Signal checking for interconnection trip signal GT-DCS

LIST Of Daily Activities


Yesterday 6/6/2023 Today 6/7/2023 Tomorrow 6/8/2023 REMARKS/LOCATION
Mechanical & Operation Mechanical & Operation Mechanical & Operation
1. Monitoring STG Flushing lube oil block 3
seal oil pump running test

2. Start CCW and air compressor block #3

3. Monitoring N2 presevation HRSG Block#3

4. Block#3 HRSG 3.3 CPH flushing

5. Support DCS for RFI HRSG 3.1

Electrical Electrical Electrical

1. Monitoring IPBD block 2 welding activity

2. Repair and functional test for ESOP feeder


block 3

3. Repair and functional test for MSOP Motor


A/B feeder block 3

I&C/DCS/TCS I&C/DCS/TCS I&C/DCS/TCS


1. Re-calibrated Feedwater LCV 30LCA90AA081
& 30LCA90AA082 and confirmed with CCR

2. Supporting DCS team for RFI logic function of


Diverter Damper 3.1

3. Supporting Operation team for installed three


way valve for generator seal oil panel at Block #3

4. Continue supporting TA of VMS for block #3

1 OF 2
5. Remove cable control and tubing of TCV CPH
inlet (31HAA80AA081) due to mech team want
to install gasket after that re-calibrated then
confirmed with CCR

6. Gtcs 3.1 - dcs loop check

7. Hrsg 3.1 rfi completed

8. Gtcs 3.2 oc mode fsnl run test with bypass


logic completed

2 OF 2