Professional Documents
Culture Documents
Integration Management
Integration Management
- Fast tracking the project adds risk as more activities are done in
parallel.
- A work authorization system helps tell the team when work should
begin on work packages.
- The schedule baseline is there for you to determine how the project is
progressing. Follow your change management process, and continue to
track against your baseline.
- It is the final plan and not the components that require authorization.
Otherwise, there is extra work for everyone.
- When helping another PM with their project, you should offer your
assistance without doing the work.
- When taking over a project from another PM, you have to know what
YOU are going to do. Developing the management strategy will provide
the framework for all the rest of the choices presented and the other
activities that need to be done.
- When you have several people sign-off on project charter, this situation
implies that there are several areas concerned with this project. In
addition to added communications requirements, you should be
concerned with competing needs and requirements impacting your
efforts on configuration management.
- The risk audit is done during monitoring and controlling, not closure.
- In the real world, problems often repeat. Without a record of what was
done, there is no opportunity to consider the same solution for future
problems. Documentation is critical to projects. Because
documentation becomes part of the historical records database.
- The project management plan contains more than just a bar or Gantt
chart and the project manager's plan for completing the work. It
includes all the management plans for the project.
- Changes are not listed in the scope management plan or in the project
charter. A PM must determine if a change is needed, if a change is
beneficial and notify stakeholders affected by the change.
- The person requesting the change usually formulates the change and
creates a change proposal. The performing organization usually
creates the procedures regarding changes. The change control board
reviews requests for changes, evaluates both the positive and negative
impacts and then approves or rejects the changes.
- The larger the BCR, SPI and CPI the better. A project with high priority
normally holds more senior commitment.
- If the same department is submitting all changes, then you must talk
to the department to understand the reason of changes. The best way
to deal with this problem is to discover the root cause.
- The project management plan is used to guide the project and it is the
project manager's integration role.
- All projects, even those that do not have a completion date (yes, they
do exist), should be planned and have a schedule, if for no other
reason than to control the project and prove project success. However,
if there is no end date, the schedule should allow for resources being
removed and other such delays.
- The sponsor issues the project charter and so he or she should help the
project manager control changes to the charter. The primary
responsibility lies with the sponsor.
- Sunk costs are expended costs. The rule is that they should not be
considered when deciding whether to continue with a troubled project.
- You want to capture data at the end of each phase of a project. If you
wait until the end, you may forget important information.
- The details of what needs to be done are found in the WBS dictionary.
The names of team members are included in responsibility assignment
matrix and other documents. Project history is found in the lessons
learned and other project documents.
- If many changes are being requested and made, it indicates that the
scope definition was incomplete. A thorough review of the project
scope with the stakeholders will help identify where problems exist and
allow you to focus on fixing them.
- If you need to make a decision over the allotted budget, discuss the
impact with the customer and ask for a decision.
- With any project, you need to focus on the needs of the stakeholders.
By understanding their needs, you will be far ahead in developing a
structured approach that fits their needs.
- The project manager needs to analyze the problems and identify what
caused them before making a decision.
- If you receive a request that does not affect the scheduled and easy to
complete; you must evaluate the impact on other project constraints.
- Value analysis is a way of making sure that the least expensive way is
found to do the work.
- The Close Contract process may happen before the project as a whole
is complete.
- Lessons Learned help to avoid future pitfalls and use the good ideas of
past projects. This leads to improvements in future projects.
- If you cannot determine how many changes are being reviewed, the
problem lies with change control system and project scope
management plan.
- Releasing the team is the last thing to do in project closure. You need
your team to do the work of project closure.
- The opportunity cost is the value of the project that was not selected;
the lost opportunity.
- Straight line depreciation uses the same amount each time period.
- The internal rate of return is similar to the interest rate you get from
the bank. The higher the rate is, the better the return.
- If a deviation has occurred from the plan, the first thing is always to
evaluate the impact of the change on the project. A good thing to do
next might be to see what the contract states and then meet with the
customer.
- If you can’t get a project charter approved for a project that is about to
begin, the best thing to do would be to show the impact. This is the
only choice that prevents future problems - always the best choice.
- Value analysis involves finding a less costly way to do the same scope
of work.
- If you learn that functionality was added to the project, after the fact
and there was no impact on cost and schedule. You need to
understand what change has taken place and then evaluate the impact
and options.
- The payback period is how long it will take the company to recoup their
investment in the project.
- If you discover that a project will take twice the time to complete as
previously mentioned in plan, you must report your assessment to the
sponsor.
- You create the change management plan before you need it; in the
planning process group.
- Pay Back period, is how long will it take to get back your initial
investment from the project. The faster you get your money back, the
faster you can re-invest that money in another endeavour. The shorter
the time the better.
- Only with formal acceptance can the project manager be sure the
project work is really complete.
- "Who creates the project management plan?" The best answer is that
project management plans are created by the project manager but
require input from the team.
- The project charter is issued by the sponsor. The project manager may
have a role in its creation.
- The needs of the stakeholders and not just the sponsor must be taken
into account on all projects.
- The company gets large value in finishing. Perhaps they can sell the
finished product to someone else. Completing the project will meet
your company objectives and help you gain the expertise you need if
the client agrees and proprietary client data is not required to
complete the work.
- The Verify Scope process occurs during the monitoring and controlling
process of the project, not at the end. A similar activity during closure
is product verification.
- You and the team need to work through the project planning processes
and then decide what the impact of the cost and schedule
requirements will be on the project. You would not accept the
requirements without proper evaluation.
- Rules for when a change should formally be made are discussed or set
up during project planning and must follow any company policies.
These plans would be included or referenced in the project's change
control system.
- A payback period is the amount of time it takes to recoup the
investment in a project.
- With everything going well on the project, the only choice that makes
sense is to review the management plans for the project.
- Historical records, they are collected throughout the project, but are
only archived during the Close Project or Phase process.
- You cannot accept a gift from the client, or any gift of the magnitude of
a car.
- If you do not know what was planned, there isn`t further information
available to make sound judgement calls.
- The project management plan is the only choice that meets the
objectives of guiding work in Execution and Monitoring & Controlling.