ID: 0502741
SUB.DATE: Feb.18.2016
BIT Page i
Wandesan Gethane
DECLARATION
I, Wandesan Gethane, hereby declare that this report is an original work of my own and is being
submitted partial fulfillment for internship during the last four months. I assure that the report
contains actual events and facts that was observed and performed during my internship practice
program. All the contents are my own and have not been submitted to any other
university/institute.
Signature:
Date: 18/2/2016
Signature: ________________
Date: 18/2/2016
BIT Page ii
Wandesan Gethane
ACKNOWLEDGEMENT
First of all I would like to thank GOD then my dearest family. I also want to thank Bahir-dar
university institute of technology and university linkage office for giving such useful internship
program to increase our knowledge on the site and office.
I would like to express my deepest gratitude to teachers in the Bahir-dar institute for taught me
course and give us an excellent advice on the class, my deepest appreciation to my mentor
yohanes mulu who show me the best way to work on the project and gives me the advice by
contact me through the internship time.
I am very thankful to yohanes who is the consultant in the project to give me the chance to work
on the company by accepting my internship request paper.
I would like to express my gratefulness to ato belay girma (project manager), ato bacha guteta
(site engineer), ato dagne mekuria (office engineer), and to all hosting company workers for your
kindness and help through the time of the internship period.
Finally I like to thank my best friends on the site for sharing knowledge and for giving me your
time.
EXECUTIVE SUMMARY
This report paper is written about the internship program which I was working for the last
months, to help me to know engineering projects their design implementation evaluation and
management in general.
The report divided into some chapters, about the background of my host company including its history,
and machinery and working achievements, my overall internship experience, my tasks I was executed to
work, the procedure I used while working in the company, the practical and theoretical knowledge I
gained including the recommendation and challenges I faced while working my task.
The contents of the report have been divided into chapters and sub chapters and the topics covered the
company background, my overall internship experience, the benefit I gained from the program, the
conclusion, recommendation and appendix.
BIT Page iv
Wandesan Gethane
BIT Page v
Wandesan Gethane
Table of Contents
Declaration ................................................................................................................................................ ii
Acknowledgement ................................................................................................................................... iii
Executive summary .................................................................................................................................. iv
List of tables and charts ............................................................................................................................ v
CHAPTER ONE ............................................................................................................................................... 1
1 BACKGROUND OF GUTEMA FIRISA CONSTRUCTION COMPANY ........................................................... 1
1.1 Brief history of the company .......................................................................................................... 1
1.2 Products and Services of the company ........................................................................................... 3
1.3 Its main customers or the end users of its product ........................................................................ 4
1.4Overall Organization and Work flow ............................................................................................... 4
Chapter two .................................................................................................................................................. 8
2 Over all internship experience ............................................................................................................... 8
2.1 How I get into the company? .......................................................................................................... 8
2.2 The section of the company I have been working .......................................................................... 8
2.3 THE WORK FLOW IN THE SECTION.................................................................................................. 9
2.4 Which work piece you have been executing? .............................................................................. 10
2.5 What procedure I have been using while performing my work task............................................ 15
2.6 How good I have been performing my work task ......................................................................... 37
2.7 What challenge I have been facing while performing my work task? .......................................... 37
Chapter three .............................................................................................................................................. 39
3 over all benefits I gained from the internship ..................................................................................... 39
3.1 Improving practical skills ............................................................................................................... 39
3.2 Upgrading theoretical understanding (knowledge) ...................................................................... 40
3.3 Improving interpersonal communication skill .............................................................................. 40
3.4 Improving my team playing skills .................................................................................................. 40
3.5 Improving leadership skill ............................................................................................................. 41
3.6 Understanding about work ethics related issues ......................................................................... 42
3.7 Entrepreneur ship skills................................................................................................................. 43
BIT Page vi
Wandesan Gethane
CHAPTER ONE
Gutema Firisa Construction Company is established in May 1995. When we compare with other
construction companies it shows a great growth and an appreciable quality standard, since its
journey has started before a few decades. The reason that I’m saying this is at when he started he
was grade 6th but now Gutema Firisa Construction Company licensed is 1st grade of Construction
Company. When this company started by using 80,000.00 (eighty thousand birr) working
EEPCO project no one expect that it can be at this stage or level.The Company uses the
combined knowledge and experience of personnel, from directors to skilled workers, for
consistent quality project delivery. The qualified, well-trained and committed workforce also
enables it to uphold project schedules, even under adverse circumstances. All the achievements
of the company have been made possible by the committed efforts of executives and qualified
personnel. The Company is highly increasing its manpower in all levels of responsibility and
professional practice pertaining to construction work. This has created a relaxed and easy
handling of a number of significant projects at a time.
The initiator and owner of Gutema Firisa Construction Company is Mr. Gutema Firisa.
Managing Director Mr. Gutema Firisa leads the company’s over all activities while the D/
Managing Director Engineer Dawit Tesema preside over the activities of the businesses.
BIT Page 1
Wandesan Gethane
The focus is always kept on the timely delivery of works and to highlighting any potential
criticality in design/production management/logistics as possible. The company believes success
originates from a pro-active mindset in dealing and tackling problems and in addressing them
timorously.
Its professional team members are educated to interact within the firm and with the clients
Management and Designers professionally. They make themselves fully aware, from the onset of
a project, of how the designer has conceived the works; promptly produce their findings and
comment any suggestion on possible best-value-for money alternatives, which would improve
the quality, durability and energy efficient of the works, reduce emission and be friendlier to the
environment.
To sum up,
BIT Page 2
Wandesan Gethane
Gutema Firisa Construction Company has a solid reputation for completing projects on time,
within budget and desired quality. It is currently executing infrastructure projects at various parts
of the country. From the companies profile stated some of them are listed below.
1.2.1 Building Construction
Major building products of the company include; Wollega university Gimbi campus library,
Kake (qaqe) TVET, Mettu Dormitory, Ayira health center, Warki health center, Karcha health
center, Gidami, Nunu,Darmu, Alemteferi, Najo, Begi, Dulli, and H/G wollega TVET.
1.2.2 Road and Bridge construction
Major road and bridge products of the company are Nunu gravel road -50 km, Illubabor gravel
road-6 km, Ilubabor bridge construction, Mettu gravel road and Mettu bridge construction.
Project title Project Employer Contract value
description
1 Nunu road project 50 km gravel road Ethiopian road 25,000,000.00
authority
⁴ Bishoftu city City Bishoftu city 100,000,000.00
administration building administration administration
project office
3 Gimbi building project Library Wollega university 30,000,000.00
4 Shambu building Library Wollega university 30,000,000.00
project
5 Mettu building project Dormitory Mettu university 60,000,000.00
6 Karcha building Health center Nation for nation 5,000,000.00
project
7 Kake (qaqe) TVTE school Oromia TVTE 26,000,000.00
8 Warki and others Health center Oromia health center 5,000,000.00
BIT Page 3
Wandesan Gethane
As we able to see above Gutema firisa Construction Company has many products but we see the
Bishoftu city administration office building end users, and the end users of this building are
Bishoftu city peoples which the building collect many offices that was distributed in the city so
the peoples can get all offices in one place, and the building also have 2 meeting halls so the
people of the city can meet in the hall without any long ride from their area.
At this time Gutema Firisa Construction Company is a well-structured and adequately staffed
organization capable of handling a number of projects. The company uses the combined
knowledge and experience of personnel, from directors to skilled workers, for consistent quality
project delivery. The qualified, well-trained and committed workforce also enables it to uphold
project schedules, even under adverse circumstances. All the achievements of the company have
been made possible by the dedicated efforts of executives and qualified personnel.
The Company is highly increasing its manpower in all levels of responsibility and professional
practice pertaining to construction work. This has created a relaxed and easy handling of a
number of significant projects at a time.
BIT Page 4
Wandesan Gethane
The Company’s senior management and the employees have solidified close working and social
relationships allowing for a working environment of mutual respect, dedication, and above all
the commitment to make a difference.
Next to the human factor, the most important element for any construction firm to carry out its
work efficiently is the availability of construction machineries, equipment and vehicles
compatible to the magnitude of projects at hand. In this regards, Gutema Firisa Construction
Company, has given due attention to the subject and acquired sufficient number of equipments
and vehicles. The Company currently owns the the following buildings and construction
machineries, big & small vehicles;
BIT Page 5
Wandesan Gethane
Vibrator 25
Dumper 4
Water Pump 4
Grinder 6
Generator Set 4
Wood Machine 3
Surveying Equipment 7
Total Amount of equipment & 116
Machineries
BIT Page 6
Wandesan Gethane
In general the company has flexible organization and work flows for each individual project.
General Manager
Purchaser
General Service
Office engineer Site engineer Auditors
Equipment &
General machinery adm.
Quantity Data Forman
surveyor collector
Carpenter Rebar
Forman Forman
BIT Page 7
Wandesan Gethane
Chapter two
Before I enjoyed this company I asked to join aser Construction Company but they doesn’t have
adequate place to accept me for the reason they accept much number of students before I asked
them. After that I asked to join sunshine construction privet limited company (plc) and they
accept me but the construction site is in addis-abeba and that is much far from my area because
of that I asked this construction company to join and they accept me.
I get into this company called Gutema firisa construction company by sending the letter which is
given by the bahir-dar university linkage office, soon the project manager ato belay accepted my
request kindly to work in the company for the next 4 months started from sep28-jan28 and am
glad to work on this company because the site found near to my family house and the project is
the beast construction project in the city also the company is well organized in which I can learn
a lot from experienced engineers and other staff members.
The section of the company I have been working was divided in to two sections which are site
and office work, and in the site I have been working is building and construction material
supervision as part of my work. I conducted supervision of footing, footing column, columns,
beams, and slab.
In addition to the site work I have worked out office work like
Preparing take off sheet
Data collection
Data preparation
Reading and checking schedules
BIT Page 8
Wandesan Gethane
BIT Page 9
Wandesan Gethane
BIT Page 10
Wandesan Gethane
As I entered at Gutema firisa construction company I was assigned to work on the site with the
site engineer ato bacha and I tried to cover all the basic work section which was related to civil
engineering, and the main works I was working on the site are site managing section and
problem solving skill, in the site many works undergoes within the site engineer and the site
engineer should manage every work and workers in the site, and while I was working on the
project the site engineer ato bacha show me how to manage things. Also in the site many
problems are arise due to poor work man ship, loose of interest in the work and be carless of the
BIT Page 11
Wandesan Gethane
As I entered to the company first they executing me on the site work but we all are decided to
work both site and office work side by side, after that I start work on the office, the works that I
was working on are
Data collection and report
Take off
All works that are done in the project are recorded by the data collector and brought to the office
engineer and the office engineer use the data to produce valuable information about
Amount of works performed
Amount of material used in work
Efficiency of machine and man power
The data collector and the office engineer use this table for their data collection and report
respectively.
BIT Page 12
Wandesan Gethane
LABOUR MATERIAL EQUIPMENT
Tr N r A Desc Des rat A
total duration
Executed Qty
Description
Description
ad o a mo ripti crip e mo
Duration
Duration
Unit rate
Total hr
Amount
e . t unt on tion unt
DATE
yes/no
Block
Unit
Unit
Qty
e
No.
Material cost Labor cost Equipment cost
worked
Type Unit Qty Rate Amount Trade Rate amount Type HR Rate amount
hrs
S
846,475.9
172,689.1
9,250.0
Material cost total Labor cost total Equipment cost Total
2.4.2.2 The takeoff shit calculation also one of the work that is executing in the office are
Take off for pit excavation
Take off for form work
Take off for concrete
Take off for rebar and
Take for ribbed block also calculated
Schedule for pit excavation, form work, concrete, and ribbed block are the same but schedule for
rebar is different from the others.
Timising Dimension Squaring Description
BIT Page 13
Wandesan Gethane
Dr. Loc Sha Dia. No. Elem Total leng Sub Total length (m)
No atio pe of ent no. of th
n bar bars Ø6 8 10 12 14 16 20 24
12 C1 20 6 28 168 4.02 752.64
Total length(m)
Unit Weight(kg/m) .22 .39 .617 .888 1. 1.5 2.467 3.5
2 5 20 79 52
Total weight(kg) 1851.4
Table 6 takeoff format for rebar
2.4.2.3 Scheduling
Schedule is a systematized program of the project in which it shows the sequential flow of work
daily, weekly and monthly schedule is prepared per week to run the construction property and
effectively.
BIT Page 14
Wandesan Gethane
2.5 What procedure I have been using while performing my work task
The procedure I have been using while performing my work task can be discussed both in site
and office work.
2.5.1Office work
The procedures I used to, while executing the office work was not that much difficult but, it’s
somehow bulky and sophisticated. While I was performing site work I developed inter personal
relation with the stuffs and supervising engineers so I have got some sort of information in how
to perform office works. Beside understanding and performing office works I become familiar
with working atmosphere of offices. While working on the office there are some office
disciplines like punctuality, responsibility, ethics, inter personal relationships, cooperation while
performing tasks, proper arrangement of your stuffs in order to make good and peaceful working
environment.
First before facing any work in the office the supervising engineer was provide the students
within the site how to be safe and execute the works. Then after he gave us small exercises and
train how to perform after that the assignment were provided to the students to solve in group
and individual. These assignments cheeked by the office engineer to know how much we were
capable of doing the tasks. After the assignment he let us to work on the project we have been
supervising to increase our knowledge and confidences.
The following are list of things I have been working and observing in the office
Preparation of take off sheet
Data collection and reporting
BIT Page 15
Wandesan Gethane
It is a chart used to determine the quantity of the particular item of work executed it needs a
personal skill of describing the item of work executed for one to understand easily .the take off
shit consists of columns and rows, and it can be prepared by using computer. Note that it can be
prepared by hand, manually.
Dr. Loc Sha Dia. No. Elem Total leng Sub Total length (m)
No atio pe of ent no. of th
n bar bars Ø6 8 10 12 14 16 20 24
12 C1 20 6 28 168 4.02 752.64
Total length(m)
Unit Weight(kg/m) .22 .39 .617 .888 1. 1.5 2.467 3.5
2 5 20 79 52
Total weight(kg) 1851.4
Here is a sample of take off sheet for concrete, form work, pit excavation
Timising Dimension Squaring Description
All works that are done in the project are recorded by the data collector and brought to the office
engineer and the office engineer use the data to produce valuable information about
Amount of works performed
Amount of material used in work
Efficiency of machine and man power
BIT Page 16
Wandesan Gethane
Material
Man power
Since there were different buildings construction site within the city I had a chance to visit and
supervise more than one building with different stage of progress, so I can certainly say that I
was so lucky and I would like to describe the site supervision work that I have been executed
plus how to execute them by classifying them of the items of work executed such as:-
Methodology and supervision of setting out
Methodology and supervision of earth work
Methodology and supervision of stone masonry work
Methodology and supervision of form work
Methodology and super vision of footing
Methodology and supervision of column and beam
Methodology and supervision of ribbed slab
Methodology and supervision of stair case
Methodology and supervision of lift
BIT Page 17
Wandesan Gethane
Is the process or operation of laying out engineering projects by placing peg(chekal) on the
site of works. Setting out is the opposite of leveling (i.e. data are transferred from plans to the
ground).
Methodology - setting out is performed in different sites through different techniques. For wide
construction sites with uneven landscape using survey level and other equipments is
recommended. But for small constructions setting out can be performed by using only water
level.
Supervision
The setting out is done correctly with proper measuring tape and accurate leveling
Instruments
All measurements to confirm the accuracy and correct locations of working areas are
properly set out.
The elevation reference point in accordance with the survey map and confirm
All bottom of trenches and floor levels are according to the elevations shown on the
drawings.
Any work related with excavation, backfill, cart way of surplus material and the others
which carried out in the site where the building/civil engineering project/ will be constructed is
known as earth work.
Excavation: - removal of soil from construction site to provide space to the building
(engineering project).
1. Site clearing: -
Is removal of top soil for the height not greater than 20cm.it is the first step in
earthwork? It includes removing grasses, bushes, and vegetables and any other unwanted
materials from the site…..
2. Bulk excavation:
BIT Page 18
Wandesan Gethane
Bulk means just huge. So bulk excavation means removal of huge amount of soil
From the site to fulfill the structural requirement. Bulk excavation can be ordered
For one or more of the following:-
Methodology: - excavation can be performed using man power (shovel & hoe) and Using
excavator for bulk excavation. Every excavation was done as per the design by providing the
required working space.
BIT Page 19
Wandesan Gethane
Back filling is the process of replacement of soil from site or selected material to the place
where it was excavated before for the purpose of placing structural member after it was placed.
Back filling performed can be performed on the side of footing pad and foundation column on
the sides of stone masonry and under hard core.
Compaction of soil is the process by which the soil particles are artificially rearranged and
packed together into a state of closer contact by mechanical means in order to decrease its
porosity and thereby increase its dry density this is usually achieved by expulsion of air.
BIT Page 20
Wandesan Gethane
The maximum layer of fill for one time compaction does not exceed 15cm the
BIT Page 21
Wandesan Gethane
2.5.2.4Form work
Form work is a temporary ancillary construction used as a mould for the structure .The
construction of form work involves considerable expenditure of time and material. Form woks
are classified as wooden, plywood, steel, combined wood-steel. Timber is the most common
material used for form work.
.Requirements of form work
A good form work should satisfy the following requirements
Should be cheap and suitable for re use several times
Should be practically water proof so that it does not absorb water from the
concrete
It should be strong enough to withstand all loads coming on it.
It should be stiff enough to that deflection is minimum
It should be as light as possible
The surface of the form work should be smooth and it should afford easy
Stripping
BIT Page 22
Wandesan Gethane
BIT Page 23
Wandesan Gethane
Supervision
Formwork is so constructed that it can be stripped from the hardened concrete easily.
The formwork must be strain enough to carry the load until the concrete is strong
enough to carry itself and burdened sufficiently.
The inside surface of form works shall, except for permanent form works, or unless
otherwise agreed by the engineer, are coated with a release agent.
Release agents do not come into contract with the reinforcement and anchorages,
and should not be visible on the finished works
Wooden form works for unexposed concrete surface, are executed of sawed boards
with sharp edges and of the same thickness.
Wooden formworks for exposed concrete surface are generally of tongued and
grooved boards of the same thickness and free from knots, holes, cracks and splits.
Before any concreting starts, the formwork has the right dimensions and is level and
straight.
Before any concreting starts, all irons are thoroughly cleaned out and free from boles
and dirt.
The top level of the formwork is at the same level as the top of the finished concrete.
All formwork is removed without any damage to the concrete during the striking.
After removal of the form work remedial treatment to surface of the broadened
concrete is carried out immediately without delay and period of removal should be in
accordance with the structural technical specification.
Where intended to re-use formwork it is thoroughly cleaned and made good to the
satisfaction of the engineer.
BIT Page 24
Wandesan Gethane
2.5.2.5 FOOTING
Footing is a part of substructure which transmits the weight of the superstructure to the
ground. In our case the building has isolated footings. There are 107 footings including 6 shear
walls. The size of footings differs based on the difference in the bearing capacity of the soil and
the loads on each footing.
BIT Page 25
Wandesan Gethane
a) Before casting
reinforcement diameter, length, spacing and anchorage length should be
Check as a design.
provision of spacer with the required dimension(50 mm for footings)
the quality of formwork (cleanliness, smoothens and treatment with release agent
for the surface of formwork )
check provision of distribution bar
b) During casting
the availability of enough man power and machineries
check the appropriate use of vibrators
check ratio of the mix
checking whether the concrete is dropped to the pad formwork appropriately.(2 m
maximum height)
c) After casting
check the time of frame for removal of form work(16 hrs)
check properly the period of curing up to 14 days at least three times a day
suggest period of backfill after curing at least 15 days
BIT Page 26
Wandesan Gethane
A. Before casting
B. During casting
C. After casting
BIT Page 27
Wandesan Gethane
A. Before casting
stirrup spacing should be checked .it depends on the design (but in our
case5cm from the floor and every 18cm up to the overlap end after that at
every 20cm)
reinforcement diameter and overlap length(40 times diameter of the
Reinforcement) should be checked
The quality of formwork (cleanliness, smoothens and treatment with release
agent for the surface of formwork) should be checked.
Sufficiency of rigidity to prevent disturbance due to pressure of concrete,
effect of vibrator and other load should also be checked.
provision of spacer with the required dimension
provision of opening for maintaining pouring height of concrete without
segregation
the vertical and the horizontal alignment of the columns should be checked
by any method approved by the engineer (here in our case with ligna and
tumbi )
Column height and spacing should be checked.
Here is a typical foundation column and the process of concrete casting.
B. During casting
BIT Page 28
Wandesan Gethane
C. After casting
check the time frame for the removal of formwork (16 hr)
Proper curing (14 days) at least three times in a day.
check if there is segregation
provide sack on the column body to hold water while curing
BIT Page 29
Wandesan Gethane
BIT Page 30
Wandesan Gethane
Column: It is used for carrying and transferring every loads coming from roofs, slabs and
beams to the foundation. There are different shapes of columns; however, at our project site
rectangular and circular shaped columns were used. As I noticed circular columns were not
reasonably incorporated for their greater load bearing, but they were situated on places where
partition walls do not exist and on spaces where offices and halls present, as they are
aesthetically pleasing than rectangular columns. Any building structure loads increase as we go
down to the ground and so bottom structural members are properly configured that they carry all
super structural loads above it and transfer safely to the foundation. Hence the sections of
columns in upper storey are reduced as they have to carry lesser loads. But center lines of
columns must coincide accurately for various columns of different storey. The steel
reinforcement from the column in the lower storey is bent such that they are accommodated in
the column of the top floor.
BIT Page 31
Wandesan Gethane
Both longitudinal bars and stirrups are provided according to their spacing
Spacers are tied with bars and then formwork is constructed for the member
Its verticality is checked with plumb bob
Concrete is poured into formwork and vibrated around rod reinforcement
Formworks are removed after expiry of their period and the concrete surface is
watered until it sufficiently cures
BIT Page 32
Wandesan Gethane
2.5.2.8 Slab:
Slab is a structural part of the building having plate shape and used to cover the distance between
beams and possibly columns. Generally slabs are constructed monolithically with beams and
concreted in one operation for the full depth. The top surface of the slab is kept rough to create a
proper bond with any type of floor finish desired. At our project site they incorporated two types
of slabs:-ribbed and solid slab.
1) Solid slab: it was constructed from a concrete quality C-25 and its reinforcement details
were the same to those of beams. The bottom reinforcement is continuous over the entire
span and top reinforcement is provided at the support section to take up the tensile forces.
The designed solid slabs were for two panels and they are the panels where meeting hall
water closets present. Since solid slabs have a greater concrete depth, they are meant for
their greater prevention of water percolation a part from its structural function.
Supporting systems constructed and formwork is laid with panels and checked
entirely for not being pierced
BIT Page 33
Wandesan Gethane
Reinforcements are provided according to their details and spacers are placed
between panels and reinforcement bars
All fixtures such as sanitary, electrical and water pipes are positioned and installed
according to their drawings
Concrete is casted properly while fulfilling its requirements
2) Ribbed slab: it is a type of one way slab which is giving considerable extra strength in
one direction. On our project site what is worth mentioning is the ribbed slab was not
what we know theoretically, instead it was constructed from the pre-cast type beams and
a concrete slab, topping, depth of 60mm.pre-cast type beams are manufactured off-site
intentionally based on the c/c spacing of beams. Generally ribs are formed or positioned
along edges parallel to the span of one-way slabs.
BIT Page 34
Wandesan Gethane
2.5.2.9Shear wall:
Is a reinforced concrete wall which is designed to bear load and used as a confining media. The
plan distribution of the wall should be such that the building is torsion, as well as flexural stiff.
The reinforcement for shear wall is provided in both directions that it can safely resist lateral and
vertical loads. And the reinforcements are extended from the foundation to the most top part of
the shear wall. At our project site shear walls were configured for the stair case to support
landing, at an elevated shaft as an enclosing media and to bear loads, and for the cabinet wall as
an enclosing media.
BIT Page 35
Wandesan Gethane
BIT Page 36
Wandesan Gethane
2.7 What challenge I have been facing while performing my work task?
In the last months I face most challenges on the site work in the site, in the office me and my
team mate are so good because of that there is no challenge that destruct our work but in the site
From the early beginning of work I cannot communicate with the labor and site
engineers by miss understand of work language.
While working column alignment the alignment of one column doesn’t feat with
other column.
While working in the meeting hall, the architectural drawing and the actual work
doesn’t feat.
While working ribbed slab placement in the 5th floor the lifting machine was broken.
I should work quantity survey which I did not learn it before on the class.
What measures I have taken in order to overcome these challenges
After a time all the communication in the site are solved by day to day communication
with each labor and site engineer.
Decide to bend the
bar 2 cm to align the
column.
BIT
Figure 15 column challenge Page 37
Wandesan Gethane
Decide to work the structural or actual working while leaving the architectural drawing
behind.
These problem solved by labor force but it cost extra amount of money.
The measure I take to prevent this problem, by making some friends which are learn
quantity survey before.
BIT Page 38
Wandesan Gethane
Chapter three
In this internship that means within these four months i observed what the outside
construction world looks like more than what i used to know when i was at school. At school I
was learned or take many theoretical lessons even difficult to understand theoretically. So in this
internship period I have got opportunity to solve these difficulties. Because those things which
were theoretically difficult to understand, were not that much hard to understand when I faced it
practically.
BIT Page 39
Wandesan Gethane
BIT Page 40
Wandesan Gethane
method but it is so much better to resolve problems or challenges with some other friends, by
sharing the challenge not only you get the answer to your problem also you increase your
communication skill and improve your knowledge. Being Good team players are willing to share
information, knowledge, and experience. They take the initiative to keep other team members
informed.
Much of the communication within teams takes place informally. Beyond discussion at
organized meetings, team members need to feel comfortable talking with one another and
passing along important news and information day-to-day. Good team players are active in this
informal sharing. They keep other team members in the loop with information and expertise that
helps get the job done and prevents surprises.
In construction project problem often arise with different reason , we have seen some
technical problem encountered during executing a particular item of work and design defaults at
this time they let us involved in the problem solving procedure and we also put our effort
proudly without any fear. There also dispute arises between the contractor and consultant but
they have solved problem easily this helped me to improve my team player skill.
In the past months I work all things with my friends especially in the office we do things
together also in the site.
BIT Page 41
Wandesan Gethane
BIT Page 42
Wandesan Gethane
e) Character:-those with a good work ethic often also posses generally strong character this
means they are self disciplined pushing themselves to complete work task instead of
requiring other to intervene they are also often very honest and trust worthy, as they view
this traits as befitting the high quality employees they seek to become to demonstrate
their strong character these workers embody these positive traits daily, likely
distinguishing themselves from the rest.
And this and some other characters are important for ethical work like
Punctuality
Accountability and transparency
Locality
Responsibility
Hard working
Risk taker
In the intern period I have understood the work ethics that all workers should follow and I
properly use them for the past 4 months accordingly.
BIT Page 43
Wandesan Gethane
BIT Page 44
Wandesan Gethane
Chapter four
4.1 conclusions
The internship program has been a help experience in exposing us to the real engineering work.
It gives me that what I wouldn’t get if I spent all the time learning in the university. Also this
internship program open an opportunity to think what way we should learn and what type of
knowledge should I have to gather before I leave the company. These days the technology of
construction industry has been improved. Consequently modern and new construction techniques
and material usage is in practice. This has greatly required the improvement of the work
methodology. As a result the supervision work shall also be improved. So it is clear that the
supervisor has a big role to improve the time quality and cost controlling in the construction
industry. To implement these parameters (time, cost and quality) the experience of the supervisor
shall be carefully determined by the consultant depending on the size and complexity of the
project.
This intern ship program also gives me skills like improving my communication skill, helps me
to improve my theoretical knowledge, gives me team playing skill with my friends, my
leadership skill and entrepreneur skill also increase and it upgrade my ability to be confident and
take risk in my professional carrier.
Generally the purpose of this Internship program was to introduce students with working
condition and mostly it helps students to grasp knowledge from practicing the theory which they
have been learning in the class. This program gave me good practical skills and made me
familiar to the outside real construction world. Most the theoretical things we been leaned got
illustrated here in this program, which develops more our confidence in the theoretical
knowledge.
BIT Page 45
Wandesan Gethane
4.2 recommendations
To my company
In the last four months I have got a chance to work on this company and the company is so good
on so much things and I cannot get much bad things I should recommend to the company but I
have some to tell:-
The wages of the workers is not enough compared to other construction companies and
other labor workers in the local area.
The company give less attention to the interns
Carless on the construction work of the daily labors
To my university
While working on the project for the past months i face some things that should be
recommended to the company like
We did not learn quantity survey before but in the past months we are working on
so the university should give some course before sending us to the intern.
The relationship between the students is weak.
BIT Page 46
Wandesan Gethane
Chapter five
5 REFERENCE
Notes from the site, diaries
From web site, http://www.thecontractor.org
Specification of the company, 2015, bacha guteta.
Company profile, from the company
Different handouts, RC, soil, communication skill.
BIT Page 47
Wandesan Gethane
Chapter six
6.1 APPENDIX
Standard Mixes for Ordinary Structural concrete per 50kg. Bag of Cement
BIT Page 48
Wandesan Gethane
Period of Removal
Props to slabs 14 “
Props to beams 21 “
BIT Page 49
Wandesan Gethane
BIT Page 50