
kind, including non - personal or contractual
(d) Bid - refers to signed offer or proposal services such as the repair and maintenance
submitted by a supplier, manufacturer, of equipment and furniture, as well as
distributor, contractor or consultant in trucking, hauling, janitorial, security, and
response to the Bidding Documents. related or analogous services, as well as
procurement of materials and supplies
(e) Competitive Bidding - refers to a method provided by the procuring entity or such
of procurement which is open to services.
participation by any interested party and
which consist of the following processes: (i) GPPB - refers to the Government
advertisement, pre-bid conference, Procurement Policy Board established in
eligibility screening of bids, evaluations of accordance with Article X of this Act.
bids, post - qualification, and award of
contract, the specific requirements and (j) Head of the Procuring Entity- refers to: (I)
mechanics of which shall be defined in the the head of the agency or his duly
IRR to be promulgated under this Act. authorized official, for national government
agencies; (ii) the governing board or its duly
(f) Consulting Services - refer to services for authorized official, for government-owned
Infrastructure Projects and other types of and/or-controlled corporations; or (iii) the
projects or activities of the Government local chief executive, for local government
requiring adequate external technical and units. Provided, That in a department, office
professional experts that are beyond the or agency where the procurement is
capability and/or capacity of the decentralized, the Head of each
government to undertake such as, but not decentralized unit shall be considered as the
limited to: (I) advisory and review services; Head of the Procuring Entity subject to the
(ii) pre investment or feasibility studies; (iii) limitations and authority delegated by the
design; (iv) construction supervision; (v) head of the department, office or agency.
management and related services; and (vi)
other technical services or special studies. (k) Infrastructure Projects - include the
construction, improvement, rehabilitation,
(g) G - EPS - refers to the Government demolition, repair, restoration or
Electronic Procurement System as provided maintenance of roads and bridges, railways,
in Section 8 of this Act. airports, seaports, communication
faci9lities, civil works components of
(h) Goods - refer to all items, supplies, information technology projects, irrigation,
materials and general support services, flood control and drainage, water supply,
except consulting services and sanitation, sewerage and solid waste
infrastructure projects, which may be management systems, shore protection,
needed in the transaction of the public energy/power and electrification facilities,
national buildings, school buildings and following the standard forms and manuals
other related construction projects of the prescribed by the GPPB.
government.
The Bidding Documents shall include the
(l) IRR - refer to the implementing rules and following:
regulations to be promulgated in (a) Approved Budget for the Contract;
accordance with Section 75 of this Act. (b) Instructions to Bidders, including criteria
for eligibility, bid evaluation and post-
(m) Portal - refers to a website that qualification, as well as the date, time and
aggregates a wide variety of content for the place of the pre-bid Conference (where
purpose of attracting a large number of applicable), submission of bids and opening
users. of bids;
(c) Terms of Reference;
(n) Procurement - refers to the acquisition (d) Eligibility Requirements;
of Goods, Consulting Services, and the (e) Plans and Technical Specifications;
contracting for Infrastructure Projects by (f) Form of Bid, Price Form, and List of
the Procuring Entity. Procurement shall also Goods or Bill of Quantities;
include the lease of goods and real estate. (g) Delivery Time or Completion Schedule;
With respect to real property, its (h) Form and Amount of Bid Security;
procurement shall be governed by the (i) Form and Amount of Performance
provisions of Republic Act No.8974, entitled Security and Warranty; and,
"An Act to Facilitate the Acquisition of Right- (j) Form of Contract, and General and
of -Way Site or Location of National special Conditions of Contract.
Government Infrastructure Projects and for
Other Purposes" and other applicable laws, The Procuring Entity may require additional
rules and regulations. document requirements or specifications
necessary to complete the information
(o) Procuring Entity - refers to any branch, required for the bidders to prepare and
department, office, agency, or submit their respective bids.
instrumentality of the government,
including state universities and colleges, Reference to Brand Names.- Specifications
government-owned and/or - controlled for the Procurement of Goods shall be
corporations, government financial based on relevant characteristics and/or
institutions, and local government units performance requirements. Reference to
procuring Goods, Consulting Services and brand names shall not be allowed.
Infrastructure Projects.
Access to Information.- In all stages of the
PROCUREMENT PROCEDURES preparation of the Bidding Documents, the
Procuring entity shall ensure equal access to
PREPARATION OF BIDDING DOCUMENTS information. Prior to their official release,
no aspect of the Bidding Documents shall
Form and Contents of Bidding be divulged or released on any prospective
Documents.- The Bidding Documents shall bidder or having direct or indirect interest in
be prepared by the Procuring Entity the project to be procured.
prospective bidders, in the case of the
INVITATION TO BID Procurement of Consulting Services the
examination and evaluation of Bids, and
Pre-Procurement Conference. - Prior to the post-qualification;
issuance of the Invitation to Bid, the BAC is (c) The date, time and place of the
mandated to hold a pre-procurement deadlines for the submission and receipt of
conference on each and every procurement, the eligibility requirements, the pre-bid
except those contracts below a certain level conference if any, the submission and
or amount specified in the IRR, in which receipt of bids, and the opening of bids;
case, the holding of the same is optional. (d) The Approved Budget for the Contract to
be bid;
The pre- procurement conference shall (e) The source of funds;
assess the readiness of the procurement in (f) The period of availability of the Bidding
terms of confirming the certification of Documents, and the place where these may
availability of funds, as well as reviewing all be secured and;
relevant documents and the draft Invitation (g) The contract duration; and
to Bid, as well as consultants hired by the (h) Such other necessary information
agency concerned and the representative of deemed relevant by the Procuring Entity.
the end -user.
Pre-bid Conference. - At least one pre-bid
Advertising and Contents of the Invitation to conference shall be conducted for each
Bid. - In line with the principle of procurement, unless otherwise provided in
transparency and competitiveness, all the IRR. Subject to the approval of the BAC,
Invitations to Bid contracts under a pre-bid conference may also be conducted
competitive bidding shall be advertised by upon the written request of any prospective
the Procuring Entity in such manner and for bidder.
such length of time as may be necessary
under the circumstances, in order to ensure The Pre-bid conference(s) shall be held
the widest possible dissemination thereof, within a reasonable period before the
such as, but not limited to, posting in the deadline for receipt of the bids to allow
Procuring Entity's premises, in newspapers prospective bidders to adequately prepare
of general circulation, the G-EPS and the their bids, which shall be specified in the
website of the Procuring Entity, if available. IRR.
The details and mechanics of
implementation shall be provided in the IRR RECEIPT AND OPENING OF BIDS
to be promulgated under this Act.
Eligibility Requirements for the Procurement
The Invitation to Bid shall contain, among of Goods and Infrastructure Projects.- The
others: BAC or, under special circumstances
(a) A brief description of the subject matter specified in IRR, its duly designated organic
of the Procurement; office shall determine the eligibility of
(b) A general statement on the criteria to be prospective bidders for the procurement of
used by the Procuring entity for the Goods and Infrastructure Projects, based on
eligibility check, the short listing of the bidders' compliance with the eligibility
requirements within the period set forth in The eligible prospective bidders shall then
the Invitation to Bid. The eligibility be evaluated using numerical ratings on the
requirements shall provide for fair and basis of the short listing requirements
equal access to all prospective bidders. The prescribed for the Competitive Bidding
documents submitted in satisfaction of the concerned, within the period stated in the
eligibility requirements shall be made under Invitation to Bid to determine the short list
oath by the prospective bidder or by his of bidders who shall be allowed to submit
duly authorized representative certifying to their respective bids.
the correctness of the statements made and
the completeness and authenticity of the Submission and Receipt of Bids.- A bid shall
documents submitted. have two(2) components, namely the
technical and financial components which
A prospective bidder may be allowed to should be in separate sealed envelopes, and
summit his eligibility requirement s which shall be submitted simultaneously.
electronically. However, said bidder shall The bids shall be received by the BAC on
later on certify under oath as to correctness such date, time and place specified in the
of the statements made and the invitation to bid. The deadline for the
completeness and authenticity of the receipt of bids shall be fixed by the BAC,
documents submitted. giving the prospective bidders sufficient
time to study and prepare their bids. The
Eligibility requirements and Short Listing for deadline shall also consider the urgency of
Consulting Services.- The Eligibility of the procurement involved.
prospective bidders for the Procurement of
Consulting Services shall be determine by Bids submitted after the deadline shall not
their compliance with the eligibility be accepted.
requirements prescribed for the competitive
Bidding concerned, within the period stated Notwithstanding the provisions of this
in the Invitation to bid. The eligibility Section and Section 26 of this Act, the GPPB
requirements shall provide for fair and may prescribe innovative procedure for the
equal access to all prospective bidders. The submission, receipt and opening of bids
prospective bidder shall certify under oath through the G-EPS.
as to the correctness of the statements
made, and the completeness and Modification and Withdrawal of Bids. - A
authenticity of the documents submitted. bidder may modify his bid, provided that
this is done before the deadline for the
A prospective bidder may be allowed to receipt of bids. The modification shall be
submit his eligibility requirements submitted in a sealed envelope duly
electronically. However, said bidder shall identified as a modification of the original
later on certify under oath as to correctness bid and stamped received by the BAC.
of the statements made and the
completeness and authenticity of the A bidder may, through a letter, withdraw his
documents submitted. bid or express his intention not to
participate in the bidding before the
deadline for the receipt of bids. In such
case, he shall no longer be allowed to participating in the bidding. There shall be
submit another Bid or the same contract no lower limit to the amount of the award.
either directly or indirectly.
Bid for the Procurement of Goods and
Bid Security. - All Bids shall be accompanied Infrastructure Projects. - For the
by a Bid security, which shall serve as procurement of Goods and Infrastructure
guarantee that, after receipt of the Notice Projects, the BAC shall evaluate the financial
of Award, the winning bidders shall enter component of the bids. The bids that passed
into contract with the Procuring Entity the preliminary examination shall be ranked
within the stipulated time and furnish the from lowest to highest in terms of their
required performance security. The specific corresponding calculated price shall be
amounts and allowable forms of the Bid referred to as the "Lowest Calculated Bid".
security shall be prescribed in the IRR.
Bid Evaluation of Short-Listed Bidders for
Bid Validity. - Bids and Bid securities shall be Consulting Services. - For the Procurement
valid for such reasonable period of time of Consulting Services, the Bids of the short
indicated in the Bidding Documents. The listed bidders shall be evaluated and ranked
duration for each undertaking shall take into using numerical ratings in accordance with
account the time involved in the process of the evaluation criteria stated in the Bidding
Bid evaluation and award of contract. Documents, which shall include factors such
as, but not limited to, experience,
Bid Opening. - the BAC shall publicly open performance, quality or personnel, price
all bids at the time, date, and place and methodology. The Bids shall be ranked
specified in the bidding documents. The from highest to lowest in terms of their
minutes of the bid opening shall be made corresponding calculated ratings. The Bid
available to the public upon written request with the highest calculated rating shall be
and payment of a specified fee. the "Highest Rated Bid." After approved by
the Head of the Procuring Entity of the
BID EVALUATION Highest Rated Bid, the BAC shall invite the
bidder concerned for negotiation and/or
Preliminary Examination of Bids. - Prior to clarification on the following item: financial
Bid evaluation, the BAC shall examine first proposal submitted by the bidder, terms of
the technical components of the bids using reference, scope of services, methodology
"pass/fail" criteria to determine whether all and work program, personnel to be
required documents are present. Only bids assigned to job, services/facilities/data to
that are determined to contain all the bid be provided by the Procuring Entity
requirements of the technical component concerned, and provisions of the contract.
shall be considered for opening and When negotiations with first-in-rank bidder
evaluation of their financial component. fails, the financial proposal of the second
rank bidder shall opened for negotiations:
Ceiling for Bid Prices. - The ABC shall be the Provided, that the amount indicated in the
upper limit or ceiling for the Bid prices. Bid financial envelope shall be made as the
prices that exceed this ceiling shall be basis for negotiations and the total contract
disqualified outright from further amount shall not exceed the amount
indicated in the envelope and the ABC. b. No bid qualifies as the Lowest Calculated
Whenever necessary, the same process shall Responsive Bid; or,
be repeated until the bid awarded to the c. Whenever the bidder with the highest
winning bidder. rated/lowest calculated responsive bid
refuses, without justifiable cause to accept
POST-QUALIFICATION the award of contract, as the case may be.

Objective and Process of Post-qualification. Under any of the above instances, the
- Post-qualification is the stage where the contract shall be re-advertised and re-bid.
bidder with the Lowest Calculated Bid, in
the case of Goods and Infrastructure The BAC shall observe the same process and
Projects, or the Highest Rated Bid, in the set the new periods according to the same
case of Consulting Services, undergoes rules followed during the first bidding. After
verification and validation whether he has the second failed bidding, however, the BAC
passed all the requirements and conditions may resort to negotiated procurement as
as specified in the Bidding Documents. provided for in Section 53 of this Act.

If the bidder with the Lowest Calculated Bid Single Calculate/Rated and Responsive Bid
or Highest Rated Bid passes all the criteria Submission. - A single calculated/rated and
for post-qualification, his Bid shall be responsive bid shall be considered for award
considered the "Lowest Calculated if it falls under of the following
Responsive Bid," in the case of Goods and circumstances:
Infrastructure or the "Highest Rated
Responsive Bid," in the case of Consulting a. If after advertisement, only one
Services. However, if a bidder fails to meet prospective bidder submits a Letter of
any of the requirements or conditions, he Intent and/or applies for eligibility check,
shall be "post-disqualified" and the BAC and meets the eligibility requirements or
shall conduct the post-qualification on the criteria, after which it submits a bide, which
bidder with the second Lowest Calculate Bid is found to be responsive to the bidding
or Highest Rated Bid. If the bidder with the requirements;
second Lowest Calculated Bid or Highest b. If after the advertisement, more than one
Rated Bid is post-disqualified, the same prospective bidder applies for eligibility
procedure shall be repeated until the check, but only one bidder meets the
Lowest Calculated Responsive Bid or Highest eligibility requirements or criteria, after
Rated Responsive Bid is finally determined. which in submits a bid which is found to be
responsive to the bidding requirements; or
In all cases, the contract shall be awarded c. If after the eligibility check, more than
only to the bidder with the Lowest one bidder meets the eligibility
Calculated Responsive Bid or Highest Rated requirements, but only one bidder submits
Responsive Bid. a bid, and its bid is found to be responsive
to the bidding requirements.
Failure of Bidding. - there shall be a failure
of bidding if: In all instances, the Procuring Entity shall
a. No bids are received; ensure that the ABC reflects the most
advantageous prevailing price for the
government. Period of Action on Procurement Activities.
AWARD, IMPLEMENTATION AND - The procurement process from the
TERMINATION OF THE CONTRACT opening of bids up to the award of contract
shall not exceed three (3) months, or a
Notice and Executive of Award. - Within a sho0rter period to be determined by the
period not exceeding fifteen (15) calendar procuring entity concerned. Without
days from the determination and prejudice to the provisions of the preceding
declaration by the BAC of the Lowest section, the different procurement activities
Calculated Responsive Bid or Highest Rated shall be completed within reasonable
Responsive Bid, and the recommendation of periods to be specified in the IRR.
the award, the Head of the Procuring Entity
or his duly authorized representative shall If no action on the contract is taken by the
approve or disapprove the said head of the procuring entity or by his duly
recommendation. In case of approval, the authorized representative, or by the
Head of the Procuring Entity or his duly concerned board, in the case of
authorized representative shall immediately government-owned and/or -controlled
issue the Notice of Award to the bidder with corporations, within the periods specified in
the Lowest Calculated Responsive Bid or the preceding paragraph, the contract
Highest Rated Responsive Bid. concerned shall be deemed approved.

Within ten (10) calendar days from receipt Performing Security. - Prior to the signing of
of the Notice of Award, the Winning bidder the contract, the winning bidder shall, as a
shall formally enter into contract with the measure of guarantee for the faithful
Procuring Entity. When further approval of performance of an compliance with his
higher authority is required, the approving obligations under the contract prepared in
authority for the contracts shall be given a accordance with the Bidding Documents, be
maximum of twenty (20) calendar days to required to post a performance security in
approve or disapprove it. such form and amount as specified in the
Bidding Documents.
In the case of government-owned and/or -
controlled corporations, the concerned Failure to Enter into Contract and Post
board shall take action on the said Performance Security. - If, for justifiable
recommendation within thirty (30) calendar causes, the bidder with the Lowest
days from receipt thereof. Calculated Responsive Bid or Highest Rated
Responsive Bid fails, refuses or is otherwise
The Procuring Entity shall issue the Notice unable to enter into contract with the
to Proceed to the winning bidder not later Procuring Entity, or if the bidder fails to post
than seven (7) calendar days from the date the required performance security within
of approval of the contract by the the period stipulated in the Bidding
appropriate authority. All notices called for Documents, the BAC shall disqualify the said
by the terms of the contract shall be bidder and shall undertake post-
effective only at the time of receipt thereof qualification for the next-ranked Lowest
by the contractor. Calculated Bid or Highest Rated Bid. This
procedure shall be repeated until an award DISCLOSURE OF RELATIONS.
is made. However, if no award is possible,
the contract shall be subjected to a new In addition to the proposed contents of the
bidding. Invitation to Bid, all bidding documents shall
be accompanied by a sworn affidavit of the
In the case of a failure to post the required bidder that he or she or any officer of their
performance security, the bid security shall corporation in not related to the Head of
be forfeited without prejudice to the the Procuring Entity by consanguinity or
imposition of sanctions prescribed under affinity up to the third civil degree.
Article XXIII.
Failure to comply with the aforementioned
Reservation Clause. - The Head of the provision shall be a ground for the
Agency reserves the right to reject any and automatic disqualification of the bid.
all Bids, declare a failure of bidding, or not
award the contract in the following ALTERNATIVE METHODS OF
situations: PROCUREMENT

a. If there is prima facie evidence of a. Limited Source Bidding, otherwise known


collusion between appropriate public as Selective Bidding - a method of
officers or employees of the Procuring Procurement that involves direct invitation
Entity, or between the BAC and any of the to bid by the Procuring Entity from a set of
bidders, or if the collusion is between or pre-selected suppliers or consultants with
among the bidders themselves, or between known experience and proven capability
a bidder and a third party, including any act relative to the requirements of a particular
which restricts, suppresses or nullifies or contract.
tends to restrict, suppress or nullify
competition; Limited Source Bidding may be resorted to
b. If the BAC is found to have failed in only in any of the following conditions:
following the prescribed bidding a. Procurement of highly specialized types
procedures; or of Goods and Consulting Services which are
c. For any justifiable and reasonable ground known to be obtainable only from a limited
where the award of the contract will not number of sources; or
redound to the benefit of the government b. Procurement of major plant components
as defined in the IRR. where it is deemed advantageous to limit
the bidding to known eligible bidders in
Contract Implementation and Termination. order to maintain an optimum and uniform
- The rules and guidelines for the level of quality and performance of the
implementation and termination of plant as a whole.
contracts awarded pursuant to the
provisions of this Act shall be prescribed in b. Direct Contracting, otherwise known as
the IRR. The rules and guidelines shall Single Source Procurement - a method of
include standard general and special Procurement that does not require
conditions for contracts. elaborate Bidding Documents because the
supplier is simply asked to submit a price
quotation or a pro-forma voice together a. The unit price must be equal to or lower
with the conditions of sale, which offer may than that provided in the original contract;
be accepted immediately or after some b. The repeat order does not result in
negotiations. splitting of requisitions or purchase orders;
c. Except in special circumstances defined in
Direct Contracting may be resorted to only the IRR the repeat order shall be availed of
in any of the following conditions: only within six (6) months from the date of
a. Procurement of Goods of propriety the Notice to Proceed arising from the
nature, which can be obtained only from original contract; and,
the propriety source, i.e. when patents, d. The repeat order shall not exceed twenty-
trade secrets and copyrights prohibit others five percent (25%) of the quantity of each
from manufacturing the same items; item of the original contract.
b. When the Procurement of critical
components from a specific manufacturer, d. Shopping - a method of Procurement
supplier, or distributor is a condition whereby the Procuring Entity simply
precedent to hold a contractor to guarantee requests for the submission of price
its project performance, in accordance with quotations for readily available off-the-shelf
the provisions his contract; or, Goods or ordinary/regular equipment to be
c. Those sold by an exclusive dealer or procured directly from suppliers of known
manufacturer, which does not have sub- qualification.
dealers selling at lower prices and for which
no suitable substitute can be obtained at Shopping may be resorted to under any of
more advantageous terms to the the following instances:
government. a. When there is an unforeseen contingency
requiring immediate purchase: Provided,
c. Repeat Order. - a method of Procurement however, That the amount shall not exceed
that involves a direct Procurement of Goods Fifty thousand pesos (P50,000); or
from the previous winning bidder, whenever b. Procurement of ordinary or regular office
there is a need to replenish Goods procured supplies and equipment not available in the
under a contract previously awarded Procurement Service involving an amount
through Competitive Bidding. not exceeding Two hundred fifty thousand
pesos (P250,000): Provided, however, That
When provided for in the Annual the Procurement does not result in Splitting
Procurement Plan, Repeat Order may be of Contracts: Provided, further, That at least
allowed wherein the Procuring Entity three (3) price quotations from bona fide
directly procures Goods from the previous suppliers shall be obtained.
winning bidder whenever there arises a
need to replenish goods procured under a The above amounts shall be subject to a
contract previously awarded through period review by the GPPB. For this
Competitive Bidding, subject to post- purpose, the GPPB shall be authorized to
qualification process prescribed in the increase or decrease the said amount in
Bidding Documents and provided all the order to reflect changes in economic
following conditions are present: conditions and for other justifiable reasons.
e. Negotiated Procurement - a method of negotiations for the procurement are
Procurement that may be resorted under commenced before the expiry of the
the extraordinary circumstances provided original contract. Wherever applicable, the
for in Section 53 of this Act and other principle shall also govern consultancy
instances that shall be specified in the IRR, contract, where the consultants have
whereby the Procuring Entity directly unique experience and expertise to deliver
negotiates a contract with a technically, the required service; or,
legally and financially capable supplier, e. Subject to the guidelines specified in the
contractor or consultant. IRR, purchases of Goods from another
agency of the government, such as the
Negotiated Procurement shall be allowed Procurement Service of the DBM, which is
only in the following instances: tasked with a centralized procurement of
a. In case of two (2) failed bidding as commonly used Goods for the government
provided in Section 35 hereof; in accordance with Letters of Instruction No.
b. In case of imminent danger to life or 755 and Executive Order No. 359, series of
property during a state of calamity, or when 1989.
time is of the essence arising from natural
or man-made calamities or other causes In all instances, the Procuring Entity shall
where immediate action is necessary to ensure that the most advantageous price for
prevent damage to or loss of life or the government is obtained.
property, or to restore vital public services,
infrastructure facilities and other public
utilities;
c. Take-over of contracts, which have been
rescinded or terminated for causes provided
for in the contract and existing laws, where
immediate action is necessary to prevent
damage to or loss of life or property, or to
restore vital public services, infrastructure
facilities and other public utilities;
d. Where the subject contract is adjacent or
contiguous to an on-going infrastructure
project, as defined in the IRR: Provided,
however, That the original contract is the
result of a Competitive Bidding; the subject
contract to be negotiated has similar or
related scopes of work; it is within the
contracting capacity of the contractor; the
contractor uses the same prices or lower
unit prices as in the original contract less
mobilization cost; the amount involved does
not exceed the amount of the ongoing
project; and, the contractor has no negative
slippage: Provided, further, That