You are on page 1of 6

Law_Information:International Trade Law:FIDIC Claim Management

Page 1 of 6

FIDIC Claim Management


By Rechtsanwalt Dr. Gtz-Sebastian Hk

As has been confirmed by Judge Sanders in Attorney General for the Falkland Islands v. Gordon Forbes Construction (Falklands) Limited, Falkland Islands Supreme Court 14 March 2003, FIDIC contracts are aimed at the early resolution of any queries at the time when the claim arises, with the likelihood that plant, manpower and witnesses are still on site (for a further construction of the relevant Sub-Clauses of the FIDIC 1999 edition see also High Court of Trinidad and Tobago, judgment from 21 October 2009 (Claim No CV2008-04881) in National Insurance Property Development Co Ltd v. NH International (Carribean) Ltd). Thus claims have to be pursued in a detailed procedure provided by the FIDIC contracts. In a summary this means: to give notice (in time) to give particulars of the claim (in time) to wait for Engineers approval or disapproval to negotiate and settle the claim to wait for Engineers determination (in case of failure to reach settlement) to refer a dispute to the DAB (in case of dissatisfaction) As "claim" means nothing else than the assertion of a right, either arising out of or in connection with the contract, it is strongly recommended to assess the whole Contract and to identify all of the claims stipulated therein as well as all relevant legal claims as provided for by the governing law (proper law of the contract). Both, Contractors and Employers, should have a clear view of the risk compensation features which can be found in the Contract and the governing law. A claim will only become an entitlement if the Contract parties strictly follow the procedures under the FIDIC Contract, which means in most cases: to give a notice of a claim to keep contemporary records to submit particulars of claim FIDIC forms of contract provide for Cost claims, Cost and profit claims and extension of Time for Completion (EOT) claims. Cost is a defined term meaning all expenditure reasonably incurred (Sub-Clause 1.1.4.3) including overheads and similar charges but no profit. The meaning of the terms "expenditure" and "overheads" is not explained. This may lead to debate. It is submitted that "expenditure" should be read and understood in the sense of the English authorities (see Hadley v. Baxendale (1854) 9 Ex. 341). However, civil law practitioners may prefer to rely on the theory that if payment of the contratcor is not exactly defined in the Contract the Contractor should be entitled to a reasonable remuneration (see Compagnie Interafricaine de Travaux v. South African Transport Services and Others (680/89) [1991] ZASCA 16; 1991 (4) SA 217 (AD); (21 March 1991). In that case the contract included the following Sub-Clause: No claim by the Contractor will be considered on account of the materials, methods of construction and/or site conditions being different from those assumed by him in tendering for the contract, except in the case of adverse sub surface conditions which in the

http://www.dr-hoek.de/EN/beitrag.asp?t=FIDIC-Claim-Management

6/25/2011

Law_Information:International Trade Law:FIDIC Claim Management

Page 2 of 6

opinion of the engineer could not reasonably have been foreseen. The governing law may also provide for claims. A contractor may for example prefer to rely on a Common Law misrepresentation claim instead of one under Sub-Clause 4.12. The Civil Law principle of good faith may also constitute a good basis for a claim. Under German law the site (which according to the courts has the nature of a free issue material) shall be "fit for the works" meaning that the contractor may be entitled to additional payment when the site is not "fit for the Works". In some countries where a contract for public works has the nature of an administrative contract (for example in France and purportedly in Egypt, Qatar and the UAE) the "imprvision" principle may give raise to claims. US courts have confirmed "constructive acceleration claims" and "loss of bonding capacity claims". Anyway, if -under a FIDIC Contract- the Contractor considers himself to be entitled to a claim (whether under a clause of the Contract or in connection with the Contract), the first step is for him to give notice. This Notice is important because: everyone involved becomes aware that there is an event or circumstance where extra time or payment may be owed to the Contractor proper contemporary records must then be kept and agreed, to avoid future argument alternative measures may also be possible to reduce the effects the matter may possibly be resolved at an early date if the event or circumstance turns out to be of insignificant effect, then it is not necessary to follow up the notice with a formal claim. As a rule claims related to extension of time and/ of additional payment under any clause of the contract or otherwise in connection with the contract must be notified within a delay of 28 days. Beware that subclause 19.2 provides a shorter period of 14 days in the event of Force Majeure circumstances. Thus the Contractor must provide to Employer's Engineer written notice of the claim for additional payment and time extension within 28 days after becoming aware of the occurrence of the event giving rise to claim (Sub-Clause 20.1). If the Contractor fails to comply with this notice requirement, his entitlement to the claim shall lapse. It should be emphasised that sometimes additional notices are required, such as under Sub-Clause 4.12 and 19.2. The claim notice must indicate basic details, in order to inform the Engineer about the scope of the claim and to enable him to give instructions, if necessary. The notice shall therefore meet the following requirements: describe the event or circumstance the notice need not state time or amount claimed or contractual basis of claim notice shall comply with Cl 1.3, i.e. in writing and properly delivered progress reports - Cl 4.21(f) - must list notices given There is no immediate response required from the Engineer (Employer) but a simple acknowledgement is normal.

http://www.dr-hoek.de/EN/beitrag.asp?t=FIDIC-Claim-Management

6/25/2011

Law_Information:International Trade Law:FIDIC Claim Management

Page 3 of 6

To the extent that a third party to the contract, the Engineer, has been nominated to determine claims, the parties to the contract shall notify him of any claims to which they consider themselves to be entitled to. He is then in charge of firstly approving or disapproving any claim and to determine it, if necessary. He shall do this with regard to all relevant circumstances, which means that he will have to take into consideration all facts reported in the monthly reports reported in contemporary records reported in labour reports stated in the claim notification obtained at site visits and inspections reported in early warning notifications concerning probable future events which may effect progress of the works and the contract price reported in the Programme reported in its own records In order to ensure that the parties and the Engineer may reach reasonable, informed, and skilful decisions, FIDIC contracts provide a sophisticated system for communications and documentation of relevant facts, events and circumstances (Sub-Clause 1.3). This system and the resulting duties as to documentation and reporting have to be recognised and respected at all times, because Judge Sanders also concluded in the Falkland case that it would be perverse if a contractor who had failed to comply with the terms of the contract should then be allowed to produce non-contemporary records to support a claim, particularly as these could not properly be investigated by the employer at a later date. The rights of the employer to inspect the records at the time the claim arose were fundamental to the FIDIC procedure. Failure to comply with the reporting duties leads to the foreclosure of claims. It should be emphasised that contractual terms requiring a contractor to give prompt notice of delay serve a valuable purpose; such notice enables matters to be investigated while they are still current. Furthermore, such notice sometimes give the employer the opportunity to withdraw instructions when the financial consequences become apparent (Steria v. Sigma per HHJ Davies, 2007] EWHC 3454 (TCC)). Thus civil law practitioners should be reluctant to rely on the principle of good faith in order to evade the notice requirements and related delays. By notice of a claim the claim determination procedure becomes initiated, which is described in Sub-Clause 3.5. According to Sub-Clause 3.5 and 20.1 the following shall happen: contemporary records shall be kept which may be inspected by the Engineer a fully detailed claim must be submitted within 42 days of the event (or other agreed time) provision for continuing claims and submittal of their details within 42 days of receiving the claim with details the Engineer shall respond with approval, or with disapproval and detailed comments. the Engineer shall determine under Clause 3.5 any time extension or additional payment to which the Contractor is entitled under the Contract. each payment certificate shall include such amounts for any claim as have been reasonably substantiated.

http://www.dr-hoek.de/EN/beitrag.asp?t=FIDIC-Claim-Management

6/25/2011

Law_Information:International Trade Law:FIDIC Claim Management

Page 4 of 6

any other specified requirements must also be satisfied (see SubClause 19.2) The Engineer may request any necessary further particulars, but shall nevertheless give his response on the principles of the claim within 42 days. Thus there is a time limit imposed on the Engineer to reply to a claim. The question may arise whether a claim fails if the Contractor failed to keep contemporary records. Following the aforementioned Falkland case this has been sometimes suggested. However the High Court of Trinidad and Tobago recently held that the relevant clauses in the respective FIDIC 1987 and FIDIC 1999 edition are different from each other. Hence, the High Court of Trinidad and Tobago held on 21 October 2009 (Claim No CV2008-04881) in National Insurance Property Development Co Ltd v. NH International (Carribean) Ltd that with respect to contemporary records Sub-Clause 20.1 FIDIC 1999, unlike clause 53.4 FIDIC 1987 in the Falklands case, does not specifically require a verification of the claim by contemporary records. With respect to contemporary records all clause 20.1 requires is that the contractor keep and have available for inspection by the Engineer these records. As per the Court the clause, is clear. A failure by a contractor to keep such records does not prevent recovery on the claim but is to be taken into account in its assessment insofar as it may have prejudiced or prevented a proper investigation of the claim. Hence the Court found that on a true construction of Sub-Clause 20.1 where there are no contemporary records the claim does not fail. Once having approved or disapproved a claim the Engineer shall attempt to reach an amicable settlement. If he fails to reach an agreement he is obliged and entitled to determine the claim. Any determination issued by the Engineer will be binding on the parties until revised by DAB or arbitration. Any agreement or determination must be notified to the parties. It is suggested that any settlement which failed to become notified according to Sub-clause 3.5 is not yet valid, even though the settlement was signed. Otherwise the danger arises that the Engineer will have no knowledge about the settlement. Moreover the notification requirement ensures that the day of validity of the settlement can be clearly identified. Each party shall give effect to each agreement or determination unless and until revised under Clause 20. Thus the date from which any agreement is binding must be clear. The new FIDIC Gold Book has slightly changed the aforementioned claim management framework. Under a Gold Book a Contractor will not only give notice of a claim within 28 days after becoming aware of the relevant event or circumstance but also give particulars within 42 days in order to prevent the claim from becoming lapsed. Employers claims are now covered by Sub-Clause 20.2 and no longer by Sub-Clause 2.5. Also any dermination by the Employers Representative (who replaces the former Engineer) shall be followed by a notice of dissatisfaction in order to safeguard the way to the Dispute Adjudication Board. Anyway, if the Contractor considers himself to be dissatisfied with any Engineers determination he may refer a dispute to the Dispute Adjudication Board (DAB). The DAB has power to open up and review any determination made by the Engineer. It has been held by the High Court of Dehli and New Dehli that under a FIDIC Contract the dispute resolution procedure stipulated therein is binding on the parties and the parties have to resort to that procedure. In other works, the Court may ask to do what has not been done. A court must first ensure that the remedies

http://www.dr-hoek.de/EN/beitrag.asp?t=FIDIC-Claim-Management

6/25/2011

Law_Information:International Trade Law:FIDIC Claim Management

Page 5 of 6

provided for in the Contract itself are exhausted (M/S SRI SAI EARTH WORKS PVT LTD v. ITALIAN THAI DEV. PUBLIC CO LTD, January 12, 2009 relying on a previous decision of the Supreme Court of India in the case of Northern Railway Administration v. Patel Engineering Company Ltd., 2008 (11) Scale 500 ). This position seems to be in line with published ICC awards (see below). The further question which arises is, whether a party who obtained a "final and binding" decision from the DAB, which the other party fails to comply with, can refer such failure to arbitration (ICC cases No. 7910 [1996] and No. 3970 [1983]) in order to enforce the DAB decision? According to Sub-Clause 20.7 the failure to comply with a DAB decision may be referred to arbitration. Thus where one party had obtained a favorable decision from the DAB which the other party had not contested and which, therefore, became "final and binding, the failure itself may be referred to arbitration. However, what does that mean? Could the aggrieved party refer such failure to arbitration in order to obtain an arbitral award in respect of such decision which could be enforced under the New York 1958 Convention on the Recognition and Enforcement of Foreign Arbitral Awards? The ICC award in case No. 7910 [1996] addressed this issue which became a dispute under FIDIC, 4th edition 1987. The arbitral court concluded that, where the claimant had submitted disputes to the Engineer under Clause 67 (FIDIC 4th edition 1987) and obtained decisions from the Engineer (who was a that time a quasi arbitrator) which had become final and binding because they was no notice of dissatisfaction by the defendant in due time, the arbitral court lacked jurisdiction with respect to such matters. Therefore the claimant's only remaining right of recourse was to seek to enforce the DAB or Engineer decision before the courts in the defendant's country. This is not a satisfying result because the enforceability of a DAB decision is subject to the governing law. Thus, as a matter of fact even final and binding DAB decisions will often be unenforceable, in particular in countries where the feature of summary proceedings is not known. Hence the solution which was submitted in the earlier ICC case No. 3790 of 1983 (110 Clunet (1983), 910 et seq.) was welcomed. In that case the tribunal had to decide on a dispute between a Libyan and a French contractor which arose out of contract for public works based on FIDIC 4th edition 1987. The Engineer had issued certain payment certificates. However, the Employer did not pay on these certificates. He purported that the work for which the Engineer had issued the certificates were defective and he declared dissatisfaction with the Engineers certificates. However, he did not refer the dispute to the Engineer (as provided for by the contract) but directly to arbitration. The contractor on the other hand claimed for outstanding payments and submitted the dispute to ICC arbitration. The arbitral tribunal made an award in favour of the contractor. It decided that the employer was bound to pay on the certificate issued by the Engineer. Accordingly the ICC court awarded the contractor the amount of money claimed based on the final and binding Engineers decision. The ICC award in the case No. 7910 [1996] is in line with this decision. Anyway, the issue raised by cases No. 7910 and 3970 was resolved by the FIDIC Conditions, 1st edition 1999. Sub-Clause 20.7 therein expressly provides that, where a decision has become final and binding, either

http://www.dr-hoek.de/EN/beitrag.asp?t=FIDIC-Claim-Management

6/25/2011

Law_Information:International Trade Law:FIDIC Claim Management

Page 6 of 6

party may, if the other party fails to comply with such decision, and without prejudice to any other rights it may have, refer the failure itself to arbitration. Consequently, a party can obtain an arbitral award in respect of such a decision, however subject to one qualification. According to Sub-Clause 20.1 any amounts shall be included in Payment Certificates. Accordingly it is submitted that the arbitral court should not award the amount of money claimed but impose the obligation on the Engineer to include the amount in the next Payment Certificate. Only if evidence can be shown that the Engineer is not willing to comply with Sub-Clause 20.1 the arbitral court may award the amount of money. The reason for this is that the Engineer shall certify the amounts which he believes being due (Sub-Clause 14.6). According to Sub-Clause 14.3 deductions for retention, calculated by applying the percentage of retention stated in Appendix to Tender to the Contract Price, shall be made. For more detailed information about claims and claim management the new FIDIC Guide for Practitioners has been published. The authors are Aexel-Volkmar Jaeger and Dr. Gtz-Sebastian Hk.

LAW OFFICE Dr. Hk, Stieglmeier & Kollegen Contact: Advocate Dr.Gtz-Sebastian Hk Eschenallee 22, 14050 Berlin Tel.: 00 49 (0) 30 3000 760-0 Fax: 00 49 (0) 30 3000 760 33 e-mail: kanzlei@dr-hoek.de

http://www.dr-hoek.de/EN/beitrag.asp?t=FIDIC-Claim-Management

6/25/2011

You might also like