Professional Documents
Culture Documents
DSN No. 5
Wood Revision
Contractor Revison 0
Status Code 4
Date
Table of Content
1. Introduction
1.1 Objectives
1.2 Project Overview
1.3 Project Implementation Schedule
1.4 Name of the EMP Preparer
1.5 Term and definitions
2. Environmental Policy and Commitment
2.1 Project Environmental Objectives
2.2 Environmental Policy
2.3 Environmental Management System
2.4 Project HSE Management System
3. Environmental Requirement
3.1 EIA Approval Condition
3.2 Related Standard and regulations
3.3 Implementation of Pollution Prevention and Control
3.4 Project Environmental Contractual Requirement
4. Roles, Responsibilities and Competence
4.1 Roles and Responsibilities
4.2 Organisation Chart for Contractor
4.3 HSE Organisation
4.4 Operational Organisation Representative
4.5 Operational Site Representatives
4.6 Petron Environmental Comittee
5. Environmental Traning and Competency
5.1 Site Induction
5.2 Toolbox talks and poster campaign
5.3 Training
6. Environmental Aspect Impact
6.1 Summary of Environmental Impacts
6.2 Description of mitigation measures
7. Erosion and Sediment Control Plan
7.1 Qualification requirement for ESCP Management
8. Monitoring and Reporting Programme
9. Materials and Waste Management
9.1 Material and Chemical Storage
9.2 Non-scheduled waste
9.3 Scheduled waste
9.4 Management of gaseous emission
9.5 Noise management
10. Environmental Audit and Review
10.1 Management review and revision of the EMP
10.2 Audit
10.3 Project Environmental Auditing Plan
11. Environmental Emergency Response Plan
11.1 Introduction
11.2 Objectives
11.3 General ERP Guidelines
11.4 Policy on incident management
11.5 Emergency Scenarios
11.6 Spill response equipment and materials
11.7 Site emergency response plan
11.8 Environmental Emergency Training Exercise / Drill
Appendix 1: Project Layout
Appendix 2 : Project Implementation Schedule
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
1. Introduction
This document contains proposed Environmental Management Plan (EMP) for Marine Import
Facilities 2, Petron Refining and Marketing Bhd. This document outlines the requirements related to
EIA report and DOE Approval Condition. Any further conditions related to the project that DOE may
apply to this project will be incorporated and implemented in the management plan.
1.1 Objectives
EMP ensures environmental practices are adhered to during construction and commissioning phase.
This document is also a mechanism to identify the significant environmental aspects and the
effectiveness of the mitigation measures. The main objectives of the EMP are to:
a) Comply with the requirement by DOE and any other relevant laws, regulations and or guidelines
pertaining to the project activities.
b) EMP document will be part of the HSE Management Plan for the project
c) Early trigger to remediate the environmental non-conformance.
d) Establish and environmental monitoring and audit program that will be used as a guide on tracking
the environmental performance of the project implementation.
e) To comply with the DOE and all the relevant agencies requirement prior to the implementation of
the EMP.
This EMP document is prepared to be consistent and in line with the following documents.
a) Environmental Impact Assessment Report (EIA) for Proposed Marine Import Facilities 2, Petron
Malaysia Refining and Marketing, Port Dickson Negeri Sembilan June 2018.
b) EIA Approval and Approval Conditions Proposed Marine Import Facilities 2, Petron Malaysia
Refining and Marketing, Port Dickson Negeri Sembilan June 2018. (ASNS(B) 35/3000/105/005 Jld ()
dated 16 July 2018)
c) Erosion and Sediment Control Plan (ESCP) for Proposed Marine Import Facilities 2, Petron
Malaysia Refining and Marketing, Port Dickson, Negeri Sembilan.
d) Petron Environmental Management Plan for Proposed Marine Import Facilities 2, Petron Malaysia
Refining and Marketing, Port Dickson Negeri Sembilan.
The acronyms used in this document have the meaning defined below:
EMP Environmental Management Plan
ESCP Erosion and Sediment Control Plan
EIA Environmental Impact Assessment
DOE Department of Environment (Malaysia)
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
During the construction and commissioning phase, CONTRACTOR is responsible to support all
contractual environmental requirements related to the scope of work and develop our own HSSE Plan
(as a minimum)
CONTRACTOR w il l implement the environmental protection measures re l at e d to project
as specified in the EIA Report and the Approval Conditions issued by DOE letter
reference: ASNS(B)35/300/105/005 dated 16 July 2018
In addition to the above, appropriate a n d adequate emergency response plan organisation and
facilities I equipment to mitigate the impact of any environmental incident will also be put in
place and to fully comply with the Site Emergency Response Plan.
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
An effective Project-wide HSSE management system has been established for this
Project which has the followIng key elements, refer to the document Project HSSE Plan,
doc No T.2417-GEN-S-004
The purpose of the HSSE plan is to outline the methodology in which the Health, Safety
and Environment (HSE) aspect of the PROJECT will be planned, administered, monitored
to ensure that the HSE objectives of the PROJECT are successfully accomplished.
In addition to the corporate policy a n d strategic objective , HSSEMS a l s o ensures the
followings:
a) Organization including responsibilities, resources, training, competency, standards
and document management;
b) Planning & Procedure including asset integrity, work instructions, management of
change contingency and emergency response planning;
c) Implementation & Monitoring including work activities, record, noncompliance and
corrective action, incident report and follow up; and
d) Auditing & Management Review.
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
3. Environmental Requirements
The EIA Approval Conditions related to this project are shown in the following (Malay Version)
version)
Sesalinan pelan susunatur yang diluluskan oleh Majlis Perbandaran Port Dickson
hendaklah dikemukakan kepada Jabatan Alam Sekitar Negeri Sembilan dalam tempoh 2
minggu dari tarikh ianya diluluskan.
7 Pelan Kawalan Hakisan Tanah dan Sedimen (Erosion and Sedimentation Control Plan -
ESCP) hendaklah disediakan sebagaimana yang ditetapkan dalam Guideline for Erosion
and Sediment Control in Malaysia October 2010 yang diterbitkan oleh Jabatan Pengairan
dan Saliran (JPS), Kementerian Sumber Asli dan Alam
8 Dua (2) salinan dokumen ESCP ini hendaklah dikemukakan kepada Jabatan Alam Sekitar
(JAS) Negeri Sembilan dalam tempoh dua (2) minggu selepas diperakui atau disahkan
oleh JPS. Pelan ESCP ini hendaklah sentiasa dikemaskini mengikut kemajuan
pelaksanaan projek dan dipamerkan di tapak projek bagi tujuan pemeriksaan JAS.
9 Semua langkah kawalan hakisan tanah dan sedimen hendaklah dilaksanakan seperti di
dalam lukisan ESCP yang tefah disahkan oleh Jurutera Bertauliah (Professional Engineer)
dan diperakui (endorsed) oleh Jabatan Pengairan dan Saliran.
10 Tolok hujan (rain gauge) hendaklah dipasang di satu kawasan yang terbuka di dalam
tapak projek.
11 Best Management Practices (BMPs) bagi langkah-Iangkah kawalan hakisan dan sedimen
hendaklah disenaraikan dan diperincikan di datam Bill of Quantities (BQ) semasa proses
tender projek serta diperincikan dalam EMP.
12 Pemasangan semua komponen BMPs sepertimana yang ditunjukkan di dalam Laporan
EIA bagi cadangan projek ini hendaklah dilaksanakan sepenuhnya oleh pemaju atau
kontraktor yang dilantik sebelum setiap fasa kerja tanah dimulakan.
13 Penyelenggaraan semua komponen BMPs hendaklah dilaksanakan secara berkala
mengikut jadual yang disediakan oleh pihak pemaju. Rekod penyelenggaraan hendaklah
disediakan dan disimpan di tapak projek pada setiap masa untuk tujuan pemeriksaan.
14 Pemeriksaan terhadap semua komponen BMPs hendaklah dijalankan dalam tempoh 24
jam selepas catatan hujan adalah bersamaan atau melebihi 12.5 mm. Laporan
pemeriksaan ini hendaklah dikemukakan secara online sepertimana format di LAMPIRAN
3 dalam tempoh 24 jam selepas pemeriksaan dijalankan. Laporan bergambar bagi
tindakan pembaikan BMPs di mana perlu hendaklah dikemukakan dalam tempoh 7 hari
dari kejadian
15 Sebarang biomas yang terhasil daripada pembersihan tapak projek hendaklah digunakan
semula di tapak dengan kaedah mulching. Manakala biomas yang tidak dapat digunakan
sebagai mulching hendaklah diuruskan seperti cadangan pelupusan di dalam para 5.3.1.2
di muka surat 5-20, di dalam Laporan EIA.
16 Sebarang pembakaran terbuka sisa biomas di tapak projek adalah tidak dibenarkan sama
sekali.
17 Pelupusan tanah-tanih berlebihan (excess cut material) di luar tapak projek hendaklah
mendapat kelulusan daripada Pihak Berkuasa Tempatan.
18 Bagi kawalan hakisan (erosion control) yang berkesan perkara-perkara beikut hendaklah
dilaksanakan :-
i. Pemasangan struktur BMPs hendaklah dilaksanakan selari dengan pelaksanaan
aktiviti kerja tanah sepertimana yang dinyatakan di para 10;
ii. Kawasan di mana kerja-kerja tanah masih dilaksanakan hendaklah dibuat
penstabilan tanah sementara; dan
iii. Kawasan terdedah di mana kerja-kerja tanah telah selesai hendaklah ditutup
dalam tempoh 14 hari dari tarikh kerja tanah selesai.
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
38 Bunyi bising hendaklah dikawal supaya tidak melebihi paras yang ditetapkan di dalam
garispanduan Maximum Permissible Sound Level Leq by Receiving Land Use for Planning
and New Development, the Planning Guidelines for Environmental Noise Limits and
Control (DOE, 2004), Designated Mixed Development Area (Residential — Commercial).
39 Pengukuran bunyi bising hendaklah dijalankan seperti yang ditunjukkan di dalam Figure
6.24 Locations of Baseline Ambient Air Quality and Noise Level Measurement
Sampling Stations and Curent Boundary Air Quality and Noise Level Monitoring Stations di
muka surat 6-55 di dalam Laporan EIA bermula di peringkat kerja tanah dan pembinaan
pada setiap tiga (3) bulan sekali. Kekerapan dan lokasi percontohan hendaklah dirujuk
dan mendapat persetujuan Jabatan Alam Sekitar Negeri Sembilan.
40 Gegaran hendaklah dikawal supaya tidak melebihi paras 5 mm/s [paras gegaran
bergantung kepada kedudukan projek dan receiving landusel semasa peringkat
pembinaan dan operasi, berpandukan kepada "Annex A Schedule of Recommended
Vibration Limits" di dalam garispanduan "Planning Guidelines for Vibration Limits and
Control in the Environment" terbitan Jabatan Alam Sekitar, 2004. Pengukuran gegaran
hendaklah dijalankan bermula di peringkat kerja tanah dan pembinaan pada setiap tiga (3)
bulan sekali. Kekerapan dan lokasi percontohan hendaklah dirujuk dan mendapat
persetujuan Jabatan Alam Sekitar Negeri Sembilan.
41 Kerja-kerja menanam cerucuk hendaklah dengan cara yang tidak mendatangkan masalah
asap hitam, bunyi bising dan gegaran seperti kaedah hydraulic piling / bore piling atau
kaedah-kaedah lain yang lebih mesra alam. Kerja-kerja menanam cerucuk hanya
dihadkan bermula jam 8.00 pagi hingga 7.00 malam sahaja.
42 Sebarang pembinaan, pemasangan atau pengubahsuaian alat pembakaran bahanapi
(APB) atau alat kawalan pencemaran udara (AKP) atau janakuasa sedia tunggu (Genset)
hendaklah diberitahu secara bertulis kepada Jabatan Alam Sekitar Negeri Sembilan dalam
bentuk sebagaimana yang dinyatakan di dalam Peraturan 5, Peraturan-Peraturan Kualiti
Alam Sekeliling (Udara Bersih) 2014 dalam masa tiga puluh (30) hari sebelum kerja
pembinaan bermula.
43 Sebarang pembuangan atau pelepasan kumbahan ke perairan pedaiaman hendaklah
diberitahu secara bertulis kepada Jabatan Alam Sekitar Negeri Sembilan melalui borang di
Jadual Pertama dalam Peraturan-Peraturan Kualiti Alam Sekeliling (Kumbahan) 2009
dalam masa tiga puluh (30) hari sebelum kerja pembinaan bermula.
44 Semua bahan petroleum, bahan kimia dan sisa buangan terjadual hendaklah diletakkan
jauh daripada mana-mana alur air bagi mencegah pertumpahan ke dalamnya.
45 Benteng hendaklah dibina di sekeliling tangki simpanan bahan kimia dan bahan
petroleum. Benteng yang dibina hendaklah berupaya menampung sekurang-kurangnya
110°/0 kandungan tangki terbesar di dalam benteng berkenaan. Tapak tangki hendaklah
diperbuat daripada konkrit dan kemudahan untuk mengepam semula bahan yang tumpah
hendaklah disediakan.
46 Sebarang buangan terjadual sepertimana yang tersenarai di Jadual Pertama (Peraturan
2), Peraturan-Peraturan Kualiti Alam Sekeliling (Buangan Terjadual) 2005, P.U. (A) 158
hendaklah diurus dengan sempurna mengikut kaedah-kaedah yang ditetapkan di dalam
Peraturan tersebut. Buanganbuangan terjadual hendaklah dilupuskan, diolah atau
diperoleh kembali di premis yang dilesenkan oleh Jabatan Alam Sekitar.
47 Semua kemudahan penstoran bahan kimia, bahan petroleum dan buangan terjadual
hendaklah diletakkan jauh daripada alur air.
48 Sistem pengurusan sisa pepejal dan sisa biomas yang baik hendaklah disediakan (satu
tempat khas untuk penyimpanan sementara buangan pepejal mesti disediakan di dalam
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
tapak cadangan). Sisa pepejal dan sisa biomas hendaklah dilupuskan di tapak pelupusan
sisa pepejal yang diluluskan oleh Pihak Berkuasa Tempatan.
49 "Environmental Management Plan" (EMP) yang memperincikan semua tindakan yang
diambil bagi mematuhi syarat-syarat keluiusan Laporan EIA dan langkah-langkah kawalan
yang dicadangkan di dalam Laporan EIA hendaklah disediakan dan diluluskan sebelum
projek bermula. EMP ini hendaklah disediakan mengikut format di LAMPIRAN A dan
dikemukakan kepada Jabatan Alam Sekitar Negeri Sembilan untuk kelulusan dan
hendaklah dikaji semula dan diubahsuai dari semasa ke semasa mengikut keperluan.
Sebarang kerjakerja di tapak pembangunan tidak boleh dimulakan sehingga Laporan
EMP ini diluluskan oleh Jabatan Alam Sekitar Negeri Sembilan.
50 Sekiranya projek ini gagal disiapkan atau penamatan projek, maka pemulihan dari segi
keselamatan awam dan alam sekitar (impak udara, impak air, tanah tercemar dan
sebagainya) adalah menjadi tanggungjawab Pemaju Projek atau pihak yang
bertanggungjawab.
51 Pemaju projek hendaklah mengemukakan pemberitahuan secara bertulis kepada Jabatan
Alam Sekitar Negeri Sembilan dengan serta merta sebaik sahaja pihak Pengurusan
Pemaju Projek menetapkan untuk menamatkan projek ini samada di peringkat kerja
tanah, pembinaan atau operasi, yang mengandungi:-
i. Tarikh penutupan/penamatan projek; dan
ii. Komitmen daripada Pemaju Projek atau pihak yang bertanggungjawab
sepenuhnya ke atas pemulihan tapak projek dari segi keselamatan awam dan
alam sekitar dan untuk mengemukakan dan melaksanakan Pelan Penutupan
yang akan dikemukakan kepada Jabatan Alam Sekitar Negeri Sembilan sebelum
projek tamat sepenuhnya.
iii. Pelan Penutupan yang terperinci termasuklah kerja-kerja penstabilan tapak
projek, kerja-kerja pemulihan tanah tercemar, pembukaan alat-alat serta jentera-
jentera proses, kerja-kerja pembersihan tapak, pengawasan alam sekitar atau
apa-apa jua langkah pemulihan yang bersesuaian yang dicadangkan
hendaklah disediakan dan dikemukakan untuk kelulusan kepada Jabatan Alam
Sekitar Negeri Sembilan sebelum projek tamat sepenuhnya.
52 Audit Alam Sekeliling Pihak Ketiga di bawah Seksyen 33A, Akta Kualiti Alam Sekeliling
hendaklah dilaksanakan terhadap projek ini berpandukan kepada Environmental Audit
Guidance Manual, terbitan Jabatan Alam Sekitar oleh pihak ketiga iaitu Juru Audit yang
berdaftar dengan Jabatan Alam Sekitar dan segala kos audit alam sekeliling hendaklah
ditanggung oleh pemaju projek seperti berikut:-
i. Di peringkat awal sebelum kerja tanah dan pembinaan bermula. Kriteria
audit hendaklah merangkumi antara lainnya dokumen-dokumen seperti Laporan
EIA, Laporan EMP, ESCP dan kelulusankelulusan lain yang berkaitan serta
pemasangan langkahlangkah kawalan hakisan dan kelodakan;
ii. Di peringkat kerja tanah dan pembinaan setiap empat (4) bulan sekali atau
mengikut arahan Jabatan Alam Sekitar Negeri Sembilan, bermula dari tarikh mula
sehingga selesai kerja tanah dan pembinaan. (Juruaudit hendaklah mempunyai
sijil CESSWI -Certified Erosion, Sediment and Storm Water Inspector atau
kelayakan yang setara); dan
iii. Segala kos audit alam sekeliling hendaklah ditanggung oleh pemaju projek.
53 Laporan-laporan berikut hendakiah dikemukakan kepada Jabatan Alam Sekitar Negeri
Sembilan yang mengandungi:-
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
60 Pemaju projek hendaklah memaklumkan secara bertulis kepada Jabatan Alam Sekitar
Negeri Sembilan jika terdapat sebarang pertukaran hak milik atau pengurusan projek
dalam tempoh 30 hari dari tarikh pertukaran hak milik atau pengurusan. Sebarang
pertukaran hak milik atau pembahagian hak milik atau pengurusan hendaklah
memasukkan kehendak mematuhi syarat¬syarat kelulusan laporan EIA kepada pemilik
baru dalam transaksi jual-beli/pertukaran hak milik tersebut.
61 Pemaju projek hendaklah mematuhi arahan dan syarat-syarat tambahan yang dikenakan
dari semasa ke semasa oleh Ketua Pengarah Kualiti Alam Sekeliling atau wakilnya.
62 Good house-keeping rules hendaklah diamaikan dalam kawasan projek pada setiap
masa.
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
The main objective of the EMP is to comply with the relevant standards and regulations applicable
during the construction activity of project are shown below and should not be limited to the follwoings:
CONTRACTOR will keep a record of all documentation related to environmental matters on the
Project. The documents to be recorded include:
• Site procedures and plans;
• Copy of any correspondence between OWNER and/or its representatives, CONTRACTOR,
Subcontractors and/or Authorities;
• Copy of correspondence with local Suppliers or Vendors related to environmental management
(such as waste recycling / treatment companies);
• Reports of formal environmental meetings and reviews;
• Reports of environmental inspections and audits;
• Monitoring and measurement data or observations;
• Reports of environmental incidents/accidents;
• Follow-up status of environmental actions;
• Monthly reports to OWNER and/or its representative; and
• Bi-weekly KPI Report shall be submitted to Owner
• Copy of Safety Data Sheets (SDS).
The document Enviromental Management Plan, is to maximize the beneficial impacts of its activities
and the activities of the Subcontractors on environment, avoid or minimize adverse impacts, and
mitigate to acceptable levels. The mitigation measures will be taken to prevent oil and
chemical (paint, blasting materials, lubricant) contamination of soil, surface water and groundwater.
CONTRACTOR and Sub-contractors will follow all HSE /Environmental / Security requirements as
listed in the documents below:
a) Environmental Management Plan (Including LDP2M2 and M2)
b) Waste Management Procedure
c) Emergency Response Plan
d) Security Plan
Competent Environmental Officer required for this project, list as per below:
Name : Nurul Izzah Binti Ab Rahim
Position : Environmental Officer
Table 4.1: EMP Roles of Responsibility during Construction and Commissioning Stage
Parties Roles and Responsibility
Sub-Contractor Implement the actions as stipulated in the EMP
document
Implement the corrective measures as identified
during the
monitoring and audit exercise
Contractor Ensure the Sub-Contractor implements the actions as
stipulated in the EMP document
Communicate the identified non conformances and
ensure the Sub-Contractor Implement the corrective
measures as identified during the monitoring and audit
exercise
The following management stucture for MIF2 Project is established and the positions within this
structure and the specific roles and responsibilities of its personnel with regard to management of
HSSE for the project are identified.
Project Manager
Construction Manager
Ng Tuck Heng
Abdul Jalil
Project Manager ensures that all environmental protection issues and relevant responsibilities must
be treated as of vital importance by recognizing those responsibilities through a positive action to
control pollution, and to reduce the impact on the environment to As Low As Reasonably Practicable
(ALARP) level.
Project Manager is responsible for coordination all health, safety, security and environmental matters
related to CONTRACTOR and its subcontractors and the identification of the potential hazards
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
associated with the performance of work, including the preparation of the related safety,environmental
procedures and the monitoring / control of their implementation etc.
CONTRACTOR will define roles and responsibilities in the respective Plans, Procedures, job
descriptions, individual tasks and targets. CONTRACTOR will establish and maintain the resources
(people, equipment, materials, information and time) needed to comply with regulatory requirements
and laws. CONTRACTOR will ensure the HSE Organization has the capacity and capability to
deliver the Environmental Management Plan (EMP) and so:
Ensure sufficient and competent incumbents of environmental critical positions during construction
stage:
• Ensure sufficient environmental competent supervision of environmental critical activities
• Ensure the line management from worker up to and including the top management level is
competent and capable of recognizing work related environmental hazards, through ongoing
site safety training, and empowered to take adequate control and undertake mitigation
measures
• Provide regular feedback on environmental performance via weekly / monthly reports, notice
boards etc.
CONTRACTOR will ensure that any organization changes are carried out in line with the
requirements as below:
• Evaluate all changes for their impact before the personnel or organizational changes are
implemented
• Communicate all the relevant information relating to a change to the affected personnel
• Update all relevant documentation such as organization charts, position descriptions, on-call
lists, etc
• Verify that the transition period is properly administered, and any concerns raised have been
resolved before the change permanently takes place
CONTRACTOR specifies the HSE responsibilities of the organizational KEY PERSONNEL for the
MIF2 Project with minimum requirements as below:
Project Manager
1) Project Manager is delegated responsibility for ensuring that the CONTRACTOR’s team complies
with the requirements of this document, and has moral obligations for ensuring that employees and
Sub-Contractor are provided with a safe, secure and environmentally sound working environment.
CONTRACTOR personnel will do utmost to promote environment matters
2) Project Manager will ensure that adequate resources are provided for the MIF2 Project in terms of
personnel, support from the CONTRACTOR’s office in its local jurisdiction, advice and planning, and
any other identified aspects of the Project that may impact the overall environment program
3) Project Manager will ensure that environmental documentation is comprehensively prepared and
delivered to OWNER at appropriate time as specified by OWNER
4) Project Manager will chair CONTRACTOR’s monthly safety, Health & Environmental committee
meetings
5) Project Manager will participate in the HSE audits and inspection programs and ensure that
relevant personnel participate in HSE audit and inspection at the Project worksite.
6) Project Manager will support the “ZERO” incident and injury culture and ensure personnel’s
participation in HSE awareness training programme(s) and activities that include promoting safety at
Project worksite
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
CONTRACTOR specifies the HSE responsibilities of the site KEY PERSONNEL for the MIF2 Project
with minimum requirements as below:
The composition of the EPMC will be in accordance with law, and as minimum will include Project
Manager as the Chairman, Construction Manager and subcontractor manager as the member
The EPMC meeting will be held fortnightly however the frequency may be increased if deemed
necessary.
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
The contractor will have environmental staff trained to ensure contractor and all subcontractor
compliance with the EMP contractual and regulatory requirements. The contractor will maintain
training record, including attendance and specific course.
Each employee arriving at the worksite will be indoctrinated as to the site HSSE Rules in language
clearly understood by each employee, before commencing work.
The tool box talk about environment will be held concurrent with SHE daily toolbox. Toolbox talks are
short, daily discussions or presentations by supervisors to their employees. They generally last no
longer than 15 minutes or so. A toolbox talk is focused on one specific topic and addresses it in
simple terms. The environmental toolbox talks will be included but not limited the following contents:
• Spill Control
• Water Pollution Prevention (Fuel and Oil)
• Soil Protection
• Dust and Air
• Noise and Vibration
• Water Pollution Prevention (Silt)
• Cement
• Material Handling
• Archaeology
• Pumping and Over-pumping
• Washing Down Plant and Machinery
• Segregation of Waste
• Working on Previously Developed Land
Continued communication with employees is the key to getting environmental management message
across. Whilst there is always a need for more formal policies and procedures to ensure legislative
compliance, it is also a good act to bring fresh eye catching ways to get the key messages across. To
help with this, CONTRACTOR will introduce a poster campaign to remind employees of some key
environmental messages they should be mindful of.
a) Physical-chemical environment
• Air Quality;
• Surface water quality;
• Marine water quality;
• Noise level;
b) Biological Environment
• Marine life and ecology;
• River ecosystem;
• Flora and Fauna.
c) Human Environment
• Human health and safety;
• Economic activities;
• Social well-being.
As summary, the construction activities that will create significant impacts on the site environment as
it involves high volume of the wastes to be produced and a big numbers of construction vehicles. The
main environmental components that may be significantly affected are air quality of the area, the
water quality of the receiving water bodies, noise generation and safety issues to the nearby
communities. Various mitigating measures are proposed to be adopted among which are the
environmental protection engineering design based on BAT, efficient traffic management plan for
construction stage, wastes management and an effective environmental management plan.
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
ESCP must be prepared by OWNER before construction begins, ideally during the project planning
and design stages. Implementation of the ESCP begins when construction begins, typically before the
initial clearing and grading operations since these activities usually increase erosion potential on the
site.
All steps to control soil erosion and sedimentation must be implemented as in the drawings of the
ESCP which have been certified by Professional Engineer and endorsed by the Jabatan Pengairan
dan Saliran. Two (2) copies of the ESCP document have to be submitted to the DOE Negeri Sembilan
within two weeks after endorsement.
During construction, the ESCP should be referred to frequently and refined by the consultant and
CONTRACTOR as changes occur in construction operations, which have significant effects on the
potential of pollutants discharge.
The document ESCP shall be prepared and signed by a professional engineer who is CPESC
certified. CPESC stands for Certified Professional in Erosion and Sediment Control. After prepared
the document, ESCP (including the drawings) has to be endorsed by a Certified Professional in
Erosion and Sediment Control (CPESC), and then submit with endorsement of a competent person
with CPESC to OWNER
Construction Phase
ESCP is heavily involved in construction phase of a development. This involvement can be further
divided into construction operation stage, and construction completion stage.
During construction operation, CONTRACTOR is responsible for implementing the BMPs according to
the ESCP. Because site conditions will inevitably vary during construction, the ESCP should be
revised as necessary, with any changes highlighted on the ESCP copy maintained at the construction
site.
The inspection and maintenance plan (part of ESCP) will play a major role in ensuring all BMPs are
implemented as planned and that the overall ESCP is servicing the development at a satisfactory
level throughout the entire project.
g) All drainage ways, pond areas, and reserves are properly gazetted in the final site plan.
h) Standard Operation Procedure (SOP) or maintenance plan for storm water structures is
produced whenever deemed necessary by authorities.
The ESCP will be read with the engineering plans in compliance with approved EMP by DOE and
any other plan or written instructions that may be issued in relation to development at the subject
area.
Contractor will ensure that all erosion and sediment control works are unertaken as instructed in
this specification and constructed in accordance with the Manual Saliran Mesra Alam – MASMA
2ND Edition published by Jabatan Pengairan dan Saliran Malaysia.
All contractor will be informed of their responsibilities in minimising the potential for soil erosion
and pollution of downslope areas.
Site work will not start until the erosion and sediment control works outlined below are installed
and functional;
a) Entry and exit to the site will be confined to one stabilised location
b) Fencing will be used to restrict all vehicular movements to the stabilised site access.
c) Silt trap will be installed as per drawings in document Erosion and Sediment Control with a
low flow of earth bank.
d) Top soil if any will be stripped and stockpiled for later used in lanscaping the site.
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
a) to provide a database to facilitate the indification af any short of long term environmental
impacts of the development project
b) to provide and early indication that any of the environment control measures or practices are
failing to achieve the acceptable standards
c) to verify the extent or significance of the impact
d) to provide data to enble environmental audit of the construction and operation of the proposed
development
However in the project all environmental monitoring will be carride out by OWNER. Results will be
discussed with contractor and further follow up / improvement to be agreed.
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
Waste management is a fundamental part of the construction activities and needs to be carefully
organized and managed. CONTRACTOR will comply with the environmental standards and
regulatory requirement and identifies the best practical solutions to allocate and minimze waste
appropriately. CONTRATOR is allowed to position waste only at the selected dumping areas as
approved by local authorities
CONTRACTOR and our sub-contractors are fully responsible for the management of the solid waste
generated by their activities from the proper segregation and storage on site to the final disposal in
the designated approved facilities importation or exportation to malaysia and any kind of transfer
inside or outside the site.
CONTRACTOR and our sub-contactors are obliged to keep relevant disposal and transportation
records/licenses and other waste management documentation fully updated and they will be audited
by the client and auditor on regular basis.
a) Each waste stream will be inventorised and characterised in the waste inventory
b) Scheduled waste will be collected and reclaimed or given to a certified third party for further
processing in accordance with local regulations
Chemical of less toxic in nature will be selected and used based on information with safet data sheet.
Chemical prohibited by the owner only relate dcodes and protocols will not be used.
All incompatibles chemicals will be segregated following hazard class to ensure a proper storage, spill
prevention device (such as level measurement independent high level alarms, high level off and batch
metering) will be design for storage vessel tanks and chemical waste storage to protect soil and
groundwater from pollution. Secondary containment will also be design for spill prevention. The
embankment built will be able to to accomodate at least 110% of the largest tank content. Facilities for
pumping spillage will be provided to prevent chemicals entering drainage system.
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
Any chemical to be bring in the Project Site, must be review by Petron Industrial Hygiene following
Chemical Entry Assessment Procedure.
a) SDS for controlled chemicals is made available to any employee or contractors who deal with
it or may be affected by it
b) Prior to any controlled chemicals being usedd or distributed in the workplace, the manager or
suervisor in control of the workplace will ensure hat all employees or contractors have read
the SDS and understand the correct procedures for the safe use as well as the potential
health effects and safety precautions,
c) SDS will be stored in a location that is readily accessible to all eployees and contractor who
handle or may be exposed to controlled chemicals. In addtion SDS must be available and
readily acessible to emergency services and medical personnel when required.
d) No details on SDS can be altered or deleted.
All non-hazardous wastes generated during site preparation work will be collected, segregated and
disposed in accordance with the Project waste management philosophy.
All wastes will be tracked by CONTRACTOR up to temporary collection points and removal is by an
appointed Waste Sub-Contractor. The determination of the locations, frequency and the amount of
temporary collection points are in charge of Site EO.
CONTRACTOR will be responsible for making arrangement for transportation of nonhazardous waste
to disposal site approved by the local authority. It is the responsibility of CONTRACTOR to monitor
and ensure that the waste transported from his site reaches the approved destination.
Any excess soil (overburden) has to be collected and cannot be disposed out of Project Site without
client approval.
Domestic waste will be collected in the domestic waste station, designed by OWNER and then
transferred to a certified dumping area by site professional domestic waste sub-contractor. The
specific details including location, frequency and record will be conducted after sub-contractor
determination.
Debris and construction waste will be collected in an area designed by CONTRACTOR, within
FACILITY Battery Limits, and then transferred to appropriate, certified landfill, by transportation
organized by CONTRACTOR
CONTRACTOR will manage scheduled waste in accordance to the Environmental Quality (Scheduled
Waste) Regulation 2005.
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
CONTRACTOR will be responsible for making arrangement for transportation of scheduled waste to
approved disposal site. The transporting of waste will conform to the consignment note system
whereby the movement of waste is monitored until it reaches the approved destination. It is the
responsibility of CONTRACTOR to monitor and ensure that the waste transported from his site
reaches the approved destination.
CONTRACTOR are also responsible to inform the transport CONTRACTOR regarding the nature of
the waste and what actions to be taken during accidents to minimize damage to human life and the
environment. Schedule wastes transporters shall also be licensed by the Department of Environment.
No scheduled waste can be placed, deposit or disposed on land or into Malaysian water without
written approval of the Malaysian authorities. No waste storage area can be closed to water system,
drainage areas and ignition sources.
The different types of solid waste shall be segregated and bunded by distance, and be stored in
compatible containers in case of chemical reactions.
The way access to waste storage area shall be controlled and limited; also the aisle and
passageways shall be kept clean.
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
The solid waste storage area shall be kept clean of any debris and waste residues and free of
damages.
The warning boards and “No Smoking” boards shall be placed in each waste storage area with both
English and Malaysian languages.
The waste containers shall be kept closed unless loading/ unloading and removing waste. Also the
waste containers shall be managed to prevent rupture, leaks or damage, and the waste containers
shall be marked with contents and hazard labels in both English and Malaysian languages.
The details of waste generation tracking system shall be kept and maintained.
Before final waste disposal or treatment, wastes are stored temporary in a temporary storage area.
Before regrouping in the primary temporary storage areas, wastes are collected in secondary storage
areas.
In any case, CONTRACTOR will do any effort to reduce emissions to the environment by using well
maintained equipment and vehicles / lorries /excavators and identify practical ways to minimize the
engines emissions and dust produced during SITE’s preparation works.
Any installation of combustion equipment such as boiler, furnace, burner, thermal oxidizer, flare stack,
stand-by generators and chimney etc for the Project require prior Written Approval from DOE Negeri
Sembilan as required under the Environmental Quality Regulation (Clean Air) 1978,P.U.(A)/280/1978.
Open burning of plant residues or waste construction materials or others waste from project site is
strictly prohibited.
1) Exhaust Emissions
Exhaust emissions will be minimized by the careful selection of equipment, machinery and vehicles.
The use of environmental-friendly engines (e.g. catalytic converters with low-NOx emissions) and
products (e.g. low sulphur fuel) will be preferred.
Vehicles and combustion equipment will be well-maintained and periodically checked. A maintenance
program will be implemented on site for vehicles, heavy equipment and construction machinery.
2) Dust Generations
Site preparation works, vehicle movements and strong winds are likely to be the major causes of dust
generation. The following measures will be implemented at site:
uncovered conveyors) will be suspended, whenever possible, during adverse weather conditions (e.g.
strong wind). Dust generating activities will be located away from dust sensitive receptors.
CONTRACTOR will monitor own discharges, take appropriate preventive and corrective actions,
comply with the requirements of the EIA approval conditions and report results to Client
Environmental Coordinator
Any discharge of surface water from the project site to outside the project site boundary during
earthwork and construction period should not contain the parameter :
The monitoring of water quality at the final discharge point at the sedimentation pond for the
Suspended Solids, (SS) must be conducted once a month from the start of the earthwork till the
completion of the construction works.
For this project, Contractor will installed cabin toilet and portable toilet. Frequency of desludging will
be determine as needed. The record for desludging record shall be kept by Environmental officer.
9.4.3 Dewatering
The water extracted during excavation (dewatering) will be disposed of in accordance with local
regulations. Temporary drainage systems will be used where required in order to capture and control
the run-off. Appropriate methods for discharging waters that are generated from dewatering activities
during earth working or from any other activities will be discussed with Site EO prior to commencing
the excavation activities.
Water sourcing for hydro testing purposes should not adversely affect the water level or flow rate of a
natural water body, and the test water withdrawal rate (or volume) should not exceed 10 percent of
the stream flow (or volume) of the water source. Erosion control measures and fish-screening controls
should be implemented as necessary during water withdrawals at the intake locations.
The disposal alternatives for test waters following hydro testing include injection into a disposal well if
one is available or discharge to surface waters or land surface. If a disposal well is unavailable and
discharge to surface waters or land surface is necessary the following pollution prevention and control
measures will be considered:
• Reduce the need for chemicals by minimizing the time that test water remains in the equipment or
pipeline.
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
• If chemical use is necessary, carefully select chemical additives in terms of dose concentration,
toxicity, biodegradability, bioavailability, and bioaccumulation potential.
• Reduce the need for chemicals by minimizing the time that test water remains in the equipment or
pipeline.
• If chemical use is necessary, carefully select chemical additives in terms of dose concentration,
toxicity, biodegradability, bioavailability, and bioaccumulation potential.
• Conduct toxicity testing as necessary using recognized test methodologies. A holding pond may be
necessary to provide time for the toxicity of the water to decrease.
• Use the same hydro test water for multiple tests.
• Hydrostatic test water quality should be monitored before use and discharge and will be treated to
meet the discharge limits.
Prior to discharge of hydrostatic test water, contractor shall sample and test the wastewater to
accredited lab. Critical parameter shall be determine accordingly and agreed by both client
representatives, and contractor.
Noise and vibration impact of site activities on the surroundings and on the personnel working on site
will be minimized by implementing mitigation measures including:
Medical Waste will be collected and transported to licensed facilities by contractor, if any.
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
The quarterly review of the Environmental Management Plan by Environmental Officer is the
minimum. However, whenever there is a change in regulatory requirements, key personnel or major
change in CONTRACTOR’s activities then it is expected that the Environmental Management Plan
will be reviewed and revised as to keep them relevant to the scope of work in progress.
10.2 Audits
Owner will carry out environmental audit to ensure ‘ prevention of pollution ’ and ‘continual
improvement’as defined inside Environmental Impact Assessment Condition of Approval (EIA COA)
requirement.
The Amendments (1996) to the EQA 1974 requires environmental audit is made mandatory under
Section 33A of the EQA 1974 for projects with EIA approvals. The purpose of the environmental audit
is to ensure compliance with the EMP and EIA Conditions of Approval, to determine the
environmental management procedures are being followed and the recommended mitigation
measures and monitoring recommendations are being fully implemented. The EMP should include a
checklist for the environmental auditor to fill in while conducting audit on site.
The audit should include the review of documents/records, environmental monitoring reports,
complaints and correspondence by other authorities or nearby residents or receptors and a thorough
inspection of site activities.
The audit findings should be used to identify any weaknesses in the EMP for the purpose of updating
the EMP and to allow for environmental management improvement practice within the Project site.
During the Site Preparation Works phase, activities within the Project site should be audited by owner
appointed third party auditor on a four-monthly basis to check the effectiveness of the mitigating
measures and BMPs and the compliance to the MIF2 EIA COA.
Any non-compliance detected during the audit will be documented and acknowledged by the
CONTRACTOR and their sub-contractors. Following this, corrective as well as preventive actions
recommended should be initiated by the CONTRACTOR within the agreed time period and to be
rectified prior to the next audit exercise.
The environmental audit conducted by owner appointed third party auditor on a four monthly basis
and the finding will be submitted to DOE and discussed in the site HSSE meetings.
c) To ensure that all the recommended mitigation measures and monitoringprogram are fully
implemented.
Section 33A of the Environmental Quality Act 1974 stipulated the requirement for the Environmental
Audit.
The Environmental Auditing shall be carried out by competent and independent by third party who are
registered with DOE. Lead auditor shall also possess a Certified Erosion Sediment and Storm Water
Inspector (CESSWI) Certificate.
At the end of site auditing, the auditor shall issue an Audit Summary which shall consist of all of the
finding from the site audit activity. Auditing finding can be divided into 3 parts :
The sufficient and appropraiate evidence to demonstrate the particular regulation or requirement has
been complied with
ii) Observation
Issues of environmetnal concern were observed which did not strictly realte to the scope of the audit
or compliance. It can be considered as indicators of potential non-compliance or area where
environmental performance need to be improved.
iii) Non-compliance
Clear evidence has been collected to demonstrate the particular regulatory requirement has not been
complied with.
After auditing findings, CONTRACTOR shall submit the corrective action report to OWNER which
required for only non-compliances that have been determined during audit and it is not required for
findings categorized as ‘Observation’. CONTRACTOR shall resolve the ‘Observation’ finding to
ensure that it does not escalate to a ‘Non-compliance’ finding in the future. CONTRACTOR shall
submit corrective action report within 21 days after the audit. The audit report shall be submited within
14 days after audit.
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
13.1 Introduction
This chapter outlines the general framework of the Environmental Emergency Response Plan to
provide standard guidelines on handling any emergency incidents that may potentially occur during
the Project construction.
Emergency Response Plan for on-site and off-site must be prepared to face any unexpected
accidents and incidents. This ERP prepared to align with owner emergency response plan.
13.2 Objectives
Objective of having an ERP is to guide the project in a safe, timely, and effective response to
incidents that threaten the plant area and public health, safety, or welfare. It is also intended to
promote coordination among project owner, local, private public and state responders. It is can also to
be used for the training of involved personnel in improving the level of emergency preparedness.
The objectives of having an ERP are to ensure that immediate and appropriate actions are directed
towards any emergency which interrupts normal safe working conditions of the proposed activities so
that :
The ERP will be prepared for construction phases. ERP procedures will be developed in compliance
with all the applicable laws pertaining to the emergency response and management and as stated
under the “Occupational Safety and Health (Control of Industrial Major Accident Hazards) Regulations
1996, Regulation 18(1)” where manufacturers who has control of an industrial activity are required to
prepare and keep up to date and adequate on site emergency plan detailing how potential major
accidents are to be dealt with.
The followings are the general principles in the management of any unforeseen
incidents:
• Preserve life, health and safety of emergency responders, employees and the
public and minimize risks to the property
• Contain and / or control the release of pollutants
• Identify the cause of the incident and the source of environmental hazards
• Collect and preserve evidence
The CONTRACTOR will supply absorbent and barrier materials sufficient to contain and recover spills
that could potentially occur from the equipment with the largest volume of fuel and lubricant. These
materials may include, but are not limited to, drip pans, buckets, absorbent pads, containment booms,
straw bales, absorbent clay, sawdust, floor-drying agents, spill containment barriers, plastic sheeting,
skimmer pumps, covered holding tanks, and fire extinguishers.
The CONTRACTOR will make known to all construction personnel the yard and warehouse locations
of spill response equipment and materials and have them readily accessible during construction.
Measures to prevent spills will be incorporated into all aspects of the construction facilities: design,
work, maintenance and emergency preparedness. Design features include mainly containment (spill
palette, bund devices, and dike) of the chemicals storage on site to prevent pollution of the
environment. Personnel will need to be properly trained to understand routine and emergency
procedures and adhere to relevant codes of practice and regulations.
CONTRACTOR will take into account the following spill prevention measures:
• Regular inspection of any storage area to identify leakage due to poor condition of containers or
damage to containers during handling.
• Designated area for the maintenance of vehicles e.g. lorries, excavators and equipment.
• Regular maintenance of vehicles, e.g. lorries, excavators and equipment.
• Provision of spill response materials in chemicals storage areas.
• Spill containment material may be sawdust, clay absorbent, sorbent mats and booms, etc.
Spills of any petroleum products, chemicals or other hazardous materials will be immediately
contained, cleaned up and reported as per the Emergency Response Procedure for spills. Exposure
of personnel during SITE’s preparation activities will not be allowed over the limits defined inside the
Occupational Safety and Health Regulation, 2000 (Use and Standards of Exposure of Chemical
Hazards to Health).
All environmental incidents occurring at work places during construction of the project will be reported
immediately to OWNER and its representatives at site. CONTRACTOR and Subcontractors will
investigate these incidents timely and submit the investigation report.
CONTRACTOR will report and investigate any incident as well as providing a full incident report to
Project Manager on time.CONTRACTOR will be responsible for our sub-contractors to performing
their incident investigation and reporting appropriately as well as providing a comprehensive incident
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
report.
CONTRACTOR will have own stock of spill kits, which will be proportioned to our activities and will be
ready for use. Contractor will be responsible for preventing, cleaning up and reporting any spill
relevant activities.
Emergency response exercises allow responders to be familiar with the procedures, facilities and
systems incorporated during an actual emergency. It facilitates comprehensive assessment in the
knowledge of emergency management, command and control element and skill levels. The
interactions within multiple response teams allow the responders to enhance decision-making
capabilities and demonstrate individual and group skill abilities to response operations. The overall
capability to respond will be tested using one of the methods below:
a) Table Top Exercise
Provides a convenient method of introducing responder to possible scenarios, situations and
to discuss approaches in problem solving. This is an effective method to determine if current
policies and procedures are adequate to manage situations which may arise during an event.
b) Functional Exercise
Simulates an actual event and involve all Project Manager nominated or dedicated
responders. The exercise is designed to test the readiness on communications and facilities.
c) Full Scale Exercise
Involves an actual deployment of personnel and equipment. The participating OWNER and
the government authorities are activated during a full scale exercise depending on the level of
the simulated escalation.
Those members of staff are to have completed the relevant courses and have proved themselves,
through experience and exercises, to have the mental and physical attributes to act calmly and
quickly in an emergency situation. Individual competency in emergency response will be validated on
the basis of:
a) Job specification procedures
b) Employee assessment procedures
c) Assessment after drills and exercises
EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD
PROJECT nominated personnel will be trained in the use of spill clean-up equipment provided in spill
kits, located at various positions around the site. Supervisors will direct the clean-up in the event of a
spill occurred.