Professional Documents
Culture Documents
AEP 345 Reconductor Project Overview
AEP 345 Reconductor Project Overview
October 7, 2013
Energized 345kV Re-Conductor Project in South Texas
Archie D. Pugh, PE, PMP
American Electric Power
EEI Conference; October 7, 2013
On February 3, 2011, loading in the Lower Rio Grande Valley of South Texas hit an all-time high of 2,734MW
due to cold temperatures causing record loads. The high loading along with transmission import limitations and a
reduced generation supply due to forced and planned outages moved operators to manual load shedding to
prevent overload of the 345kV transmission system and potential cascading outages.
In September 2011, ERCOT recommended system improvements to address the problem, part of which included
the reconductoring two existing 345kV lines, 251 miles total, that generally run from the Corpus Christi area, south
to the lower Rio Grande Valley. Due to clearance constraints, this project was approved to be completed while
the lines remain in-service. The magnitude of this energized re-conductor project makes it the largest of its kind in
the world as well as the largest single installation of advanced conductor (ACCC). The project was projected to
cost $525M and would nearly double the ampacity of the two transmission lines.
AEP embarked upon a comprehensive line inspection program that assessed each structure, insulation, conductor
hardware and foundations to identify structure upgrades and enhancements prior to the reconductoring. Once
these upgrades are completed, the reconductoring is performed while the circuits remained energized. This
presentation will highlight all aspects of the project including the overall scope of work, inspection program and
energized reconductor process.
AEP Transmission Footprint
- 39,000 Miles of Transmission – Largest in the Nation
- Nearly 38,000MW of Generation
Process
Basically consists of installing a “D” phase on the edge of
right-of-way
Physically moving the outside phase to the “D” position.
Install New Conductor in the vacant position
Electrically move the next phase load to the new Conductor
Repeat until all phases done.
Conductor Selection
ACCC
Conductor
TITLE
...Provides Full Time Resource for
Project Duration
III. INSPECTION
Need for Inspection
Inspectio Inspection
n Program Continued
Replacements (6)
Edinburg Breaker
Lon Hill & North
Reconductor
Mobilization
Rio Hondo
Breaker
Start of
Outage
Outage
Outage
Outage
Outage
PROCUREMENT
LH - NE Delivery
LH - NE Delivery
LH - NS Delivery
A - RH Delivery
A - NS Delivery