You are on page 1of 4

PROJECT :

CILEGON SAG PROJECT : DBT &


HOPPER DAILY PROGRESS REPORT

Contractors:
WEEK :W75 TIME : 08:00 - 21:00 WIB

DATE : Monday, June 12th, 2023 No. 85.16.457

MANPOWER ACTIVITIES START FINISH STATUS REMARK


MANAGEMENT QTY 1. Construction Stage 1
1 Project Manager - a. Hopper :
2 Deputi PM - - Commissioning 3/18/2023 postponed
3 Site Manager -
4 Construction Manager 1 2. Stage 3 (ILHT)
5 Project Control - - Commissioning 3/18/2023 postponed
6 Document Control 1
7 General Affair 1 2. Stage 4 (Bucket Elevator)
FIELD QTY - Commissioning 3/18/2023 postponed
1 HSE Officer -
2 Safetyman 1 3. Stage 5 (Chute)
3 HSE Coordinator - - Commissioning 3/18/2023 postponed
4 Supervisor Civil 1
5 Supervisor Mechanical 1 4. Stage 6 (Electrical)
6 Supervisor Electrical - a. Electrical
7 QC Mechanical 1 4/1/2023 Finish
8 Quality Control - 5. Forger Area
9 Operator TMC 10 Ton - Forger Foundation
10 Team Civil 4 survey check condition 6/12/2023 Continue
11 Helper 2
12 Scaffolder 2 Platform Forger
13 Rigger 1 survey check condition 6/12/2023 Continue
14 Electrician 2
15 Material Control 1 Roller Table
16 Warehouse - survey check condition 6/12/2023 Continue
17 Surveyor 2
18 Driver 1 6. Engineering desain ( to be concern )
19 Tim Rotary 5
20 Tim Electrical HKTM - 8. Chute DBT & J-Tube
21 Tim ZEE 4 5/5/2023 finish
Summary : 31
9. Forger Electrical
Install n Fit Up Support cable ladder 4/1/2023 postponed

10. Administration
11. others
- Housekeeping 1/28/2023 info
- Install Ball Catcher 5/19/2023 Postponed

METHODS
1 Survey using total station
2 Unloading material using TMC 8
3 Mob-demob material use mobile pick up
4 Erection bucket elevator using overhead crane extisting 10 Ton
5 Scaffolding for work at height
1 Utility car 3 unit TOOLS QTY MATERIAL QTY SAFETY ISSUE
2 1 Toolkit 5 set 1 Rebar 1 lot
3 2 Ladder 6 ea 2
4 3 Scaffolding 1 lot 3
5 4 Ratchet 4 Set 4
5 Total station 2 Set 5
6 Saw 2 unit
7 Grinder 3 unit
8 Drill machine 5 unit
9 Welding machine 5 unit
10 Drill impack 1 unit
11 Electrical tools set 2 set
12 Sump pump 1 set
13 Blower 2 set
Prepared By:
PT. Livia Andalan Indonesia Checked By: Approved By:
PT. Molycop Indonesia PT. Molycop Indonesia

PROJECT CONTROL
PROJECT SPV PROJECT MANAGER
CILEGON SAG PROJECT : DBT & HOPPER

DAILY PROGRESS REPORTS


Photo of Documentation

ZZ

6 Juli 2018

==================================================
==================================================
==================================================
==================================================
==================================================
==================================================
==================================================
=========================================

F
CILEGON SAG PROJECT : DBT & HOPPER

DAILY PROGRESS REPORTS


Photo of Documentation

6 Juli 2018

-
CILEGON SAG PROJECT : DBT & HOPPER

DAILY PROGRESS REPORTS

Photo of Documentation

6 Juli 2018 6 Juli 2018

Toolbox meeting Bore pile works area DBT

Pouring concrete Fabrication rebar

Clearing area hopper