You are on page 1of 9

Development and Qualification of a

New Wirelessly Controlled Retrofit Safety


Valve: An Alternative to Well Workover
That Enhances Well Safety and Maximizes
Production Uptime
B.P. Champion, SPE, Expro; G. Gandini, Eni E&P Division; and A. Gabbiani, AREP-Stogit

Summary Introduction
There are many examples of wells around the world today that are Tubing-retrievable SCSSVs are critical devices in achieving safe
shut in because of failure of surface-controlled subsurface safety well-flow management. These valves are designed to close in the
valves (SCSSVs). While these valves are generally very reliable, event of a catastrophic failure of the topside flow-control equipment.
the control line that runs to the surface in the annulus is susceptible The SCSSV is installed with the production tubing and connected to
to plugging by contaminants in the hydraulic control fluid and also surface, typically using a ¼-in. stainless-steel control line that runs
to corrosion, which causes leaks; both are outcomes that render the in the annulus from the valve through a wellhead exit to the surface
valve inoperable. The failure of the control line also means that the well-control/safety shutdown system. The valve is a fail-safe closed
contingency solution of installing a wireline-retrievable surface- device that is held in the open position by the surface application
controlled subsurface safety valve (WR-SCSSV) is not possible. of hydraulic pressure down the control line. If the pressure is bled
When a safety valve fails, the most common remedial solu- off because of an emergency-shutdown (ESD) event, then the valve
tion today involves installing a subsurface-controlled safety valve closes automatically and shuts off the well flow.
(SSCSV), such as an ambient valve or storm choke. While this If the control line becomes plugged or develops a leak, then it
solution is lower cost and more straightforward than performing a is no longer possible to operate the safety valve from surface. A
full rig-based well workover, it is not as safe. SSCSVs are directly related study by Eni concluded that 23% of their SCSSV failures
influenced by changing well-flow conditions, such as high flow are related to control-line issues. Remedial actions, which may
rates and low pressures, or by water slugs, and thus are notoriously include pumping sealants to stem a leak or trying to flush out
unpredictable in operation. Additionally, they are not controllable contaminants plugging the line, rarely result in long-term solu-
from surface and not fail-safe, which is undesirable from a well- tions. Because it may take a significant time to mobilize a rig to
control and safety standpoint. perform a full well workover, some operators are permitted to
By transmitting electromagnetic (EM) signals from surface to use an SSCSV as a temporary solution to minimize the period of
downhole, it is possible to control downhole hardware. A wire- deferred production before the well can be worked over.
lessly controlled safety valve has been developed that can be ret- Ambient valves function on the basis of pressure, while storm
rofitted into a well using conventional slickline intervention equip- chokes function on the basis of the velocity of the fluid flow and the
ment and procedures. Being controllable from surface and of a resulting differential pressure created across the valve. The mechani-
fail-safe closed design, this valve offers both functional and safety cal settings of the valve that define the performance envelope within
advantages over existing SSCSV solutions. This new valve also which the valve will remain open, or close in, are configured at
offers a retrofittable solution for wells having no hydraulic control surface before deployment. However, the environment of a flow-
line installed. In situations where a capillary string may need to be ing well is dynamic, with ever-changing flow conditions such as
installed for foam- or chemical-injection purposes, it also provides liquid slugs or ongoing pressure depletion, causing these valves
an opportunity to free up the hydraulic control line. to sometimes close in erratically and unpredictably. This dynamic
A prototype valve was subjected to qualification and functional- environment means that frequent well interventions may be required
ity testing in accordance with a modified International Organiza- to recover the SSCSV, adjust the settings, and then redeploy it, which
tion for Standardization (ISO) 10432 test procedure. This testing is inconvenient, costly, and results in deferred production. Of greater
was followed by installation in an onshore gas well for a 6-month concern would be if the tolerances on the valve configuration settings
trial that involved both flowing and injection phases. The valve cause the valve to fail to close in during an emergency event.
was cycled and inflow-tested regularly and performed reliably, Recognizing the limitations of the existing SSCSV solution and
consistently, and fully in accordance with specification throughout with the rapid advancements in wireless in-well communications
the trial period. technology that is already being applied routinely for reservoir-
This successful trial of a new wirelessly controlled safety valve monitoring purposes, an alternative, retrofittable, and surface-con-
marks the introduction of a more-controllable and -predictable trollable flow-control solution now exists.
alternative to an ambient valve or storm choke, minimizes deferred
production, and increases the well’s safety. Following the success- Introducing the Wireless Communications
ful onshore trial, the valve is now considered ready for wide-scale Technology
field application onshore, and at the time of writing this paper,
plans for performing a first trial on an offshore platform are well The underlying principle of the wireless technology used on this
advanced. project has been described previously by Champion (2006), and
some case histories where it has been applied for wireless reser-
voir monitoring have been documented by Champion et al. (2007,
2009) and by Quint et al. (2005, 2006).
Copyright © 2011 Society of Petroleum Engineers
In development for more than 15 years and entering the com-
This paper (SPE 130427) was accepted for presentation at the SPE/ICoTA Coiled Tubing mercialization phase approximately 5 years ago, the solution
and Well Intervention Conference, The Woodlands, TX, USA, 23–24 March 2010, and
revised for publication. Original manuscript received 19 January 2010. Revised manuscript
uses EM through-tubing communications. In the downhole flow-
received 30 June 2010. Paper peer approved 3 September 10. control application, successful communication relies on a path of

February 2011 SPE Production & Operations 111


Tool String Diagram

Fig.1—Downhole tool string and flow path through the valve.

continuous electrical conduction from the point of transmission at Once the system is commissioned, the valve is held open using
the surface to a receiver located at the downhole location. A modu- an electromechanical latch mechanism and by the repeated trans-
lated EM signal is applied to the well at surface, which then propa- mission of EM “stay open” commands from surface. Should these
gates through the completion metallurgy to the downhole location, commands stop being received by the valve, perhaps because of a
where it is detected and demodulated by a highly sensitive receiver power failure or some form of catastrophic event at surface, then
located within the downhole valve-control module. Though this the valve will close with assistance from a powerful spring after a
sounds simple in principle, careful planning is required in prepara- preconfigured timeout period has elapsed.
tion for an installation in practice because of electrical leakage of To ensure that operation and control of the valve is fully
the transmitted signal into the topside infrastructure, background integrated with the wellsite’s existing safety systems, the topside
noise considerations, and other environmental challenges. transmitter module has a flexible interface to allow connection
with the ESD system. In the event that a controlled well shut-in
The Retrofit Wireless Flow-Control System event is initiated by activating the surface ESD system, a “close”
The system comprises a topside controller/transmitter unit located command is transmitted to the downhole valve and the valve will
at surface, with the valve, receiver, and battery power-supply immediately commence the close-in sequence. Similarly, if there
modules located downhole. The valve is a fail-safe closed poppet- is a loss of battery power supply to the downhole valve module,
style device that can be suspended in an existing nipple profile or the valve will close in immediately. In the interests of maintaining
elsewhere in the well using an appropriate monobore suspension fail-safe functionality, there is no facility to lock the valve in the
packer. The poppet valve design and the presence of electronics open position or for it to self-equalize.
and battery packs below the valve mean that it is not a full-bore To reopen the valve, an overpressure reset is required from
device. The well flow is directed through flow ports on the side of surface along with a short commissioning sequence. The over-
the valve and then exits through the top of the module. pressure required to reopen the valve is 1,500 psi over the static

112 February 2011 SPE Production & Operations


Equalizing Assembly
The equalizing assembly is located between the lock and valve
modules and provides a flow path around the valve so that any
Lock pressure differential can be equalized during the valve-retrieval
adapter operation. During valve installation, the equalizing assembly is
typically run in the closed position, and during valve retrieval, a
prong is run on slickline to jar an internal sleeve off seat, which
opens the flow ports. This equalizes the pressure above and below
the valve, making it ready for retrieval from the well. Fig. 2 shows
the equalizing sub and the prong.

Valve Assembly
Fig. 3 shows simplified diagrams of the valve in closed, semiopen
Prong
(while resetting), and open positions. Typically, the valve is con-
veyed into the well in the closed position. The application of pres-
sure from surface forces a sleeve to move downward, pushing the
sealing poppet into the open position. The topside transmitter then
Equalizing sub sends “stay open” commands from surface to latch the poppet in the
open position. The surface overpressure is then bled off, allowing the
upper sleeve to retract and the well to be brought onto production.

Electronics and Power Module


The electronics and battery assembly contains a receiver to collect and
decode the EM signal being transmitted from surface and then uses
this to control the activation of the valve-latching mechanism (Fig.
4). Depending on the specific details of the operating environment,
the electronics module can be placed at well depths to approximately
2,000 ft in the well. The transmission range achievable onshore using
the EM-telemetry technology was validated in 2004 when a valve was
Fig. 2—Equalizing assembly and prong. activated successfully on several occasions at 3,000-ft depth during
an operator-sponsored technology trial in a test well in Aberdeen.
Offshore-platform in-well communication trials followed in 2006,
with trials performed in the North Sea for ConocoPhillips in Norway
pressure below the closed valve. When considering the design of and for Shell in the Netherlands. The results of the offshore-platform
the valve, a surface overpressure reset was considered to be the trials supported an achievable transmission range of approximately
preferred solution because there is no additional electrical energy 2,000 ft. The standard battery pack targets a 6-month duration, but
consumed to perform the reset operation. This ensures that the this can be extended to a duration of more than 12 months by the use
energy in the downhole battery power supply is conserved, which of additional cells inside an extended-length battery housing.
maximizes the in-hole operating duration between well interven-
tions for battery change out. Topside Equipment
The surface-equipment package transmits signals to the downhole
Downhole Components and Flow Path valve through the well completion. The surface package com-
The key downhole components comprise the lock mandrel, an prises two key elements—a master control unit/transmitter and a
equalizing assembly, the valve module, and the electronics and wellhead transformer. The master-control unit consists of a rack-
battery-power-supply modules. The flow path through the valve mountable module with proprietary hardware and software (Fig.
assembly is illustrated in Fig. 1. 5) that generates and transmits EM signals to the downhole valve

Safety-Valve Lock Mandrel

Poppet-Valve Assembly

EM-Activated Latch

EM Module

Closed Semiopen Open

Fig. 3—Valve-operation sequence.

February 2011 SPE Production & Operations 113


Fig. 4—Electronics and power module.

Fig. 5—The topside controller (offshore specification).

by means of the wellhead transformer. The master-control unit is


typically positioned in a control room or safe area and is interfaced
with the local ESD system to enable automated downhole valve
closure in the event of an ESD event.
The wellhead transformer (Fig. 6) provides the interface from
the master-control unit to the well in which the downhole valve
system is installed. The topside equipment is currently in the pro-
cess of being certified for compliance with the European ATEX
and the American underwriters laboratories regulations.
24 in.

Valve-Qualification Process
As part of the valve-qualification process, extensive testing was per-
formed before deploying the valve in a live well for the first time.
• Highly accelerated lifetime testing was performed to 125°C
and 20-G vibration.
• Extensive function testing of all component parts including
100 valve cycles during official recorded function and life-expec-
12 in. tancy testing, and in excess of a further 500 cycles throughout the
entire internal test process.
• The valve was pressure tested across the sealing face to 7,500
Fig. 6—The wellhead transformer (offshore specification). psi, which is 1.5 times the maximum working pressure.

114 February 2011 SPE Production & Operations


Safe Area Hazardous Area
ESD interface Power supply

Topside transmitter Wellhead/flowline


signal connection

Armored cable
Ground reference
anode

Valve module

7 Armored cable

Fig. 7—Site layout and key system components.

• The 4½-in. valve successfully completed flow-loop testing, The modifications/exceptions to the standard ISO test proce-
seeing a maximum pressure drop across the tool of 34 psi at a flow dure include
rate of 7 bbl/min, which is equivalent to 10,080 B/D. • Because of the functionality and control logic involved in the
• A full-system test was performed in an onshore test well. wireless valve-closing sequence, the maximum closure time for the
In the first quarter of 2008, the valve was sent to the USA for valve was in excess of the 15 seconds allowed by ISO.
further testing at the Flow Component Testing Facilities valve-test • The valve was not fully drifted because it has no through-bore.
laboratories at Southwest Research Institute (SwRI). Experimental However, it was drifted to the point of the known bore reduction.
safety-valve testing was performed in accordance with a modified ISO • Because the valve requires 1,500-psi pressure to be applied
10432 Class 1 test procedure, which is the ISO equivalent of American from above to open it, the unequalized opening test could not be
Petroleum Institute (API) 14A. The experimental test procedure fol- performed.
lowed the standard ISO procedure as closely as possible, given that • No hydraulic-control-line tests were possible because the
this new valve is fundamentally different from a standard SCSSV. system is controlled by wireless telemetry and not a hydraulic
control line.
• The functional testing of the valve in propane was not per-
formed, although the valve did undergo the propane soak. The main
purpose of the propane cycling is to remove grease and debris from
the valve. Because the valve successfully passed nitrogen testing,
the propane test was not considered important.
The poppet valve was designed with the aim of having zero
leak rate on closure. Shut-ins performed after gas-flow testing at
SwRI at rates of 22.5, 34.0, 11.9, and 23.1 MMscf/D registered
0.0-scf/min leak rates, thus verifying the valve design objectives.
This is an improvement on the allowable leak rate of 5 scf/min
detailed in ISO 10432 and therefore enhances well safety.
In December 2008, the valve that was to be used for the 6-
month extended in-well trial was subjected to detailed function
testing in accordance with the modified ISO 10432 procedure. The
testing was completed with zero leak rate observed, and the valve
was then shipped to Italy for installation in the well.

Six-Month Valve Trial in a Live Gas Well


The wireless valve was installed for a 6-month trial in Well San
Salvo 54. This is a gas-storage well in the Fiume Treste field
located onshore southern Italy and operated by Stogit, part of the
Eni group. Because San Salvo 54 is a gas-storage well, the valve
was able to be tested during both production and injection phases.
A site survey of the San Salvo wellsite location was conducted in
September 2008, resulting in the preparation of a detailed installa-
tion plan and identification of the necessary groundworks (Fig. 7).
The ground reference anode was buried in the ground near to
the cabin that contained the topside controller equipment, and a
Fig. 8—The ground reference anode. cable was run from the anode to the controller unit (Fig. 8).

February 2011 SPE Production & Operations 115


Fig. 10—The prototype topside controller/transmitter unit (on-
Fig. 9—EM Signal connection on the tree. shore specification).

A second cable was run from the topside controller/transmitter Specifications of the wireless valve deployed for the 6-month
to the wellhead where it was connected to the kill valve flange (Fig. trial are summarized in Table 1.
9). The prototype topside controller unit used during the onshore
trial in San Salvo 54 is shown in Fig. 10. This was interfaced with Installation-Phase Activities and Commissioning
the wellsite ESD system. The on-site installation work commenced in December 2008.
The tool string that was deployed in the well for the 6-month In preparation for the valve deployment, a scraper run was
trial is shown in Fig. 11. performed on slickline across the interval where the valve was

TABLE 1—PERFORMANCE SPECIFICATIONS OF THE WIRELESS VALVE


Parameter Value
Physical Parameters

Valve size To suit 4.5 in. 12.6# tubing nominal size for a 3.812 in. landing nipple
Maximum OD 3.60 in. (excluding lock no-go)
Length < 30 ft (excluding lock but including equalizing assembly)
Metallurgy and seals Suitable for sour service (to NACE MR0175 – 2003)

Operating Parameters

Pressure rating 5,000 psig (34.4 MPa)


Test pressure 7,500 psig (51.7 MPa)
Temperature range 0°C to 125°C (32°F to 257°F)
Maximum tensile load 75,000 lbf
Maximum compressive load 75,000 lbf
Mode of operation Fail-safe close
Time to close < 20 seconds in operating mode
< 40 seconds in fail-safe mode
Time to open Approximately 10 minutes
Flow performance in 4.5 in. 12.6# tubing Minimum 2.835 sq. i n. (based on equivalent 1.9 in. ID)
Pressure requirement to reset 1,500 psi above the static pressure below the closed in valve
Setting depth 0 to 2,000 ft, subject to well parameters
Deploym ent & retrievability W ir e l i n e s e t a n d r e t r i e v a b l e
Battery life expectancy Target 12 months
Q ualification Tested in accordance with a modified ISO 10432 class 1 test procedure

116 February 2011 SPE Production & Operations


Tool String Diagram

Outside
Length diameter
(m) (in.)
No-Go Seal Sub for 3.812 in. Bore

Equalizing Assembly

Valve Assembly

Valve and Telemetry Interface

EM Telemetry and Battery Section

EM Contact Centralizer

Bullnose

Total length = 5.668 m

Maximum outside
diameter = 3.860 in.

Tool-string weight = 125 kg

System shown with 6-month battery pack. 12-month pack would be 2 m longer.

Fig. 11—Tool string as conveyed in San Salvo 54.

to be set [approximately 20 to 35 m rotary kelly bushing (RKB)] A 15-minute inflow test with a tubinghead pressure (THP) of
to ensure that there would be good electrical contact between the 1,090 psi was performed. It confirmed that the valve seals and
valve and the tubing string. lock-mandrel packings were sealing correctly. The well remained
Next, a short survey was performed in the well to confirm the closed in overnight, and the next day it was confirmed that the
performance of the communication channel between the surface valve was still sealing correctly.
and downhole. This involved running a survey tool in the well After pressure testing the surface lines, the THP was increased
and transmitting a series of test signals using the surface transmit- to 3,000 psi by pumping nitrogen against the closed valve. The
ter, which were then recorded downhole by the survey tool. On EM “stay open” signal transmission was then activated and after
retrieval to surface, the survey logs were downloaded from the tool approximately 10 minutes, the THP was bled down slowly to open
memory and examination of the log data verified that there was the valve. With the THP at 1,500 psi, a pressure spike provided a
suitable signal strength being received downhole at the valve-set- good indication that the valve was open. The well was then flowed to
ting depth to ensure robust communications between the topside the flare for approximately 5 minutes to confirm that the valve was
transmitter and the valve. open and the status indication was checked with the control room.
Following the communication-channel survey, the wireline tool An ESD event was then initiated by pushing the “close” button
string (Fig. 11), which comprises a lock mandrel, equalizing sub, on the topside controller, which transmitted a “close” command,
valve module (Fig. 12), electronics, battery section, and electrical- and the valve was seen to close in less than 20 seconds. With the
contact centralizer, was run in hole. With a tool-string weight of THP bled off to zero psi, a 15-minute inflow test was conducted
approximately 350 lbm, the lock mandrel was jarred into the land- with no leak detected at the valve.
ing nipple profile located approximately 14 m below the first flange The valve was then opened again by repeating the previous
at 24 m RKB. A pull test was performed to 450 lbm to ensure that opening sequence, and the well flowed to flare for a short period.
the lock was set, and then the running tool was disengaged with a The transmitter “stop” button was then pushed on the topside trans-
jar-up action and recovered to surface. mitter to simulate a loss-of-power situation, and the valve was seen

February 2011 SPE Production & Operations 117


7. Bleed off the overpressure and return the well to produc-
tion/injection.
All of the monthly valve cycling tests were completed success-
fully, with zero leakage observed during any of the shut-ins.
It should be noted that between December 2008 and March
2009, the well was on production at rates up to 500 000 std m3/d,
and between April 2009 and June 2009, it was on injection at rates
up to 300 000 std m3/d.
In addition to the scheduled monthly closures, three unplanned
closures occurred because of human error activating the ESD sys-
tem. These closures all occurred during shut-in periods.
In June 2009, a further inflow test was completed successfully
before conducting a slam test on the valve. The slam test involved
using the wireless valve as the sole means to close in the flowing well
and aimed to subject the valve to the maximum possible degree of
stress. With the well flowing at a stabilized rate of approximately 49
000 std m3/d the valve was closed in by transmitting a “close” com-
mand from surface. By monitoring the falloff in THP, the closure time
for the slam test was assessed to be approximately 20 seconds.
The slam test was followed by a further flow period and then a
final valve closure with inflow test to verify the valve performance
after the slam test. Both the slam test and the final inflow test were
successful, with zero leak rate recorded. The mechanical design
of the poppet-valve closure mechanism results in the valve mod-
ule closing in a controlled manner and typically over a period of
less than 10 seconds. This controlled closure of the poppet valve
ensures that there is no significant mechanical shock suffered by
any components of the valve mechanism during a slam shut event.
In this respect, it is believed that the poppet-style valve design
represents a robust solution to withstand repeated slam tests.

Valve-Retrieval Phase
After equalizing the pressure across the valve, it was retrieved
from the well on slickline and recovered to surface for inspection.
Detailed post-job inspection of the valve concluded that it had
performed to specification, with only routine wear and tear being
observable in the mechanical assemblies.
Fig. 12— The wireless valve, showing flow ports closed, ready
for installation in San Salvo 54. Assessment of the condition of the 6-month-capacity battery
pack concluded that an additional 6- to 8-week duration was
available from the pack, which would have extended its actual
performance to closer to 8 months.
to close in less than 40 seconds. The THP was then bled off to zero,
and a further 15-minute inflow test was performed with no change Conclusions
in THP, confirming that the valve was closed and sealing with no • The Expro wirelessly operated safety valve successfully completed
measurable leak observable. The additional close-in time as com- experimental testing in accordance with a modified ISO 10432
pared to the ESD close results from the timeout value programmed Class 1 test procedure. The modified test procedure followed the
into the valve-logic process that is used in recognizing that this was standard ISO procedure as closely as possible, given that the valve
a genuine event. The time to close can potentially be reduced by is fundamentally different from a standard SCSSV.
varying the settings in the valve logic process. However, this will • The valve successfully completed a 6-month test in a gas well
likely result in a higher risk of false closure events. onshore southern Italy. Throughout periods of production and
The valve was then reopened and the well put on production at injection, the valve was inflow tested regularly and performed
approximately 200 000 std m3/d for 2 hours before being closed in reliably, consistently, and fully in accordance with specification.
and handed over to production. • The poppet-valve mechanical design, and its controlled rate of
closure, minimizes any mechanical stress on the valve compo-
Results of the Long-Term Valve Testing nents and is considered to represent a robust solution to repeated
After the installation phase was completed, further valve closure slam-test closures.
tests were performed on 13 January 2009, 17 February 2009, 17 • Zero leakage was observed during repeated gas-flow testing at
March 2009 (two tests performed), 21 April 2009 (two tests per- SwRI and also during the 6-month trial in an onshore gas well,
formed), and 12 May 2009 (two tests performed). which enhances well safety.
The standard procedure adopted for each test comprised • In situations where the tubing-retrievable SCSSV has failed, the
1. Monitor and record the flowing tubinghead pressure (FTHP) Expro wirelessly operated valve represents a retrofit solution that is
for 15 minutes. surface controllable and a more predictable alternative to SSCSVs.
2. Close the well in at the wellhead.
3. Monitor and record the shut-in tubinghead pressure (STHP) Acknowledgments
for 15 minutes. The authors wish to thank the management of ENI and Expro for
4. Close the valve by activating the topside controller. their permission to publish and present this work. Thanks also go
5. Bleed the STHP to zero, or to the flowline pressure, and to ENI and STOGIT for their support throughout the 6-month field
monitor and record the STHP for 15 minutes. trial. The authors also wish to thank Petrowell Ltd, developers of
6. Using nitrogen, pressurize the tubing to between 1,500 to the poppet valve assembly, and the Expro Wireless Well Solutions
2,000 psi above the STHP to reset the valve and commence the Team in Dorset, UK, for their significant contribution in making
EM-signal transmission from surface. this project happen.

118 February 2011 SPE Production & Operations


References Gas. Paper SPE 102745 presented at the SPE Annual Technical Confer-
Champion B.P., Strong, A., and Moodie, N. 2009. Mungo Platform: A ence and Exhibition, San Antonio, Texas, USA, 24–27 September. doi:
New Wireless Retrofit Solution to Restore Real Time BHP / BHT Data 10.2118/102745-MS.
After a Permanently Installed Monitoring System has Failed – A North
Sea Case History. Paper SPE 124100 presented at Offshore Europe,
Aberdeen, 8–11. doi: 10.2118/124100-MS. Brian Champion is general manager of Expro’s Wireless Well
Champion, B.P. 2006. A Novel Wireless Solution To Address Uncertainties Solutions Product Line, a business focused on developing and
commercializing novel solutions for wireless in-well monitor-
in Reservoir Connectivity. Paper SPE 102547 presented at the SPE
ing and control. Champion has more than 30 years of global
Annual Technical Conference and Exhibition, San Antonio, Texas, industry experience in new-product development, technical
USA, 24–27 September. doi: 10.2118/102547-MS. and operations management, and business development. He
Champion, B.P., Searle, I.R., and Pollard, R.K. 2007. Clair Field: Reducing holds degrees in geology and physics from the University
Uncertainty in Reservoir Connectivity During Reservoir Appraisal— of Sunderland, UK. An SPE member for 18 years, Champion
A First-Time Application of a New Wireless Pressure-Monitoring Technol- has authored five SPE papers. Gabriele Gandini is a comple-
ogy in an Abandoned Subsea Appraisal Well. Paper SPE 108435 presented tion and workover engineer for Eni’s Exploration and Production
at Offshore Europe, Aberdeen, 4–7 September. doi: 10.2118/108435-MS. Division. Currently assigned to Eni GSA (Groupement Sonatrach
Quint, E., Brake, C.B., Bickley, J., Johnston, B., and Huckabee, P. 2005. Agip) operations in Algeria, Gandini has a BS degree in electri-
cal engineering from the Politecnico Milano University. Andrea
From Liability to Cost Effective Data Gathering Opportunity. Paper
Gabbiani is a rigless well-intervention engineer for Stoccaggi
presented at the SPWLA 46th Annual Logging Symposium, New Gas Italia Spa focused on natural-gas storage. Gabbiani has a
Orleans, 26–29 June. technical degree in electronics engineering and has been in-
Quint, E., Singh, M., Huckabee, P., Brown, D., Brake, C.B., Bickley, J., volved in operations for well completion, workover, and rigless
and Johnston, B. 2006. 4D Pressure Pilot to Steer Well Spacing in Tight well interventions in Italy since 1988.

February 2011 SPE Production & Operations 119

You might also like