Professional Documents
Culture Documents
Cameron - Layout - Rev A2
Cameron - Layout - Rev A2
Backfill with Soil 10" UPVC Overflor Pipe 2.00 mm HDPE Lining Excavate and
500 Backfill with Soil
500
Embeded 8" HDPE Pipe
2 2
Detail 'A'
NATURAL Earth 1 1
POND Detail 'A'
100
Overflow Pipe Pipe (2 nos)
200
ELEVATION
CONCRETE
HDPE Anchor Trench
POND
along the of perimeter pond
2.00 mm HDPE Lining New Sump 800 x 800
C
8" HDPE Pipe HDPE Anchor Trench 8" HDPE Overflow Pipe (2 Nos)
Existing Sump Existing UPVC Pipe
along the of perimeter pond Slope
HDPE Lining
7000
Existing Outlet
New Sump 800 x 800
Depth to Lowest Pipe Elevation
4. HDPE anchor trench must be excavated and construct along the perimeter of pond to secure the lining.
Concrete Pond
500 Please be noted HDPE piping materials will arrive at the site entry on 16/6/2023 (Friday)。