ID Task Task Name Duration Start Finish June 2023 July 2023 August 2023 September 2023 October

3 July 2023 August 2023 September 2023 October 2023 November 2023
Mode 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20
1
2 Zone B 12 days Mon 6/5/23 Tue 6/20/23
3 Flushing 6 days Mon 6/5/23 Mon 6/12/23
4 Initial Turbidity 1 day Mon 6/12/23Mon 6/12/23
5 Chlorination 3 days Tue 6/13/23 Thu 6/15/23
6 Final Turbidity 1 day Fri 6/16/23 Fri 6/16/23
7 End Capping 2 days Mon 6/19/23Tue 6/20/23
8 ZoneC 13 days Fri 6/16/23 Tue 7/4/23
9 Flushing 6 days Fri 6/16/23 Sun 6/25/23
10 Initial Turbidity 2 days Mon 6/26/23Tue 6/27/23
11 Chlorination 2 days Wed 6/28/23Thu 6/29/23
12 Final Turbidity 1 day Fri 6/30/23 Fri 6/30/23
13 End Capping 2 days Mon 7/3/23 Tue 7/4/23
14 Zone D 14 days Mon 7/3/23 Thu 7/20/23
15 Flushing 6 days Mon 7/3/23 Mon 7/10/23
16 Initial Turbidity 2 days Tue 7/11/23 Wed 7/12/23
17 Chlorination 3 days Thu 7/13/23 Mon 7/17/23
18 Final Turbidity 2 days Tue 7/18/23 Wed 7/19/23
19 End Capping 1 day Thu 7/20/23 Thu 7/20/23
20 Zone K 13 days Thu 7/20/23 Mon 8/7/23
21 Flushing 7 days Thu 7/20/23 Fri 7/28/23
22 Initial Turbidity 2 days Mon 7/31/23Tue 8/1/23
23 Chlorination 2 days Wed 8/2/23 Thu 8/3/23
24 Final Turbidity 1 day Fri 8/4/23 Fri 8/4/23
25 End Capping 1 day Mon 8/7/23 Mon 8/7/23
26 Zone J 16 days Tue 8/8/23 Tue 8/29/23
27 Flushing 7 days Tue 8/8/23 Wed 8/16/23
28 Initial Turbidity 2 days Thu 8/17/23 Fri 8/18/23
29 Chlorination 3 days Mon 8/21/23Wed 8/23/23
30 Final Turbidity 2 days Thu 8/24/23 Fri 8/25/23
31 End Capping 2 days Mon 8/28/23Tue 8/29/23
32 Zone E 14 days Wed 8/30/23Mon 9/18/23
33 Flushing 7 days Wed 8/30/23Thu 9/7/23
34 Initial Turbidity 2 days Fri 9/8/23 Mon 9/11/23
35 Chlorination 3 days Tue 9/12/23 Thu 9/14/23
36 Final Turbidity 1 day Fri 9/15/23 Fri 9/15/23
37 End Capping 1 day Mon 9/18/23Mon 9/18/23
38 Zone G 14 days Tue 9/19/23 Fri 10/6/23
39 Flushing 7 days Tue 9/19/23 Wed 9/27/23
40 Initial Turbidity 1 day Thu 9/28/23 Thu 9/28/23
41 Chlorination 3 days Fri 9/29/23 Tue 10/3/23
42 Final Turbidity 1 day Wed 10/4/23Wed 10/4/23
43 End Capping 2 days Thu 10/5/23 Fri 10/6/23
44 Zone F 14 days Mon 10/9/23Thu 10/26/23
45 Flushing 7 days Mon 10/9/23Tue 10/17/23
46 Initial Turbidity 1 day Wed 10/18/23Wed 10/18/23
47 Chlorination 3 days Thu 10/19/23Mon 10/23/23
48 Final Turbidity 1 day Tue 10/24/23Tue 10/24/23
49 End Capping 2 days Wed 10/25/23Thu 10/26/23
50 Zone H 14 days Fri 10/27/23 Wed 11/15/23
51 Flushing 7 days Fri 10/27/23 Mon 11/6/23
52 Initial Turbidity 1 day Tue 11/7/23 Tue 11/7/23
53 Chlorination 3 days Wed 11/8/23Fri 11/10/23
54 Final Turbidity 1 day Mon 11/13/23Mon 11/13/23
55 End Capping 2 days Tue 11/14/23Wed 11/15/23

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Flushing and Disinfectio Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline