Professional Documents
Culture Documents
shortly
VARIATION
UNDER FIDIC 1999 RED BOOK
Delivered by
Asmy Sheriff
MRICS, CCMP, LLM, MBA, BSc(Eng)
ö What is variation
ö Who Can order variation
ö Right to vary in
α Changes to sequence and timing of the execution of the Works
α Methods of construction
α Changes in quantities of any item of work included in the Contract
α Omission of work
CHECKLIST
The right of the employer to vary or change the works - After the contract has
been entered into is generally considered by many to be an essential element of a construction contract.
In the absence of a right to vary - The parties would be required to reach an agreement as to any
changes of the works and the time and cost consequences.
Variation in FIDIC
The Contractor is expressly required to execute each Variation unless he
considers that he has a valid ground to object.
ö Whether the instructed change is within the scope of Variations permitted under the Contract or
under the governing law;
ö where the Contractor has the responsibility for the design of the Works and/or where the Works
are specified in terms of performance requirements, the effect of the Variation on design
responsibility and/or the performance guarantees; and
c) changes to the levels, positions and/or dimensions of any part of the Works,
e) any additional work, Plant, Materials or services necessary for the Permanent Works, including any
associated Tests on Completion, boreholes and other testing and exploratory work, or
us???
Omission of work.
but subject to one important qualification, namely
Sub-Clause 13.1 of the Red Book grants the ‘‘unless it is to be carried out by others’’.
Engineer an express power to omit any
Main Roads v. Reed & Stuart Pty Ltd – by High court of
work. Australia ( Common law)
Changes to sequence and timing of the
execution of the Works.
Sub- Clause 13.1( f ) grants the Engineer the Can the Engineer use this clause
express right to change the ‘‘sequence or to accelerate the work?
timing of the execution of the Works’’. This does not empower the
Engineer to instruct the
Contractor, as a Variation, to
Do we have Variation for any changes to the accelerate so as to require him
methods of construction. to complete the Works (or a
Notably, changes to the Contractor’s methods for the execution of the Section) prior to the Time for
Works are not included in the list in Sub-Clause 13.1.
Completion.
This is because a change to the Temporary Works is caught by the
definition of a Variation.
Grounds for objection
The Contractor is required to execute and is The Engineer is required to cancel,
bound by each Variation, except where he confirm or vary the instruction.
administrator to explore the feasibility of a (i) ‘‘a description of the proposed [design and/or (Y/S/G)]
Variation before being bound by it. work to be performed’’;
the letter (iv) a proposal for the evaluation of the Variation (R/M)
Yes, because to avoid the risk that a request The Contractor may not submit a
may appear to be an instruction where that proposal
will be a Variation 1. The reasons are the same as those for which it can give
notice of an objection to a Variation under Sub- Clause 13.1,
(iii) improve the efficiency or value to the Employer of Therefore, the Contractor has little
the completed Works, or incentive to make a proposal that has
no tangible benefit to the Employer
(iv)otherwise be of benefit to the Employer.
even if it is cost or time neutral and
Who will take design responsibility? would benefit the Contractor.
Matter Reference to Variation/Clause Sub-Clause Matter Reference to Sub-
13 Variation/Clause 13 Clause
8.3
Contractor may be required to Proposal under Sub-Clause
5.1
Instruction to employ a nominated Instruction under Clause 13
Subcontractor submit an estimate of the 13.3
anticipated effect of the future
event or circumstances, and/or a
4.6
Unforeseeable cost of co-operating Variation
with Employer’s Personnel, other proposal.
contractors, public authorities, as
instructed by contract administrator
4.12
Instructions from contract If instruction constitutes a
Prolonged suspension affecting Omission under Clause 13
administrator following the Variation, Clause 13 applies
part of the Works.
Contractor encountering
Unforeseeable physical conditions 8.11
11.2
Remedying defects for which Sub-Clause 13.3 applies
Contractor is not responsible. (R/M/Y/S)/ Variation under
Clause 13 (G)
7.2
Instruction to submit additional Instructed as a variation
samples.
7.4
Instruction for additional or amended Instruction under Clause 13
tests (where results show no default)
13.5
or delayed tests. Provisional Sums. Valued under Sub- Clause
13.3