Network Diagram
a. Bacalah buku teks Project Management: Achieving Competitive Advantage
karangan Pinto (2016) Chapter 9 halaman 296-322 tentang Project
Scheduling: Networks, Duration Estimation and Critical Path. Sebagai
tambahan anda juga bisa membaca slide deck tentang project scheduling dari
Binusmaya.
b. Kerjakanlah soal di bawah
i. Network Diagram
i. Network Diagram, Duration Estimates using PERT (3 Points
Estimates)
2501972335 – Justin Romero Susilo

JAWABAN PROJECT MANAGEMENT

total duration
for the project
is 18 days
1.

1C

J 18 18 0

Conclusion, activity have slack is C,D,E,G & I.


Kesimpulannya bahwa Brust activities ditunjukkan bagan A dan E,
dan merge activities ditunjukkan pada bagan H dan J

2. C. Critical path is B-C-E-G


C. Alternative paths is A-D-G, A,E,G dan B,F,G
2. D. Identity burst activity and merge activity is
- Burst activity is A,B
- Merge activity is E, G